CN204940337U CN201520689856.4U CN201520689856U CN204940337U CN 204940337 U CN204940337 U CN 204940337U CN 201520689856 U CN201520689856 U CN 201520689856U CN 204940337 U CN204940337 U CN 204940337U
Authority
CN
China
Prior art keywords
piping lane
cambered surface
cambered
plate
brace summer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520689856.4U
Other languages
Chinese (zh)
Inventor
叶柃
朱鑫
牛琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonglin Xinzhou Bamboo Winding Development Co ltd
Original Assignee
Zhejiang Xinzhou Bamboo Based Composites Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xinzhou Bamboo Based Composites Technology Co Ltd filed Critical Zhejiang Xinzhou Bamboo Based Composites Technology Co Ltd
Priority to CN201520689856.4U priority Critical patent/CN204940337U/en
Application granted granted Critical
Publication of CN204940337U publication Critical patent/CN204940337U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The utility model discloses a kind of prefabricated bamboo compound piping lane, this piping lane is spliced by identical cambered plate, this cambered plate plate benging that is square becomes arc surfaced, the external surface of this cambered plate is by a depression cambered surface, one protrudes cambered surface, two curved ends and two side planes are formed, this depression cambered surface and this protrusion cambered surface lay respectively on two coaxial faces of cylinder, inner liner is comprised successively to this protrusion cambered surface by this depression cambered surface, deck and external protection coating, this inner liner comprises the flame-retardant textile that some layers are stained with flame-retarded resin, this deck at least comprises the thin bamboo strips used for weaving layer that some layers are stained with water-soluble resin, this external protection coating at least comprises flame-retarded resin.The utility model is spliced into piping lane by prefabricated cambered plate, substantially reduce production and construction period, employing bamboo wood is made, and while guaranteed strength is high, quality is light, cost is low, environmental protection, solve existing pipe gallery consumptive material many, construction is large, long construction period, the technical problem that cost is high.

Description

A kind of prefabricated bamboo compound piping lane
Technical field
The utility model belongs to urban operating mechanism field, particularly relates to a kind of prefabricated bamboo compound piping lane.
Background technology
Piping lane is built in Urban Underground for laying the urban operating mechanism of municipal pipeline.The multiple municipal pipelines such as its current collection power, communication, broadcasting and TV, combustion gas, plumbing, heating power are in one, efficiently utilize the space under road, save Underground Space Resource, also stopped each special pipelines irregularly to excavate respectively, on the impact that road and surrounding enviroment cause, thoroughly solve the problem such as " road slide fastener ", " aerial cobweb ".
At present, no matter piping lane is Cast-in-situs type or prefabricated, mostly adopts reinforced concrete structure, but this structure consumes material is many, and construction is large, long construction period, and cost is high, is more and more difficult to the demand adapting to Modernized City Construction.
Utility model content
For the above problem of prior art, the purpose of this utility model is to provide a kind of prefabricated bamboo compound piping lane, utilizes bamboo wood to make standardized prefabricated component assembled, bamboo wood environmental protection, with low cost, prefabricated component processing convenient transportation, be applicable to producing in enormous quantities, substantially reduce production and construction period, substitute existing reinforced concrete structure, solve existing pipe gallery consumptive material thus many, construction is large, long construction period, the technical problem that cost is high.
For achieving the above object, according to an aspect of the present utility model, provide a kind of prefabricated bamboo compound piping lane, the circular cross-section of this piping lane, the cambered plate identical by several is spliced, this cambered plate plate benging that is square becomes arc surfaced, the external surface of this cambered plate is by a depression cambered surface, one protrudes cambered surface, two curved ends and two side planes are formed, this depression cambered surface and this protrusion cambered surface lay respectively on two coaxial faces of cylinder, this depression cambered surface and this protrusion cambered surface all have two camber line limits and two straight lines, the axis on the face of cylinder that this straight line is all coaxial with these two parallels, these two side plane place Plane intersects, and the axis on this intersecting lens and this coaxial face of cylinder on the same line, this cambered plate comprises inner liner, deck and external protection coating from this depression cambered surface successively to this protrusion cambered surface direction, this inner liner comprises the flame-retardant textile that some layers are stained with flame-retarded resin, this deck at least comprises the thin bamboo strips used for weaving layer that some layers are stained with water-soluble resin, and this external protection coating at least comprises flame-retarded resin.
The utility model technique scheme compared with prior art, bigbore piping lane is adopted standardized prefabricated component---cambered plate is assembled, facilitate large batch of production and transport, thus substantially increase production efficiency, transport and construction very convenient, shorten the construction period, and then reduce construction cost.In addition, adopt bamboo wood as main reinforcing material innovatively, utilize the characteristic that its intensity is high, is combined with flame-retarded resin, gently, environmental protection, resource are renewable, with low cost for the high and quality of the cambered plate intensity made.It utilizes flame-retarded resin and flame-retardant textile to make inner liner, is the inwall of piping lane after assembled, the piping lane inner wall smooth of formation, antiseepage waterproof, corrosion-resistant; Utilize the external protection coating that flame-retarded resin is made, after assembled, be the external surface of piping lane, the deck made in order to protect thin bamboo strips used for weaving, make piping lane external surface have antiseepage waterproof, corrosion resistance; And because inner liner, external protection coating resin all adopt flame-retarded resin, deck resin adopts water-soluble resin, has flame retardancy, and the fabric that inner liner uses is the flame-retardant textile with anti-flammability, makes the piping lane entirety be assembled into have fire line.
Alternatively, two side plane sides of this cambered plate are provided with the lug boss protruded along this side plane place plane.Such vibrational power flow facilitates assembled connection, connects after this lug boss through hole of cambered plate between two with securing member, connects effect firm, can pad rubber pad and increase sealing further, ensure the waterproof, seepage control of overall piping lane between two lug bosses be connected.
Alternatively, two curved ends of this cambered plate are the plane paralleled, and these two curved end sides are provided with the lug boss protruded along this curved end place plane.Such vibrational power flow facilitates assembled connection, connects after this lug boss through hole of cambered plate between two with securing member, connects effect firm, can pad rubber pad and increase sealing further, ensure the waterproof, seepage control of overall piping lane between two lug bosses be connected.
Alternatively, the water-soluble resin of this thin bamboo strips used for weaving layer is water soluble amino resin.Water-soluble resin and plant have good affinity, and water soluble amino resin and bamboo wood have better associativity, and obtained deck intensity is high, and quality is good, long service life.
Alternatively, the depression cambered surface of this cambered plate is fixed with load-carrying member.Piping lane inner surface arranges load-carrying member in order to be connected with other inner structural members, ensure to give other inner structural members enough supporting forces.
Alternatively, this load-carrying member is fixed on the fixed form in this depression cambered surface is pre-buried or bonding.Can in the process preparing cambered plate this load-carrying member pre-buried, or to be bonded in after preparing cambered plate in this depression cambered surface.
Alternatively, the inside of this piping lane is provided with vertical brace summer, horizontal shore and support of pipelines, this vertical brace summer and horizontal shore are all positioned in the plane perpendicular to this piping lane axis, and this vertical brace summer, horizontal shore and support of pipelines are all connected on this load-carrying member.Arrange vertical brace summer and horizontal shore provides the support force of horizontal direction and vertical direction for piping lane in piping lane inside, make overall structure firmly durable, increase piping lane application life, support of pipelines is in order to supporting flue.
Alternatively, in the same plane perpendicular to this piping lane axis, this vertical brace summer is set to two, be respectively in this piping lane both sides, this vertical brace summer is axially arranged in parallel multiple along this piping lane, two arrange between this vertical brace summer of being oppositely arranged and form access path, between these piping lane both sides this vertical brace summer and this load-carrying member, be connected with support of pipelines.Adopt this structure can make full use of piping lane inner space, centre is set to access path, and both sides arrange support of pipelines, convenient maintenance.
Alternatively, this horizontal shore is positioned at the below in this piping lane circular cross section center of circle, this horizontal shore is axially arranged in parallel multiple along this piping lane at grade, connecting rod is connected with between the horizontal shore that this is parallel, this connecting rod and horizontal shore are equipped with cover plate, this cover plate is provided with grid, and the below of this cover plate is set to gutter.Such vibrational power flow, while guarantee provides the support force of horizontal direction, it can also be utilized to be configured to support baseboard for people or vehicle to run, on the cover board arranging grid can make the ponding of the generations such as piping lane internal cause pipe leakage flow to below cover plate by grid, is that water just can directly discharge by gutter by the spatial placement formed with piping lane below cover plate.
Alternatively, this load-carrying member, vertical brace summer, horizontal shore, support of pipelines, cover plate and connecting rod are stainless steel.Adopt stainless steel rigidity high, durable in use, corrosion-resistant, long service life.
Accompanying drawing explanation
Fig. 1 is the cambered plate structural representation in the utility model embodiment;
Fig. 2 is the prefabricated bamboo compound piping lane section structure schematic diagram in the utility model embodiment.
In all of the figs, identical Reference numeral is used for representing identical element or structure, wherein: 1-cambered plate; 101-protrudes cambered surface; 102-caves in cambered surface; 103-side plane; 104-curved end; 11-inner liner; 12-deck; 13-external protection coating; 14-lug boss; 15-rubber pad; 16-securing member; 2-load-carrying member; The vertical brace summer of 3-; 4-horizontal shore; 5-support of pipelines; 6-gutter; 7-access path.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the utility model, and be not used in restriction the utility model.In addition, if below in described each embodiment of the utility model involved technical characteristic do not form conflict each other and just can mutually combine.
Embodiment 1
An embodiment of the present utility model as shown in Figure 1, is the structural representation of cambered plate 1.Cambered plate 1 plate benging that is square becomes arc surfaced, the external surface of cambered plate 1 protrudes cambered surface 101, two curved ends 104 by a depression cambered surface 102, and two side planes 103 are formed, depression cambered surface 102 and protrude cambered surface 101 and lay respectively on two coaxial faces of cylinder, this cylinder axis as shown in Figure 1.Depression cambered surface 102 and protrusion cambered surface 101 all have two camber line limits and two straight lines, the axis on the face of cylinder that this straight line is all coaxial with these two parallels, these two side plane 103 place Plane intersects, and the axis on this intersecting lens and this coaxial face of cylinder is on the same line (as shown in dotted line in Fig. 1).The central angle i.e. central angle on this camber line limit of the cambered surface that cambered plate 1 is bending should be eliminated by 360 degree of integers, and the cambered plate of such guarantee same size can be combined into cylindric piping lane.As shown in Figure 2, be one prefabricated bamboo compound piping lane section structure schematic diagram, be spliced into the piping lane of circular cross-section by 6 pieces of cambered plates 1, then connect into piping lane by some piping lanes, namely the central angle of this cambered surface is 60 degree.Cambered plate 1 comprises inner liner 11, deck 12 and external protection coating 13 from depression cambered surface 102 successively to protrusion cambered surface 101 direction, inner liner 11 comprises the flame-retardant textile that some layers are stained with flame-retarded resin, flame-retarded resin can be the resin of the water proofing property such as vinyl ester resin, epoxy resin, good corrosion resistance, can also add the fillers such as curing compound in resin, flame-retardant textile can for having the fabric such as non-woven fabrics, grid cloth, needled mat of anti-flammability; Deck 12 at least comprises the thin bamboo strips used for weaving layer that some layers are stained with water-soluble resin, and external protection coating 13 at least comprises flame-retarded resin, can be the resin of the water proofing property such as vinyl ester resin, epoxy resin, good corrosion resistance, can also add the filler such as curing compound, dyestuff.Inner liner 11 and external protection coating 13 are all in order to operator guards layer 12, the piping lane waterproof making to be assembled into, antiseep, corrosion-resistant, and increase the service life, deck 12 is the main enhancing structure of piping lane.The water-soluble resin that this thin bamboo strips used for weaving layer uses is preferably water soluble amino resin, because the associativity of amino resins and thin bamboo strips used for weaving is best.Because deck 12 adopts thin bamboo strips used for weaving to make, make the piping lane that is assembled into and manufacture process environmental protection, and bamboo wood intensity is high, modulus of elasticity is higher, and obtained piping lane is while guaranteed strength, and quality is light, transport and easy for installation, and bamboo is renewable resource, and the cost of raw material is low.Because inner liner 11, deck 12, external protection coating 13 all use fire-retardant or difficult combustion resin, the piping lane entirety be therefore assembled into has fire line.The curved end 104 of cambered plate 1 can be plane can be also curved surface, for being parallel to each other during plane, for ensureing during curved surface that identical cambered plate 1 can firmly connect each other.In order to make splicing structure firm, when making cambered plate 1, the lug boss 14 protruded along this side plane 103 place plane can be provided with in two of cambered plate 1 side plane 103 side, when curved end 104 is plane, the lug boss 14 protruded along this curved end 104 place plane also can be provided with two curved end 104 sides.This lug boss 14, in order to play the effect of flange flange, makes every sheet cambered plate 1 by this lug boss 14 through hole above, just can be fastenedly connected, be assembled into piping lane with securing member 16.The protrusion direction of this lug boss 14 can by depression cambered surface 102 inwardly protruding, also can by protrusion cambered surface 101 outwardly convex, individually or simultaneously lug boss can be set at side plane 103 and curved end 104 side, and its protrusion direction can be all protruding by same cambered surface, also can be protruding by different cambered surface.This lug boss 14 can be one-body molded when making cambered plate 1.The lug boss 14 being positioned at side plane 103 side shown in Fig. 2 is by depression cambered surface 102 to projecting inward, and the lug boss 14 being positioned at curved end 104 side is outwardly by protrusion cambered surface 101.Securing member 16 can be bolt and nut, and is lined with rubber pad 15 between the side plane 103 spliced mutually and between curved end 104.The gap of the adjacent arcs panel 1 of splicing is tamped by rubber pad 15, increases sealing further.At the surfaces externally and internally brushing one deck anti-corrosion resin again splicing the piping lane well, waterproof, seepage control can also be improved further, extends the application life of piping lane.Securing member 16 should select stainless steel.
The method making cambered plate 1 can adopt mould pressing process, forming shape as required selects the mould of respective shapes, lay the deck 12 formed with the thin bamboo strips used for weaving being soaked with water soluble amino resin by the inner liner 11 that the flame-retardant textile that flame-retarded resin soaks into is formed in a mold from level to level, inner liner 11 should select the flame-retarded resin of corrosion resistance, water proofing property, good-extensibility, the vinyl ester resin, epoxy resin etc. with anti-flammability can be adopted, also can add as fillers such as curing compound in resin; After compression molding, protrusion cambered surface 101 applies one deck flame-retarded resin, and this resin should have corrosion resistance simultaneously, can adopt vinyl ester resin, epoxy resin etc., also can add as the filler such as curing compound, dyestuff in resin.If need to arrange lug boss 14, the mould with respective shapes should be selected, thus be molded into respective shapes.
The depression cambered surface 102 of cambered plate 1 is fixed with load-carrying member 2, in order to support other components inner such as vertical connecting brace summer 3, horizontal shore 4 and support of pipelines 5, provide enough supporting forces for other components inner such as vertical brace summer 3, horizontal shore 4 and support of pipelines 5 are connected on piping lane.Load-carrying member 2 can have any shape, and plays supporting role as long as can be fixedly connected with.Arc is set to, as shown in Figure 2 in the present embodiment.Fixed form directly can be embedded on inner liner 11 when making cambered plate 1 or be bonded in depression cambered surface 102 after shaping, also can be bonding again after being assembled into piping lane.Bonding way can adopt the adhesive such as epoxy resin, rubber-type resin bonding, is connected firmly after solidification.Piping lane inside is provided with vertical brace summer 3, horizontal shore 4 and support of pipelines 5, vertical brace summer 3 and horizontal shore 4 are all positioned in the plane perpendicular to this piping lane axis, in order to the support force providing vertical direction and horizontal direction to columnar piping lane, can be gone down by permanent, safe, firm use, vertical brace summer 3, horizontal shore 4 and support of pipelines 5 are all connected on load-carrying member 2.In the present embodiment, horizontal shore 4 is positioned at the below in the piping lane circular cross section center of circle, is axially arranged in parallel multiple at grade, between parallel horizontal shore 4, is connected with connecting rod along piping lane, this connecting rod and horizontal shore 4 are equipped with cover plate, form the support baseboard in order to walking.The below of this cover plate is set to gutter 6, and this cover plate is provided with grid, drains in gutter 6 discharge in order to make the ponding such as the pipe leakage that produces in piping lane from grid.In the present embodiment, vertical brace summer 3 one end is connected on load-carrying member 2, the other end is connected on horizontal shore 4, in the same plane perpendicular to piping lane axis, this vertical brace summer 3 is set to two, be respectively in the both sides of piping lane, this vertical brace summer 3 is axially arranged in parallel multiple along piping lane, and two arrange between the vertical brace summer 3 that is oppositely arranged and form access path 7, between piping lane both sides this vertical brace summer 3 and this load-carrying member 2, be connected with support of pipelines 5.Support of pipelines 5 one end is connected on load-carrying member 2, and the other end is connected on vertical brace summer 3, in order to set up pipeline.In order to make pipeline construction convenient, can by vertical brace summer 3 connection segment from bottom to up, often connect one section of vertical brace summer 3, between itself and load-carrying member 2, horizontal direction just connects one deck support of pipelines 5, then will need to be laid on the pipeline construction on this support of pipelines 5, carry out the more vertical brace summer 3 of last layer and the connection of support of pipelines 5 again, until be connected to the top of body 1.Above-mentioned horizontal shore 4, vertically brace summer 3, support of pipelines 5, load-carrying member 2, cover plate and connecting rod preferably adopt stainless steel, and corrosion-resistant, long service life, rigidity is high.The connected mode of above-mentioned horizontal shore 4, vertically brace summer 3, support of pipelines 5 and load-carrying member 2 and horizontal shore 4 and vertical brace summer 3, support of pipelines 5 and the connected mode vertically between brace summer 3 can be with bolts or the mode such as to weld.After having spliced piping lane, at the inner vertical connecting brace summer 3 of piping lane, horizontal shore 4 and support of pipelines 5, connecting rod, cover plate.Can will need the pipeline construction of corridor on support of pipelines 5, also on the cover board can increase pipe support in order to support feedwater piping, regenerated water pipeline etc.Piping lane internal construction can adjust according to actual needs, is only to provide a kind of frame mode in the present embodiment.
The prefabricated bamboo compound piping lane environmental protection that the present embodiment is obtained, stabilized structure, can substitute existing reinforced concrete structure piping lane completely, and cost is low, and quality is light, production, transport, easy construction.
Those skilled in the art will readily understand; the foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all do within spirit of the present utility model and principle any amendment, equivalent to replace and improvement etc., all should be included within protection domain of the present utility model.

Claims (10)

1. a prefabricated bamboo compound piping lane, the circular cross-section of this piping lane, it is characterized in that, this piping lane is spliced by several identical cambered plates, this cambered plate plate benging that is square becomes arc surfaced, the external surface of this cambered plate is by a depression cambered surface, one protrudes cambered surface, two curved ends and two side planes are formed, this depression cambered surface and this protrusion cambered surface lay respectively on two coaxial faces of cylinder, this depression cambered surface and this protrusion cambered surface all have two camber line limits and two straight lines, the axis on the face of cylinder that this straight line is all coaxial with these two parallels, these two side plane place Plane intersects, and the axis on this intersecting lens and this coaxial face of cylinder on the same line, this cambered plate comprises inner liner, deck and external protection coating from this depression cambered surface successively to this protrusion cambered surface direction, this inner liner comprises the flame-retardant textile that some layers are stained with flame-retarded resin, this deck at least comprises the thin bamboo strips used for weaving layer that some layers are stained with water-soluble resin, and this external protection coating at least comprises flame-retarded resin.
2. prefabricated bamboo compound piping lane as claimed in claim 1, is characterized in that, two side plane sides of this cambered plate are provided with the lug boss protruded along this side plane place plane.
3. prefabricated bamboo compound piping lane as claimed in claim 1, is characterized in that, two curved ends of this cambered plate are the plane paralleled, and these two curved end sides are provided with the lug boss protruded along this curved end place plane.
4. prefabricated bamboo compound piping lane as claimed in claim 1, is characterized in that, the water-soluble resin of this thin bamboo strips used for weaving layer is water soluble amino resin.
5. prefabricated bamboo compound piping lane as claimed in claim 1, is characterized in that, the depression cambered surface of this cambered plate is fixed with load-carrying member.
6. prefabricated bamboo compound piping lane as claimed in claim 5, is characterized in that, this load-carrying member fixed form be fixed in this depression cambered surface is pre-buried or bonding.
7. prefabricated bamboo compound piping lane as claimed in claim 5, it is characterized in that, the inside of this piping lane is provided with vertical brace summer, horizontal shore and support of pipelines, this vertical brace summer and horizontal shore are all positioned in the plane perpendicular to this piping lane axis, and this vertical brace summer, horizontal shore and support of pipelines are all connected on this load-carrying member.
8. prefabricated bamboo compound piping lane as claimed in claim 7, it is characterized in that, in the same plane perpendicular to this piping lane axis, this vertical brace summer is set to two, be respectively in this piping lane both sides, this vertical brace summer is axially arranged in parallel multiple along this piping lane, two arrange between this vertical brace summer of being oppositely arranged and form access path, between these piping lane both sides this vertical brace summer and this load-carrying member, be connected with support of pipelines.
9. prefabricated bamboo compound piping lane as claimed in claim 7, it is characterized in that, this horizontal shore is positioned at the below in this piping lane circular cross section center of circle, this horizontal shore is axially arranged in parallel multiple along this piping lane at grade, connecting rod is connected with between the horizontal shore that this is parallel, this connecting rod and horizontal shore are equipped with cover plate, this cover plate is provided with grid, the below of this cover plate is set to gutter.
10. prefabricated bamboo compound piping lane as claimed in claim 9, is characterized in that, this load-carrying member, vertical brace summer, horizontal shore, support of pipelines, cover plate and connecting rod are stainless steel.
CN201520689856.4U 2015-09-08 2015-09-08 A kind of prefabricated bamboo compound piping lane Active CN204940337U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520689856.4U CN204940337U (en) 2015-09-08 2015-09-08 A kind of prefabricated bamboo compound piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520689856.4U CN204940337U (en) 2015-09-08 2015-09-08 A kind of prefabricated bamboo compound piping lane

Publications (1)

Publication Number Publication Date
CN204940337U true CN204940337U (en) 2016-01-06

Family

ID=55007779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520689856.4U Active CN204940337U (en) 2015-09-08 2015-09-08 A kind of prefabricated bamboo compound piping lane

Country Status (1)

Country Link
CN (1) CN204940337U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064399A (en) * 2015-09-08 2015-11-18 浙江鑫宙竹基复合材料科技有限公司 Assembly type prefabricated bamboo composite pipe rack

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105064399A (en) * 2015-09-08 2015-11-18 浙江鑫宙竹基复合材料科技有限公司 Assembly type prefabricated bamboo composite pipe rack

Similar Documents

Publication Publication Date Title
CN105064399A (en) Assembly type prefabricated bamboo composite pipe rack
CN205136858U (en) Compound piping lane of prefabricated bamboo
CN105042213A (en) Prefabricated bamboo composite pipe gallery and manufacturing method thereof
CN201038690Y (en) Cover plate type cable or water drainage groove
CN203701416U (en) Coreboard
CN204199536U (en) A kind of composite material plate-girder
CN103114527A (en) Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN204940337U (en) A kind of prefabricated bamboo compound piping lane
CN103924820A (en) Mounting method for thermal power plant wet chimney with flame retardant anti-corrosion glass fiber reinforced plastic structure
CN206784606U (en) Adjustable built-in fitting
CN206538932U (en) Precast light partition plate
CN103343573A (en) Modular building with high bearing performance and capable of being produced in industrialized mode and being dismantled and installed rapidly
CN110056117B (en) Corrugated surface hollow FRP profile sea sand concrete slab structure
CN206521696U (en) A kind of bridge drainage system
CN110820470B (en) Assembly type ECC-photovoltaic power generation pavement structure and construction method
CN108396644B (en) SMC composite material and pavement system using same
CN103590419B (en) Assembling is adjustable, and high voltage reactor is basic
CN202324155U (en) Adjustable corrugated prestress anti-pollution drainage culvert
CN203144900U (en) Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN206538929U (en) Prefabricated wallboard
CN210685112U (en) Steel-concrete combined prefabricated bottom plate assembly for laminated slab and wall
CN104775829A (en) High-durability composite prefabricated pipe piece
CN204163293U (en) The roof structure of steel concrete integrated building
CN103758278B (en) Battenboard
CN102518287A (en) Manufacturing method of boninite air tube and manufactured product thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230228

Address after: 311122 No. 29-16, Jiaqi Road, Xianlin Street, Yuhang District, Hangzhou, Zhejiang

Patentee after: Zhonglin Xinzhou Bamboo Winding Development Co.,Ltd.

Address before: 311115 Fengdu village, Pingyao Town, Yuhang District, Hangzhou, Zhejiang

Patentee before: ZHEJIANG XINZHOU BAMBOO-BASED COMPOSITES TECHNOLOGY Co.,Ltd.

Patentee before: Ye Ling