CN204921558U - A interim connecting device that is used for component and bracket to dock - Google Patents

A interim connecting device that is used for component and bracket to dock Download PDF

Info

Publication number
CN204921558U
CN204921558U CN201520500821.1U CN201520500821U CN204921558U CN 204921558 U CN204921558 U CN 204921558U CN 201520500821 U CN201520500821 U CN 201520500821U CN 204921558 U CN204921558 U CN 204921558U
Authority
CN
China
Prior art keywords
component
bracket
plate
connecting device
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520500821.1U
Other languages
Chinese (zh)
Inventor
张贺
陆建新
王川
霍宗诚
杨传斌
孔卉楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201520500821.1U priority Critical patent/CN204921558U/en
Application granted granted Critical
Publication of CN204921558U publication Critical patent/CN204921558U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the building field provides an interim connecting device that is used for component and bracket to dock, and it is including fixing at the locating plate of bracket upper surface and fix the bridging plate at the component upper surface, the bridging plate projection goes out the side end face of component, pass through the bolt fastening between locating plate and the bridging plate. Foretell interim connecting device is through setting up locating plate and bridging plate respectively on bracket upper surface and component upper surface to the side end face that makes the bridging plate projection go out the component is fixed bridging plate and locating plate through the bolt simultaneously, can guarantee the accuracy of butt joint, avoids appearing wrong limit mismatch phenomenon, and at the interim in -process of connecting, need not to use welding equipment, and the tower crane also need not the wait, and the installation effectiveness is high.

Description

A kind of temporary connecting device docked for component and bracket
Technical field
The utility model belongs to building field, particularly relates to a kind of temporary connecting device docked for component and bracket.
Background technique
At present, the domestic super high steel structure engineering development impetus is swift and violent, level or the inclination steel beam column such as a large amount of girder steels, truss, diagonal brace must be used in Steel Structure Work, this class steel beam column must use interim connection measure in an installation, by connect temporarily measure by the steel beam column of lifting with dock bracket and fix, complete permanent to connect and behind location Deng steel beam column, then cut off interim connection measure.
Interim connection measure is in the field of business two kinds of usual practices, and one arranges horse plate 20 at steel beam column 10 upper surface, and horse plate 20 and bracket 30 are fixed by spot welding, as depicted in figs. 1 and 2.The another kind of practice all arranges connecting plate 40 in the upper and lower surface of steel beam column 10 and bracket 30, then be fixedly connected with by bolt B with the connecting plate 40 on bracket 30 by steel beam column 10 with connecting otic placode 50, as shown in Figure 3 and Figure 4.But these two kinds of usual practices all have open defect, the former fixes owing to adopting spot welding, causes needing in temporary fixed process to use welding equipment, cause temporary fixed not convenient, the latter is in temporary fixed process, and tower crane cannot loose hook, and overlap joint difficulty, easily there is misalignment mismatch phenomenon.
Model utility content
Technical problem to be solved in the utility model is to provide a kind of temporary connecting device docked for component and bracket, can ensure the accuracy of docking, avoid occurring misalignment mismatch phenomenon, and in the interim process connected, without the need to using welding equipment, tower crane is also without the need to waiting for, installation efficiency is high.
The utility model realizes like this, a kind of temporary connecting device docked for component and bracket, comprise the positioning plate being fixed on bracket upper surface and the lapping plate being fixed on member upper surface, described lapping plate stretches out the side end face of component, is bolted between described positioning plate and lapping plate.
Further, the part described lapping plate stretching out member side end face is provided with overlap adjacent one another are and positioning area, and described overlap is taken and is placed on bracket, and described positioning area is fixed by described bolt and positioning plate.
Further, described positioning plate is fixed by welding on bracket.
Further, the positioning area of described lapping plate is provided with the breach for hiding described positioning plate weld bead height.
Further, described lapping plate is also provided with and for being welded on component is welded and fixed district.
Further, being welded and fixed on described lapping plate is provided with between district and overlap crosses welding hole for what ensure to weld space.
The utility model compared with prior art, beneficial effect is: the temporary connecting device docked for component and bracket described in the utility model, by arranging positioning plate and lapping plate respectively on bracket upper surface and member upper surface, and make lapping plate stretch out the side end face of component, by bolt, lapping plate and positioning plate are fixed simultaneously, the accuracy of docking can be ensured, avoid occurring misalignment mismatch phenomenon, and in the interim process connected, without the need to using welding equipment, tower crane is also without the need to waiting for, installation efficiency is high.
Accompanying drawing explanation
Fig. 1 is the schematic front view of a kind of interim Placement that prior art provides.
Fig. 2 is the schematic top plan view in Fig. 1.
Fig. 3 is the schematic front view of the interim Placement of another kind that prior art provides.
Fig. 4 is the schematic top plan view in Fig. 3.
Fig. 5 is the schematic front view of the temporary connecting device that the utility model embodiment provides.
Fig. 6 is the schematic top plan view of the temporary connecting device that the utility model embodiment provides.
Fig. 7 is the decomposing state schematic diagram of temporary connecting device in Fig. 3.
Embodiment
In order to make the purpose of this utility model, technological scheme and advantage clearly understand, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the utility model, and be not used in restriction the utility model.
Fig. 5 to Fig. 7 is the temporary connecting device docked for component 1 and bracket 2 shown in the utility model embodiment, it comprises the positioning plate 3 being fixed on bracket 2 upper surface and the lapping plate 4 being fixed on component 1 upper surface, lapping plate 4 stretches out the side end face of component 1, is fixed between positioning plate 3 and lapping plate 4 by bolt A.
Concrete, part lapping plate 4 stretching out component 1 side end face is provided with overlap 41 adjacent one another are and positioning area 42, and overlap 41 is taken and is placed on bracket 2, and positioning area 42 is fixed by bolt A and positioning plate 3.Lapping plate 4 is also provided with and for being welded on component 1 is welded and fixed district 43, and being welded and fixed on lapping plate 4 to be provided with between district 43 and overlap 41 and to cross welding hole 44 for what ensure to weld space.In the present embodiment, positioning plate 3 is fixed by welding on bracket 1.For ensureing the accuracy that positioning plate 3 is connected with lapping plate 4, the positioning area 42 of lapping plate 4 is provided with the breach 421 for hiding positioning plate 3 weld bead height.
Before construction, between lapping plate 4 with component 1 weld and welding between positioning plate 3 with bracket 2 all completes when dispatching from the factory, then job site is transported to together, then, by component 1 hoisted in position at the scene, utilizing overlap 41 to be taken by component 1 is placed on bracket 2, now, tower crane can unclamp and do other procedure arrangements, then, positioning area 42 and positioning plate 3 is connected and fixed by bolt A, complete component 1 to be connected with the interim of bracket 2, finally, after waiting component 1 forever to connect, then lapping plate 4 and positioning plate 3 entirety are excised and clear up.
The temporary connecting device docked for component 1 and bracket 2 described in the utility model, by arranging positioning plate 3 and lapping plate 4 respectively on bracket 2 upper surface and component 1 upper surface, and make lapping plate 4 stretch out the side end face of component 1, by bolt A, lapping plate 4 and positioning plate 3 are fixed simultaneously, the accuracy of docking can be ensured, avoid occurring misalignment mismatch phenomenon, and in the interim process connected, without the need to using welding equipment, tower crane is also without the need to waiting for, installation efficiency is high.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all do within spirit of the present utility model and principle any amendment, equivalent to replace and improvement etc., all should be included within protection domain of the present utility model.

Claims (6)

1. the temporary connecting device docked for component and bracket, it is characterized in that, comprise the positioning plate being fixed on bracket upper surface and the lapping plate being fixed on member upper surface, described lapping plate stretches out the side end face of component, is bolted between described positioning plate and lapping plate.
2. the temporary connecting device docked for component and bracket as claimed in claim 1, it is characterized in that, the part described lapping plate stretching out member side end face is provided with overlap adjacent one another are and positioning area, described overlap is taken and is placed on bracket, and described positioning area is fixed by described bolt and positioning plate.
3., as claimed in claim 1 or 2 for the temporary connecting device that component and bracket dock, it is characterized in that, described positioning plate is fixed by welding on bracket.
4., as claimed in claim 3 for the temporary connecting device that component and bracket dock, it is characterized in that, the positioning area of described lapping plate is provided with the breach for hiding described positioning plate weld bead height.
5. as claimed in claim 2 for the temporary connecting device of component and bracket docking, it is characterized in that, described lapping plate is also provided with and for being welded on component is welded and fixed district.
6. as claimed in claim 5 for the temporary connecting device of component and bracket docking, it is characterized in that, being welded and fixed on described lapping plate is provided with between district and overlap crosses welding hole for what ensure to weld space.
CN201520500821.1U 2015-07-10 2015-07-10 A interim connecting device that is used for component and bracket to dock Active CN204921558U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520500821.1U CN204921558U (en) 2015-07-10 2015-07-10 A interim connecting device that is used for component and bracket to dock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520500821.1U CN204921558U (en) 2015-07-10 2015-07-10 A interim connecting device that is used for component and bracket to dock

Publications (1)

Publication Number Publication Date
CN204921558U true CN204921558U (en) 2015-12-30

Family

ID=54970691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520500821.1U Active CN204921558U (en) 2015-07-10 2015-07-10 A interim connecting device that is used for component and bracket to dock

Country Status (1)

Country Link
CN (1) CN204921558U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930408A (en) * 2017-04-19 2017-07-07 中国建筑第二工程局有限公司 Rigid connection joint of steel pipe column and H-shaped steel beam and construction method of rigid connection joint
CN108529415A (en) * 2018-06-19 2018-09-14 中国五冶集团有限公司 Multi-functional lifting ear plate for lifting steel member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106930408A (en) * 2017-04-19 2017-07-07 中国建筑第二工程局有限公司 Rigid connection joint of steel pipe column and H-shaped steel beam and construction method of rigid connection joint
CN108529415A (en) * 2018-06-19 2018-09-14 中国五冶集团有限公司 Multi-functional lifting ear plate for lifting steel member

Similar Documents

Publication Publication Date Title
CN104131704A (en) Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN102518300B (en) Embedded conical bearing joint type steel structure support and construction method thereof
CN204921558U (en) A interim connecting device that is used for component and bracket to dock
CN103206075B (en) Suspension platform for construction of steel reinforced concrete cantilever structure
CN203938346U (en) Moving staircase girders connection structure
CN104477791A (en) Novel tower crane-attached-to-wall attached lattice type support frame auxiliary device
CN204342309U (en) Novel tower crane attached wall attachment lattice bracing frame auxiliary device
CN203271096U (en) Operating platform
CN204850048U (en) Overlap joint structure of quick hoist and mount of supplementary high -rise girder steel
CN203475690U (en) Steel beam butting connecting plate
CN209523198U (en) A kind of underpinning structure supporting lattice column
CN204940851U (en) A kind of sideslip type operating platform
CN205476083U (en) Concrete beam's cover to reinforcement structure
CN203834809U (en) Steel pipe column structure for steel pipe column concrete side pouring method
CN103174300B (en) Viscous damper installation construction method
CN204024084U (en) Easy unloading type triangular pipe truss just spells moulding bed
CN109797853A (en) A kind of recoverable function steel frame eccentrical braces of flange plate
CN204941564U (en) Subway tunnel narrow spacing leaves the right or normal track row gate-type lining cutting bench frame apparatus
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed
CN210366740U (en) Tower crane landing leg fixing device
CN103498559A (en) Splicing movable bridge frame of steel structure industrial factory building and construction method for applying splicing movable bridge frame to roof construction
CN205917715U (en) A positioner that is used for high -pressure superhigh pressure pipe pier bolt
CN207700528U (en) A kind of steel column structure
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN202787300U (en) Control form for positions of foundation bolts of fixed tower crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant