CN204728189U - Based on the bridge corrugated sheet box beam that full RPC is applied - Google Patents
Based on the bridge corrugated sheet box beam that full RPC is applied Download PDFInfo
- Publication number
- CN204728189U CN204728189U CN201520320929.2U CN201520320929U CN204728189U CN 204728189 U CN204728189 U CN 204728189U CN 201520320929 U CN201520320929 U CN 201520320929U CN 204728189 U CN204728189 U CN 204728189U
- Authority
- CN
- China
- Prior art keywords
- corrugated sheet
- bridge
- rpc
- box beam
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of bridge corrugated sheet box beam applied based on full RPC, comprise a main structure body, described main structure body is by top board, web and base plate composition, described top board, web and base plate are corrugated sheet, the composite steel silk screen that described corrugated sheet is arranged by the densely covered formula of layer of concrete and inside forms, pressure-bearing set shaped steel formwork is adopted to pass through pressure, solve the problem of RPC flow difficulties, ensure concrete compaction, stream curing is carried out at twice, adopt air energy heating technique and solar boiler heating technique respectively.This structure, relative to conventional concrete case beam weight reduction 50%, solves cost height and later maintenance problem relative to steel work.
Description
Technical field
The utility model relates to bridge construction technical field, particularly relates to a kind of bridge corrugated sheet box beam applied based on full RPC.
Background technology
Reinforced concrete structure is that outstanding contribution has been made in the development of World Economics, Reinforced Concrete Bridge engineering is seen everywhere, the girder span structure section form of bridge mainly contains hollow slab beam, T-shaped beam and box beam, box beam is the bridge span structure that in bridge engineering, frequency of utilization is the highest, box beam is called for short case beam, typical section form is made up of top board, web plate and back plate, general 20 ~ 40cm is thick for top board, general 20 ~ 50cm is thick for web, general 20 ~ 40 cm are thick for base plate, and the conventional construction technology of case beam is support cast-in-place.Ordinary concrete bridge is by the utilization of more than 100 year, perfect and development, and potentiality obtain sufficient excavation, and people also rack one's brains at the development and progress continuing as ordinary concrete bridge technology, but progress is extremely slow.Want the breakthrough in acquisition of technology, concrete compressive strength must be improved, the compressive strength of general concrete is 20 ~ 50Mpa, global experts and scholars are also alleviating dead load and effort for improving intensity, constantly advance to batch production, standardization, continuous productive process, along with appearance and the utilization of RPC, people see again the direction of effort.Present bridge construction becomes the serious social concern of one, China, because traffic jam need build more bridge, the support that bridge construction uses and enclosing make traffic more block, vehicle can't walk any longer, the time loss of people on the way, the non-renewable energy of the idling of vehicle waste earth, and increase the discharge of carbon dioxide, becomes a complicated social concern.
Summary of the invention
The purpose of this utility model is to provide a kind of bridge corrugated sheet box beam applied based on full RPC, effectively solves the problem.
For effectively solving the problems of the technologies described above, the technical scheme that the utility model is taked is as follows:
Based on the bridge corrugated sheet box beam that full RPC is applied, comprise a main structure body, described main structure body is made up of top board, web and base plate, described top board, web and base plate are corrugated sheet (if base plate needs to configure prestressing force, then base plate is still dull and stereotyped), the composite steel silk screen that described corrugated sheet is arranged by the densely covered formula of layer of concrete and inside forms, and described gauze wire cloth is bellows-shaped.
Especially, described layer of concrete is the RPC layer of pressure.
Especially, described gauze wire cloth is made up of high tensile steel wire, and is interconnected by lateral connection steel wire between composite steel silk screen.
Especially, described steel wire diameter is 0.1 ~ 0.5mm, and the gap between steel wire is 1 ~ 2mm, and described transverse steel wire diameter is 0.5 ~ 1 mm, and intensity is 2 ~ 3 times of powder concrete compressive strength.
The beneficial effects of the utility model are: the bridge corrugated sheet box beam applied based on full RPC that the utility model provides, the construction period of half can be shortened, can accomplish, without support or limited bracket construction, fundamentally to solve the problem of urban traffic blocking; Girder span weight reduction 50%, bridge foundation is also corresponding with pier stud load to be alleviated, and physical dimension is corresponding reduction also, and construction technology becomes more simple and easy, and speed of application is faster; It is prefabricated that bridge pier column can adopt RPC to carry out batch production equally, on-site consolidation, and because dead load alleviates, bridge foundation just can adopt static pressed pile or driven pile, and stake is also prefabricated by batch production; Bridge need carry out except cast-in-place construction except cushion cap and bridge deck pavement, and other are all buy mill work to carry out on-site consolidation, and the construction period can shorten 50% ~ 70%, will bring significant social benefit; Large span stayed-cable bridge, suspension bridge use full RPC corrugated sheet box beam to substitute steel box-girder, both can save great deal of steel, and can avoid steel work later stage protection question again.
Below in conjunction with accompanying drawing, the utility model is described in detail.
Accompanying drawing explanation
Fig. 1 is the bridge corrugated sheet box beam composition structural representation applied based on full RPC described in the utility model;
Fig. 2 is gauze wire cloth composition structural representation in the bridge corrugated sheet box beam applied based on full RPC described in the utility model;
Fig. 3 is gauze wire cloth fabricated structure schematic diagram in the bridge corrugated sheet box beam applied based on full RPC described in the utility model;
Fig. 4 is A-A corrugated sheet profile in Fig. 1;
Fig. 5 is B-B corrugated sheet profile in Fig. 1;
Fig. 6 is C-C corrugated sheet profile in Fig. 1.
Wherein:
001 top board, 002 web, 003 base plate, 004 gauze wire cloth, 005 lateral connection steel wire.
Detailed description of the invention
Embodiment 1:
In the present embodiment, the composition original paper of described conventional known structure does not do explanatory note and display in the drawings.
As shown in figures 1 to 6, the disclosed bridge corrugated sheet box beam applied based on full RPC of the present embodiment, comprise a main structure body, described main structure body is made up of top board 001, web 002 and base plate 003, described top board 001, web 002 and base plate 003 are corrugated sheet, if base plate 003 needs to configure prestressing force, then base plate 003 is still dull and stereotyped, the composite steel silk screen 004 that described corrugated sheet is arranged by the densely covered formula of layer of concrete and inside forms, and described gauze wire cloth 004 is bellows-shaped.
Described layer of concrete is the RPC layer of pressure.Described gauze wire cloth 004 is made up of high tensile steel wire, and is interconnected by lateral connection steel wire 005 between composite steel silk screen.Described steel wire diameter is 0.1 ~ 0.5mm, and the gap between steel wire is 1 ~ 2mm, and described transverse steel wire 005 diameter is 0.5 ~ 1 mm.The shaping stream curing of described main structure body is carried out at twice, first time is maintenance 24 hours in 60 DEG C of processing environments after slip casting completes, realized by air energy heating technique, second time stream curing maintenance 48 hours in 100 DEG C of processing environments after demoulding, is realized by solar boiler heating.
Applicant states, person of ordinary skill in the field is on the basis of above-described embodiment, by above-described embodiment step, combined with the technical scheme of utility model content part, thus the new method produced, also be one of record scope of the present utility model, the application, for making manual simple and clear, no longer enumerates other embodiment of these steps.
Know-why is as follows:
Adopt the gauze wire cloth that gathers, steel wire diameter is 0.1 ~ 0.5mm, and the thickness according to layer of concrete arranges two-layer or composite steel silk screen, and the gap between steel wire is 1 ~ 2mm, uses steel wire lateral connection between adjacent steel silk screen, and lateral connection steel wire diameter is 0.5 ~ 1 mm.The gauze wire cloth of top board, web plate and back plate is pressed into corrugated by designing requirement, the rigidity (bending resistance) of object is w=kbh2 with the pass of the width b of object and height h, k is coefficient, cuboid k=1/6, so the corrugated sheet of same volume is more a lot of by force than the bending resistance of solid slab.Adopt pressure-bearing set shaped steel formwork by pressure, solve the problem of RPC flow difficulties, ensure concrete compaction.Stream curing is carried out at twice, and first time 60 DEG C of maintenances 24 hours, is energy conservation after slip casting completes, and adopts air energy heating technique, and second time stream curing, after demoulding 100 DEG C of maintenances 48 hours, adopts solar boiler heating.
The technology path being different from prior art in the present embodiment is:
1. can shorten the construction period of half, the overhead road of city bridge construction of ten kilometers namely within three months, can be completed, can accomplish, without support or limited bracket construction, fundamentally to solve the problem of urban traffic blocking; Girder span weight reduction 50%, bridge foundation is also corresponding with pier stud load to be alleviated, and physical dimension is corresponding reduction also, and construction technology becomes more simple and easy, and speed of application is faster;
2. RPC can be adopted to carry out batch production equally prefabricated for bridge pier column, on-site consolidation, and because dead load alleviates, bridge foundation just can adopt static pressed pile or driven pile, and stake is also prefabricated by batch production;
3. bridge needs to carry out except cast-in-place construction except cushion cap and bridge deck pavement, and other are all buy mill work to carry out on-site consolidation, and the construction period can shorten 50% ~ 70%, will bring significant social benefit;
4. large span stayed-cable bridge, suspension bridge use full RPC corrugated sheet box beam to substitute steel box-girder, both can save great deal of steel, and can avoid steel work later stage protection question again;
5. be applicable to batch production streamline Prefabrication, better quality controls.
The another statement of applicant, the utility model illustrates implementation method of the present utility model and apparatus structure by above-described embodiment, but the utility model is not limited to above-mentioned embodiment, namely do not mean that the utility model must rely on said method and structure could be implemented.Person of ordinary skill in the field should understand; to any improvement of the present utility model; implementation method equivalence selected by the utility model is replaced and the interpolation of step, concrete way choice etc., all drops within protection domain of the present utility model and open scope.
The utility model is not limited to above-mentioned embodiment, and all employings and the utility model analog structure and method thereof realize all embodiments of the utility model object all within the utility model protection domain.
Claims (4)
1. based on the bridge corrugated sheet box beam that full RPC is applied, it is characterized in that, comprise a main structure body, described main structure body is made up of top board, web and base plate, described top board, web and base plate are corrugated sheet, the composite steel silk screen that described corrugated sheet is arranged by the densely covered formula of layer of concrete and inside forms, and described gauze wire cloth is bellows-shaped.
2. the bridge corrugated sheet box beam applied based on full RPC according to claim 1, is characterized in that, described layer of concrete is the RPC layer of pressure.
3. the bridge corrugated sheet box beam applied based on full RPC according to claim 1, it is characterized in that, described gauze wire cloth is made up of high tensile steel wire, and is interconnected by lateral connection steel wire between composite steel silk screen.
4. the bridge corrugated sheet box beam applied based on full RPC according to claim 3, it is characterized in that, described steel wire diameter is 0.1 ~ 0.5mm, and the gap between steel wire is 1 ~ 2mm, described transverse steel wire diameter is 0.5 ~ 1 mm, and intensity is 2 ~ 3 times of powder concrete compressive strength.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520320929.2U CN204728189U (en) | 2015-05-19 | 2015-05-19 | Based on the bridge corrugated sheet box beam that full RPC is applied |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520320929.2U CN204728189U (en) | 2015-05-19 | 2015-05-19 | Based on the bridge corrugated sheet box beam that full RPC is applied |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204728189U true CN204728189U (en) | 2015-10-28 |
Family
ID=54386551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520320929.2U Withdrawn - After Issue CN204728189U (en) | 2015-05-19 | 2015-05-19 | Based on the bridge corrugated sheet box beam that full RPC is applied |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204728189U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104846732A (en) * | 2015-05-19 | 2015-08-19 | 卢国林 | Total-activity powder concrete application-based corrugated plate box beam of bridge |
CN105937203A (en) * | 2016-06-06 | 2016-09-14 | 湖南中路华程桥梁科技股份有限公司 | Reinforced joint structure of interface between reactive powder concrete layer and steel structure layer and construction method of reinforced joint structure |
-
2015
- 2015-05-19 CN CN201520320929.2U patent/CN204728189U/en not_active Withdrawn - After Issue
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104846732A (en) * | 2015-05-19 | 2015-08-19 | 卢国林 | Total-activity powder concrete application-based corrugated plate box beam of bridge |
CN105937203A (en) * | 2016-06-06 | 2016-09-14 | 湖南中路华程桥梁科技股份有限公司 | Reinforced joint structure of interface between reactive powder concrete layer and steel structure layer and construction method of reinforced joint structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102888815B (en) | The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam | |
CN206070562U (en) | Subassembly formula underground structure | |
CN103147385B (en) | Double-spliced extradosed cable-stayed bridge | |
CN203475292U (en) | Arch bridge structure | |
CN202450427U (en) | Variable box variable cross-section continuous rigid frame aqueduct structure | |
CN204728189U (en) | Based on the bridge corrugated sheet box beam that full RPC is applied | |
CN101864731A (en) | Mobile framework equipment | |
CN104846732B (en) | The bridge corrugated sheet box beam applied based on full RPC | |
CN209397803U (en) | A kind of removable steel bar girder laminated floor slab of UHPC ultra-high performance concrete | |
CN201713764U (en) | Movable formwork apparatus | |
CN201686953U (en) | Novel wall fence used for road | |
CN101451380A (en) | Prefabricating common concrete outer plate recycled concrete core shear wall and processing method thereof | |
CN109537775A (en) | The method for preparing assembly concrete shear wall using local corrugated thin-wall steel pipe | |
CN204551172U (en) | A kind of prefabricated road surface of assembled steel reinforced concrete hollow | |
CN202989755U (en) | Integral-casting and fabricated prestressing force bridge structure | |
CN201016157Y (en) | Steel-mixing composite box beam | |
CN104032741B (en) | The rapid constructing method of a kind of hydraulic engineering large volume temperature control | |
CN203593973U (en) | Continuous beam long cast-in-site section bracket balancing method construction device | |
CN205591349U (en) | Strong prestressing tendons's precast concrete beam post node in adoption | |
CN204825656U (en) | Cast -in -place formwork support structure in bridge sound barrier basis | |
CN204000562U (en) | The compound rigid frame bridge of a kind of vertical prestressing steel-concrete | |
CN202849924U (en) | Corrugated steel web plate concrete continuous box girder for curved bridge | |
CN208395634U (en) | A kind of wood-ultra-high performance concrete combined bridge structure | |
CN207211189U (en) | The underground pipe gallery of enhanced 3D printing | |
CN207027858U (en) | A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20151028 Effective date of abandoning: 20160824 |
|
C25 | Abandonment of patent right or utility model to avoid double patenting |