CN204715501U - The interim water draw-off of Assembled environmental type - Google Patents

The interim water draw-off of Assembled environmental type Download PDF

Info

Publication number
CN204715501U
CN204715501U CN201520274937.8U CN201520274937U CN204715501U CN 204715501 U CN204715501 U CN 204715501U CN 201520274937 U CN201520274937 U CN 201520274937U CN 204715501 U CN204715501 U CN 204715501U
Authority
CN
China
Prior art keywords
drain tank
sections
water draw
cell body
environmental type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520274937.8U
Other languages
Chinese (zh)
Inventor
李青
王春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Highway Engineering Group Co Ltd
Original Assignee
Henan Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Highway Engineering Group Co Ltd filed Critical Henan Highway Engineering Group Co Ltd
Priority to CN201520274937.8U priority Critical patent/CN204715501U/en
Application granted granted Critical
Publication of CN204715501U publication Critical patent/CN204715501U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The interim water draw-off of a kind of Assembled environmental type, described water draw-off comprises drain tank sections, the drain tank cell body that described drain tank sections comprises the structure that takes the shape of the letter U and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body of multistage match strap successively.The utility model work progress is simple, and easy accessibility is flexible, and environment pollution is little, and efficiency of construction is high, and cost is extremely low, be convenient to the standard formulation that country realizes the interim standardized production sluiced, and can recycling.Water draw-off of the present utility model itself is also a kind of " scale ", because its physical dimension and segmental length system are according to country's sizing mark design, form through emulating different slope designs, if " built-in groove offered " is incorrect, water draw-off of the present utility model just can not well be installed and spreading, guiding construction that can be useful conversely.

Description

The interim water draw-off of Assembled environmental type
Technical field
The utility model belongs to traffic, municipal administration, hydraulic engineering technical field, relates to the interim water draw-off of a kind of Assembled environmental type specifically.
Background technology
Along with country strengthens infrastructure construction dynamics, the measure of various raising national industry foundation level emerging in large numbers like the mushrooms after rain.Along with this strand of tide, highway, railway, municipal administration and hydraulic engineering construction are unprecedentedly surging especially, but whatsoever engineering all cannot avoid the Pluvial, and " draining " problem that how to solve is the difficult problem that does not obtain thoroughly for a long time, science solves.Traditional interim draining device is all the modes adopting masonry mortar or concrete masonry units, and complex process will be passed through: the construction line-putting, excavation groove, lay prime cement, mortar flag stone, smash slurry, wipe one's face, jointing Deng Ji road technique.Complex process, cost is very high, and efficiency of construction is low, and will along with constantly increasing of banketing and repeatedly spreading.How spreading? repair often and pounded, pounded and repaiied, patched up, its temporary drainage effect is well imagined, the interim water draw-off that many units implement not only can not play the effect of sluicing in rainy season, is even by chance destroyed by rush of water by water herein, become a mere formality completely, become ornaments.And its interim drain tank implemented is multifarious, various, physical dimension disunity, process basis of also will doing over again during permanent structure to be installed, causes cross pollution and inaction to do over again.Somebody even adopts cast iron and steel part, and cost is high, installs difficult.
Meanwhile, the said equipment environment pollution is large, cannot recycling, wastes the efficient resource of country greatly.
More importantly, at present country produces wideling popularize " standardization ", and our country formulates and published many standards, is still blank only at " sluicing " this part temporarily.
Utility model content
The purpose of this utility model is for above-mentioned Problems existing and deficiency, there is provided a kind of work progress simple, easy accessibility is flexible, environment pollution is little, efficiency of construction is high, cost is extremely low, is convenient to the standard formulation that country realizes the interim standardized production sluiced, and can the interim water draw-off of combined type of recycling.
For achieving the above object, the technical scheme taked is:
The interim water draw-off of a kind of Assembled environmental type, described water draw-off comprises drain tank sections, the drain tank cell body that described drain tank sections comprises the structure that takes the shape of the letter U and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body of multistage match strap successively.
Described water draw-off also includes the catchment tray sections overlapped with drain tank segment matches being positioned at top, and described catchment tray sections comprises the variable cross-section catchment tray cell body that cross section is bell mouth shape and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body.
Described drain tank sections is overlapped by the corresponding double buckle that mates be provided with between drain tank sections, between drain tank sections with catchment tray sections, and the described sub-buckle be positioned on drain tank sections or catchment tray sections is pressed on above the box of drain tank sections of the bottom be adjacent, and smear hermetic seal glue in overlapping the slot place.
Described drain tank cell body and the biside plate top of catchment tray cell body be provided with the gradient be 1% ~ 2% charge for remittance shirt rim.
The standard sections that the different lengths size that comprises described drain tank sections does not wait and non-standard sections, and the length of various drain tank sections is 0.5m ~ 2.5m, the length of described catchment tray sections is 0.5m ~ 1.5m.
Multiple tracks deep floor is also provided with bottom described drain tank cell body.
The material of described water draw-off is pp polypropylene.
Take technique scheme, acquired beneficial effect is:
1. product of the present utility model belongs to and tailors according to current China relevant criterion design drawing, until engineering construction reach need permanent water draw-off is installed time, do not need do over again again process, the physical dimension of rebuilding the drain tank of former excavation and structure etc., there is versatility widely, and design has fully taken into account the various complex situations of building-site reality, very flexibly light and handy, compliance is extremely strong, there is the value promoted in the whole nation, and the sections cell body used has recycling function, not only save national resources, and improve efficiency of construction.
2. water draw-off of the present utility model itself is also a kind of " scale ", because its physical dimension and segmental length system are according to country's sizing mark design, form through emulating different slope designs, if " built-in groove offered " is incorrect, water draw-off of the present utility model just can not well be installed and spreading, changes one and says, if smooth installation, just can play inspection " effect whether the works gradient of practice of construction is correct ", guiding construction that can be useful conversely.
3. the utility model theory is exquisite.Because since be interim water draw-off, will distinguish to some extent with " permanent " structure design.Although and be " temporory structure ", because it leaks cruelly under large natural environment, must solve " mechanical property that raw material are good, excellent moulding processability, higher heat resistance, good decay resistance, to absorb water hardly; reactivity worth, quality are impure with most chemicals, nontoxic performance; Good electrical insulation capability and properties of transparency, and pp material itself possesses these performances completely.
4. the length of each sections of the present utility model calculates through Simulation Science, thoroughly breach these puzzled people bottleneck problem for many years, the means of " toner and light agent " can be added in material, produce the interim drain tank that shades of colour is glittering and translucent, give aesthetic feeling, innervation, not hard to imagine, so not only the circumstances that building site is filthy in the past can be changed, stay under such circumstances, as tourist attraction of roaming leisurely, its meaning is inestimable.
The utility model is economical and practical, be based upon completely on the basis of practice, design ingenious, cost is low, easy accessibility, environmental protection, renewable recycling (now cost will be reduced to the limit), not only science solve this global problem, fill up domestic and even the world is blank, and, for country " markization " of this part produce provide hard thick after basis and foundation, to our key industry level of lifting, will be a revolutionary activity.
Accompanying drawing explanation
Fig. 1 is the structural representation of drain tank sections of the present utility model;
Fig. 2 be in Fig. 1 A-A to structural representation.
Fig. 3 be in Fig. 1 B-B to structural representation.
Fig. 4 is the structural representation of catchment tray sections.
Fig. 5 be Fig. 4 look up structural representation.
Fig. 6 is double buckle bridging arrangement schematic diagram.
Fig. 7 is the overlap joint mounting structure schematic diagram of interim water draw-off of the present invention.
Sequence number in figure: 1 be drain tank cell body, 2 be sub-buckle, 3 be box, 4 be anchoring piece, 5 be ribs, 6 be catchment tray cell body, 7 for charge for remittance shirt rim.
Detailed description of the invention
Below in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described in detail.
Embodiment one: as described in Fig. 1 ~ 7, the interim water draw-off of a kind of Assembled environmental type, described water draw-off comprises the multistage drain tank sections of match strap and the catchment tray sections overlapped with drain tank segment matches that is positioned at top successively, the drain tank cell body 1 that described drain tank sections comprises the structure that takes the shape of the letter U and the anchoring piece 4 be arranged on roadbed side slope anchoring bottom cell body, described catchment tray sections comprises the variable cross-section catchment tray cell body 6 that cross section is bell mouth shape and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body, between described drain tank sections and drain tank sections, the corresponding double buckle of coupling by being provided with between drain tank sections with catchment tray sections overlaps, its sub-buckle is the step sunk in drain tank cell body or catchment tray cell body lateral, described box is the step outwards sunk inside drain tank cell body or catchment tray cell body, in the application, the thickness of drain tank cell body and catchment tray cell body is 5mm, wherein sub-buckle sinking thickness is 2mm, box sinking thickness is 3mm, and the described sub-buckle 2 be positioned on drain tank sections or catchment tray sections is pressed on above the box 3 of the drain tank sections of the bottom be adjacent, and smear hermetic seal glue in overlapping the slot place, described drain tank cell body 1 and the biside plate top of catchment tray cell body 6 are provided with the charge for remittance shirt rim 7 that the gradient is 1% ~ 2%.
The standard sections that the different lengths size that comprises described drain tank sections does not wait and non-standard sections, the length specification that wherein drain tank sections is conventional has following three kinds of 0.5m, 1m, 2m, the length of described catchment tray sections is 1m, need the built-in groove of the size of the built-in groove of slope excavation and later stage permanent drain tank measure-alike when this drain tank sections and catchment tray sections are installed, namely after building subgrade construction completes, interim water draw-off is only needed to remove, just directly can carry out the construction operation of permanent drain tank, the material of each sections of described water draw-off is pp polypropylene, meet the time limit that interim water draw-off needs reach its service life, useful life for the interim water draw-off in building subgrade construction process is generally 18 ~ 20 months, the interim water draw-off made by PP polypropylene during this period can reach the good mechanical property of raw material, excellent moulding processability, higher heat resistance, good decay resistance, absorb water hardly, with most chemicals not reactivity worth, quality is pure, nontoxic performance and good electrical insulation capability and properties of transparency.
Construction method of installation of the present utility model is: in building subgrade construction process, for common practice and the requirement of construction both at home and abroad, needs the construction and installation carrying out interim water draw-off for raising higher than the roadbed both sides of 2m, as follows for specifically comprising step:
1. first press design size along slope excavation built-in groove, overlap the drain tank sections that installation length is 2m with upwards pedaling successively from toe, carry out anchoring by anchoring piece;
2. while installation this section of drain tank sections, continue raising roadbed, after the height of the two-layer soil layer of every raising, its length of grade is about the roadbed length of grade of 0.5m or 1m, excavation built-in groove is carried out to the roadbed both sides of newly-increased floor height, and to be overlapped the drain tank sections of new 0.5m or 1m length specification by double buckle with mounted drain tank segment matches, for the overlapping the slot between the adjacent two sections of drain tank sections overlapped, carry out drying cleaning, polishing, and smear hermetic seal glue, and connect by clamp on the shirt rim of adjacent two drain tank sections;
3. step is repeated 2. until when building roadbed earthwork raising height also has certain height apart from the roadbed height preset, now this highly corresponding length of grade length is 1m, stops setting up drain tank sections; Roadbed is filled out for the follow-up increasing to top, excavation built-in groove is carried out to its both sides, and match strap installation length specification is the catchment tray sections of 1m length on the basis of the drain tank sections overlapped; Described catchment tray sections comprises the variable cross-section catchment tray cell body 6 that cross section is bell mouth shape and the anchoring piece 4 be arranged on roadbed side slope anchoring bottom cell body, for catchment tray sections and and the drain tank sections of its overlap joint between overlapping the slot, carry out drying cleaning, polishing, and smear hermetic seal glue.
The overlapping mode of described double buckle is: remain that the sub-buckle be positioned on drain tank sections or catchment tray sections is pressed on above the box of drain tank sections of the bottom be adjacent
Length for overlap joint drain tank sections of the present utility model carries out Reasonable adjustment for different weather, as being in drought work progress in season, by once increasing higher floor height newly, the longer drain tank sections of length specification can be chosen and reduces overlap joint number of times; When being in rainy season, by reducing the newly-increased floor height of single, choosing the drain tank sections that length specification is shorter, increasing overlap joint number of times, contributing to draining timely.
Toner and light agent can be added with in the material of interim water draw-off of the present utility model,, segmental length calculates through Simulation Science, adds the means of color and light agent in material, produce the interim drain tank that shades of colour is glittering and translucent, give aesthetic feeling, innervation.
According to above-mentioned utility model feature, it thoroughly breaks through these puzzled people bottleneck for many years, solve this global problem at one stroke, fill up domestic and even the world is blank, standardized production can be realized simultaneously, to promoting our key industry level, it will be a revolutionary activity, not hard to imagine, so not only the circumstances that building site is filthy in the past can be changed, stay under such circumstances, as tourist attraction of roaming leisurely, its meaning is inestimable, this product belongs to and tailors according to current China relevant criterion design drawing, until engineering construction reach need permanent water draw-off is installed time, do not need process of doing over again again, rebuild the physical dimension and structure etc. of the drain tank of former excavation, there is versatility widely, and design has fully taken into account the various complex situations of building-site reality, very flexibly light and handy, compliance is extremely strong, there is the value promoted in the whole nation, and the sections notch used has recycling function, not only save national resources, and improve efficiency of construction.

Claims (7)

1. the interim water draw-off of Assembled environmental type, it is characterized in that, described water draw-off comprises the drain tank sections of multistage match strap successively, the drain tank cell body that described drain tank sections comprises the structure that takes the shape of the letter U and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body.
2. the interim water draw-off of Assembled environmental type according to claim 1, it is characterized in that, described water draw-off also includes the catchment tray sections overlapped with drain tank segment matches being positioned at top, and described catchment tray sections comprises the variable cross-section catchment tray cell body that cross section is bell mouth shape and the anchoring piece be arranged on roadbed side slope anchoring bottom cell body.
3. the interim water draw-off of Assembled environmental type according to claim 2, it is characterized in that, described drain tank sections is overlapped by the corresponding double buckle that mates be provided with between drain tank sections, between drain tank sections with catchment tray sections, and the described sub-buckle be positioned on drain tank sections or catchment tray sections is pressed on above the box of drain tank sections of the bottom be adjacent, and smear hermetic seal glue in overlapping the slot place.
4. the interim water draw-off of Assembled environmental type according to claim 2, is characterized in that, described drain tank cell body and the biside plate top of catchment tray cell body be provided with the gradient be 1% ~ 2% charge for remittance shirt rim.
5. the interim water draw-off of Assembled environmental type according to claim 2, it is characterized in that, the standard sections that the different lengths size that comprises described drain tank sections does not wait and non-standard sections, and the length of various drain tank sections is 0.5m ~ 2.5m, the length of described catchment tray sections is 0.5m ~ 1.5m.
6. the interim water draw-off of Assembled environmental type according to claim 1, is characterized in that, the bottom of described drain tank cell body is also provided with multiple tracks deep floor.
7. the interim water draw-off of Assembled environmental type according to claim 1, is characterized in that, the material of described water draw-off is pp polypropylene.
CN201520274937.8U 2015-04-30 2015-04-30 The interim water draw-off of Assembled environmental type Active CN204715501U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520274937.8U CN204715501U (en) 2015-04-30 2015-04-30 The interim water draw-off of Assembled environmental type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520274937.8U CN204715501U (en) 2015-04-30 2015-04-30 The interim water draw-off of Assembled environmental type

Publications (1)

Publication Number Publication Date
CN204715501U true CN204715501U (en) 2015-10-21

Family

ID=54314503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520274937.8U Active CN204715501U (en) 2015-04-30 2015-04-30 The interim water draw-off of Assembled environmental type

Country Status (1)

Country Link
CN (1) CN204715501U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790505A (en) * 2015-04-30 2015-07-22 河南省公路工程局集团有限公司 Combined type environment-friendly temporary water draining device and mounting construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790505A (en) * 2015-04-30 2015-07-22 河南省公路工程局集团有限公司 Combined type environment-friendly temporary water draining device and mounting construction method thereof

Similar Documents

Publication Publication Date Title
CN203394170U (en) Prefabricated enclosing wall
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN204551532U (en) Assembling cable shaft
CN204715501U (en) The interim water draw-off of Assembled environmental type
CN110306396A (en) A kind of assembly concrete road surface and construction method
CN202543757U (en) Filling structure for blown sand road foundation
CN107486940A (en) A kind of water channel is passed by one's way the production method of prefabricated component
CN2937300Y (en) FRP vinyl glass fibre reinfroced plastic strengthening rib cage
CN203403434U (en) Basement
CN203284814U (en) Transformer substation prefabricated concrete water-scattering device
CN104790505A (en) Combined type environment-friendly temporary water draining device and mounting construction method thereof
CN202247924U (en) Assembled steel structure open caisson in pipe jacking construction
CN107060040A (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN202672331U (en) Prefabricated reinforced concrete circular grit well
CN203346857U (en) Prefabricated part for trapezoid channel lining
CN204530375U (en) Novel interlocked impervious concrete precast curb
CN201381518Y (en) Standard integral outdoor equipment well
CN202830968U (en) Building blocks and prefabricated underground continuous wall
CN207619919U (en) A kind of assembled eco-embankment structure
CN202865802U (en) Flexible channel
CN209144964U (en) A kind of efficient rainwater isolation collection device
CN208933775U (en) Water-permeable brick wet-laying pavement
CN207775818U (en) A kind of anchoring grid bank protection
CN102852063B (en) concrete block and construction method for road construction
CN202543759U (en) Concrete block for road construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant