CN204876190U - Brickwork infilled wall adds muscle constructional column of plastering - Google Patents

Brickwork infilled wall adds muscle constructional column of plastering Download PDF

Info

Publication number
CN204876190U
CN204876190U CN201520595934.4U CN201520595934U CN204876190U CN 204876190 U CN204876190 U CN 204876190U CN 201520595934 U CN201520595934 U CN 201520595934U CN 204876190 U CN204876190 U CN 204876190U
Authority
CN
China
Prior art keywords
masonry
band steel
constructional column
reinforcing bar
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201520595934.4U
Other languages
Chinese (zh)
Inventor
马广生
汪黄东
于科
高存金
解小东
葛振刚
张爱军
辛建龙
张宗志
姜太平
张爱中
杨涛
刘彬
张东
李应心
李蕾
刘斌
李超
庞茜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
China Construction Industrial and Energy Engineering Group Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201520595934.4U priority Critical patent/CN204876190U/en
Application granted granted Critical
Publication of CN204876190U publication Critical patent/CN204876190U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a brickwork infilled wall adds muscle constructional column of plastering belongs to the building field. Its technical scheme does: including the brickwork, the brickwork both sides all are provided with reinforcing bar net piece, are connected with the brickwork embedded bar that runs through the brickwork between the reinforcing bar net piece, both ends difference fixedly connected with went up band steel and lower band steel about the piece was netted to the reinforcing bar, upper portion joint bar and last band steel fixed connection, lower part joint bar and lower band steel fixed connection, the mortar has all been smeared in the outside in the reinforcing bar net piece. The beneficial effects of the utility model are that: cancel the reinforcing bar preparation and ligature link, constructional column concrete link and formwork and form removal link of traditional constructional column, save material, saved artifical, time limit for a project sparingly, be connected with the structural framework system, make building atress system more equitable, reinforcing bar net piece, band steel, building block, checking fibre anti -crack mortar etc. And adopting the finished product in a large number, the quality is more secure, and the used time limit for a project only is 10% of traditional way, the process is simple, and is easy and simple to handle, and the popularization is high.

Description

A kind of masonry filler wall reinforced coating constructional column
Technical field
The utility model belongs to the technical field of building operations, is specifically related to a kind of masonry filler wall reinforced coating constructional column.
Background technology
The masonry structure of current China strengthens the method that main employing arranges reinforced concrete structural column, comprise the operations such as reserved steel bar, bar planting, making and assembling reinforcement, formwork, hand-placed concrete, form removal, its principle is that masonry passes through that longitudinal reserved steel bar is connected with concrete-constituted pile, concrete-constituted pile is connected with concrete frame structure by top and bottom reinforcing bar.The method duration is longer, operation is loaded down with trivial details, quality is wayward, and comprehensive cost is high.In addition, existing part dilapidated house structural strengthening antidetonation construction method, what adopt adds cartridge plate and is connected lacing wire on the basis of original body of wall, this method often needs to hole so that embedded reinforcement on body of wall, result in walling unit structure itself and suffer secondary damage, body of wall itself also can be made to become out-of-flatness.
Utility model content
For solving the deficiency of above-mentioned prior art, the purpose of this utility model is to provide a kind of masonry filler wall reinforced coating constructional column and construction method thereof.
A kind of masonry filler wall reinforced coating constructional column, it is characterized in that, comprise masonry, described masonry both sides are provided with reinforced mesh 1, the masonry embedded bar 2 running through described masonry is connected with between described reinforced mesh 1, described masonry embedded bar 2 two ends are provided with crotch, described reinforced mesh about 1 two ends are fixedly connected with band steel 5 and lower band steel 9 respectively, described top joint bar 6 is fixedly connected with upper band steel 5, described bottom joint bar 7 is fixedly connected with lower band steel 9, in described reinforced mesh 1, outside is all wiped with mortar 3, reinforced mesh is placed in the centre of inside and outside two-layer described mortar 3.
Described masonry is piled up by building block 8 and is formed.
Masonry mortar 4 is wiped with between described building block 8.
Described masonry embedded bar 2 is embedded in masonry mortar 4.
Described mortar 3 is composite fibre anticracking grout.
The construction method of masonry filler wall reinforced coating constructional column:
Described reinforced mesh 1 upper and lower side welds band steel 5 and lower band steel 9 respectively, and this step is directly processed into finished product;
Needing the upper end of beam embedding described top, the corresponding top joint bar 6 that constructional column position is set, the lower end of corresponding lower beam embedding described bottom joint bar 7;
Described building block 8 and construction wall design building block and select identical material, the masonry Thickness Ratio design thickness of wall body that building block 8 is built into is smaller, embedding between described building block 8 have the masonry embedded bar 2 that runs through described masonry and be wiped with described masonry mortar 4, described masonry embedded bar 2 two ends are fixedly connected with the described reinforced mesh 1 being arranged at described masonry both sides respectively, described upper band steel 5 welds with top joint bar 6, described lower band steel 9 welds with bottom joint bar 7, described mortar 3 is covered in both sides inside and outside described reinforced mesh 1, reinforced mesh is placed in the centre of inside and outside two-layer described mortar 3.
Described top joint bar 6 adopts HRB400 diameter 6.5 ㎜ reinforcing bar;
Described upper band steel 5 all adopts Q235 steel with lower band steel 9;
Described reinforced mesh 1 is finished product welded reinforcement mesh sheet, adopts HRB400 diameter 6.5 ㎜ reinforcing bar, professional factory pressure welding or field fabrication;
Described top joint bar 6 and bottom joint bar 7 all adopt HRB400 diameter 6.5 ㎜ reinforcing bar;
Described masonry embedded bar 2 adopts HRB400 diameter 6.5 ㎜ reinforcing bar;
Described masonry mortar 4 adopts supporting mortar or the layout design material of masonry;
Described building block 8 and the same material of design building block, cross sectional dimensions 40 ㎜s less of design building block;
Described mortar 3 is composite fibre anticracking grout, and its thickness approximates 30 ㎜.
By test, a kind of masonry filler wall reinforced coating constructional column beneficial effect is: eliminate traditional construction constructional column reinforcement fabrication and colligation link, saves material steel and saves artificial, the saving duration; Eliminate constructional column concrete link, save the duration; Eliminate formwork and form removal link, save material, save artificial, the saving duration; Be connected with structural framing system, make building stress system more reasonable; Finished product reinforced mesh, band iron, the building block of customization size, check fibre crack-resistance mortar etc. and adopt finished product in a large number, quality is more secure, and the duration used is only 10% of traditional method; Operation is simple, and easy and simple to handle, popularization is high.Masonry arranged outside reinforced mesh, and reinforced mesh is connected integrally with top beam lower beam, not only saves material, and better play the effect of support and antidetonation; Embedding embedded bar when masonry is built by laying bricks or stones, and embedded bar is embedding with in masonry mortar, does not damage the structure of building block own, thus more firm.Reinforced mesh upper and lower side is all connected with band steel, and the operation of connection top and the bottom joint bar can be made more simple.Composite fibre anticracking grout covering structure post is adopted outside reinforced mesh, there is good effect of prestressed, in addition, the reinforced mesh of both sides couples together by masonry embedded bar, make the reinforced mesh of building block and both sides and smear the mortar close proximity in reinforced mesh both sides, ensure the integration of each parts of constructional column; Masonry thickness is less than architectural design body of wall, smoothly attractive in appearance with architectural design surface of wall after constructional column can be made to have smeared composite fibre anticracking grout.The utility model installs reinforced mesh and composite fibre anticracking grout additional, the effect replacing conventional construction post and plaster, whole process implements in the process of infilled wall formation and after terminating, the end until plaster, and be different from the way of generally in the unsafe situation of structure, constructional column being reinforced after body of wall is formed; Say from cost, the utility model is the constructional column substituting traditional design completely, on the basis reducing integrated cost, meets shockproof requirements.In construction measure, the cost generally carrying out the reinforcing of constructional column later stage is the expense increasing 25%-35% on the basis of former cost, and the utility model is the expense reducing 25%-30% on the basis of former cost.
Accompanying drawing explanation
Fig. 1 is the vertical figure in the utility model front.
Fig. 2 is the A-A sectional drawing of Fig. 1.
Fig. 3 is the B portion enlarged drawing of Fig. 2.
Fig. 4 is the utility model upper connection point enlarged drawing.
Fig. 5 is the utility model low connection point enlarged drawing.
Wherein, Reference numeral is: 1, reinforced mesh; 2, masonry embedded bar; 3, mortar; 4, masonry mortar; 5, upper band steel; 6, top joint bar; 7, bottom joint bar; 8, building block; 9, lower band steel.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the utility model is further elaborated.Certainly, specific embodiment described herein only in order to explain the utility model, and is not used in restriction the utility model.
Embodiment 1
See Fig. 1, the utility model is a kind of masonry filler wall reinforced coating constructional column, comprise masonry, masonry both sides are provided with reinforced mesh 1, the masonry embedded bar 2 running through masonry is connected with between reinforced mesh 1, masonry embedded bar 2 two ends are provided with crotch, reinforced mesh about 1 two ends are fixedly connected with band steel 5 and lower band steel 9 respectively, top joint bar 6 is fixedly connected with upper band steel 5, bottom joint bar 7 is fixedly connected with lower band steel 9, in reinforced mesh 1, outside is all wiped with mortar 3, and reinforced mesh is placed in the centre of inside and outside two-layer described mortar 3.
Masonry is piled up by building block 8 and is formed.
Masonry mortar 4 is wiped with between building block 8.
Masonry embedded bar 2 is embedded in masonry mortar 4.
Mortar 3 is composite fibre anticracking grout.
The construction method of masonry filler wall reinforced coating constructional column:
Reinforced mesh 1 upper and lower side is welded with band steel 5 and lower band steel 9 respectively, and this step is directly processed into finished product;
Needing the upper end of beam embedding top, the corresponding top joint bar 6 that constructional column position is set, the lower end of corresponding lower beam embedding bottom joint bar 7;
Building block 8 and construction wall design building block and select identical material, the masonry Thickness Ratio design thickness of wall body that building block 8 is built into is smaller, embedding between building block 8 have the embedded bar 2 that runs through masonry and be wiped with masonry mortar 4, masonry embedded bar 2 two ends are fixedly connected with the reinforced mesh 1 being arranged at masonry both sides respectively, upper band steel 5 welds with top joint bar 6, lower band steel 9 welds with bottom joint bar 7, and mortar 3 is covered in both sides inside and outside reinforced mesh 1.
Top joint bar 6 adopts HRB400 diameter 6.5 ㎜ reinforcing bar;
Upper band steel 5 adopts Q235 steel with lower band steel 9;
Reinforced mesh 1 is finished product welded reinforcement mesh sheet, adopts HRB400 diameter 6.5 ㎜ reinforcing bar, professional factory pressure welding;
Top joint bar 6 and bottom joint bar 7 all adopt HRB400 diameter 6.5 ㎜ reinforcing bar;
Masonry embedded bar 2 adopts HRB400 diameter 6.5 ㎜ reinforcing bar;
Masonry mortar 4 adopts supporting mortar or the layout design material of masonry;
Building block 8 and the same material of design building block, cross sectional dimensions 40 ㎜s less of design building block;
Mortar 3 is composite fibre anticracking grout, and its thickness approximates 30 ㎜.
The utility model can pass through without the technical characteristic described or adopt existing techniques in realizing; do not repeat them here; certainly; above-mentioned explanation is not to restriction of the present utility model; the utility model is also not limited in above-mentioned citing; the change that those skilled in the art make in essential scope of the present utility model, remodeling, interpolation or replacement, also should belong to protection domain of the present utility model.

Claims (5)

1. a masonry filler wall reinforced coating constructional column, it is characterized in that, comprise masonry, described masonry both sides are provided with reinforced mesh (1), the masonry embedded bar (2) running through described masonry is connected with between described reinforced mesh (1), described masonry embedded bar (2) two ends are provided with crotch, described reinforced mesh (1) is fixedly connected with band steel (5) and lower band steel (9) in two ends up and down respectively, top joint bar (6) is fixedly connected with upper band steel (5), bottom joint bar (7) is fixedly connected with lower band steel (9), in described reinforced mesh (1), outside is all wiped with mortar (3).
2. masonry filler wall reinforced coating constructional column according to claim 1, is characterized in that, described masonry is piled up by building block (8) and formed.
3. masonry filler wall reinforced coating constructional column according to claim 2, is characterized in that, is wiped with masonry mortar (4) between described building block (8).
4. masonry filler wall reinforced coating constructional column according to claim 3, is characterized in that, described masonry embedded bar (2) is embedded in masonry mortar (4).
5., according to the arbitrary described masonry filler wall reinforced coating constructional column of claim 1-4, it is characterized in that, described mortar (3) is composite fibre anticracking grout.
CN201520595934.4U 2015-08-10 2015-08-10 Brickwork infilled wall adds muscle constructional column of plastering Withdrawn - After Issue CN204876190U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520595934.4U CN204876190U (en) 2015-08-10 2015-08-10 Brickwork infilled wall adds muscle constructional column of plastering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520595934.4U CN204876190U (en) 2015-08-10 2015-08-10 Brickwork infilled wall adds muscle constructional column of plastering

Publications (1)

Publication Number Publication Date
CN204876190U true CN204876190U (en) 2015-12-16

Family

ID=54820582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520595934.4U Withdrawn - After Issue CN204876190U (en) 2015-08-10 2015-08-10 Brickwork infilled wall adds muscle constructional column of plastering

Country Status (1)

Country Link
CN (1) CN204876190U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019579A (en) * 2015-08-10 2015-11-04 中建八局第一建设有限公司 Masonry filler wall reinforcement and plastering constructional column and construction method thereof
CN106168068A (en) * 2016-08-04 2016-11-30 中国十七冶集团有限公司 A kind of constructional column joint bar, tension rib joint bar locating mounting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019579A (en) * 2015-08-10 2015-11-04 中建八局第一建设有限公司 Masonry filler wall reinforcement and plastering constructional column and construction method thereof
CN106168068A (en) * 2016-08-04 2016-11-30 中国十七冶集团有限公司 A kind of constructional column joint bar, tension rib joint bar locating mounting method

Similar Documents

Publication Publication Date Title
CN105019579B (en) Masonry filler wall reinforcement and plastering constructional column and construction method thereof
CN107100290A (en) A kind of prefabricated shear wall and overlapping plate node
CN103924710B (en) Low layer assembled combined wall house Plate Welding node structure
CN206174146U (en) Assembly type structure's assembly node
CN105649113A (en) Structure and construction method of basement post-cast strip
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN106968381A (en) With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection
CN108867935A (en) L shape connecting structure of wall and assembled arthitecutral structure system
CN209509222U (en) Assembled arthitecutral structure system
CN205530815U (en) Vertical connection structure of assembled shear force wall
CN110359631A (en) Secondary structure Constructional Col-umn Construction method
CN108661202A (en) A kind of large area hollow out lattice brick curtain wall construction modelled after an antique and construction method
CN106948514B (en) Construction method of ultrahigh masonry wall anti-seismic structure
CN106245817A (en) A kind of fabricated shear wall vertical connection structure and installation method thereof
CN104727440B (en) Industrialized production efficiently-assembled type building frame column beam and manufacturing method
CN204876190U (en) Brickwork infilled wall adds muscle constructional column of plastering
CN209260979U (en) Wall vertical connection structure and assembled arthitecutral structure system
CN201473974U (en) Novel steel plate water stopper
CN103410172A (en) Construction method for post pouring belt plugging of underground structural roof plate
CN206873734U (en) With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection
CN207189929U (en) Roofing assembled concrete blast cap prefabricated mould
CN203361643U (en) Removing-free and dabbing-free template provided with preformed holes
CN109057080A (en) Assembled arthitecutral structure system
CN207959532U (en) A kind of structure that wallboard is connect with coupling beam
CN209670114U (en) Assembled arthitecutral structure system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20151216

Effective date of abandoning: 20170510

AV01 Patent right actively abandoned