CN204676578U - The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting - Google Patents

The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting Download PDF

Info

Publication number
CN204676578U
CN204676578U CN201520230733.4U CN201520230733U CN204676578U CN 204676578 U CN204676578 U CN 204676578U CN 201520230733 U CN201520230733 U CN 201520230733U CN 204676578 U CN204676578 U CN 204676578U
Authority
CN
China
Prior art keywords
hole
curtain
disturbed
dam foundation
belts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520230733.4U
Other languages
Chinese (zh)
Inventor
张伟狄
徐建荣
吴关叶
何世海
周垂一
何明杰
祝青
唐鸣发
石安池
王建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201520230733.4U priority Critical patent/CN204676578U/en
Application granted granted Critical
Publication of CN204676578U publication Critical patent/CN204676578U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model relates to a kind of curtain hole and cuts the dam foundation containing many disturbed belts oozing hole Combined Protection.The purpose of this utility model is by co-design, thus realizes ensureing on basis to the seepage preventing effect of weak low-angle dip disturbed belt, reach reduce dam foundation cavern quantity, speed up the work, the object of cost saving.The technical solution of the utility model is: the dam foundation containing many disturbed belts of hole Combined Protection is oozed in a kind of curtain hole with cutting; in basement rock below dam top, different elevation distributes many weak low-angle dip disturbed belts; described weak low-angle dip disturbed belt is arranged curtain hole and Jian Jieshen hole, curtain hole; be connected by grouted cut off wall between each layer curtain hole or between curtain hole with Jian Jieshen hole, curtain hole, the lower end of grouted cut off wall is positioned at lower floor's hole upstream side 5 ~ 10m scope and is connected by the level overlap joint curtain in lower floor hole.The utility model is applicable to dam foundation and there is the weak low-angle dip disturbed belt that many may form leakage passage.

Description

The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting
Technical field
The utility model relates to Hydraulic and Hydro-Power Engineering, and the dam foundation containing many disturbed belts of hole Combined Protection is oozed in especially a kind of curtain hole with cutting.Be applicable to dam foundation and there is the weak low-angle dip disturbed belt that many may form leakage passage.
Background technology
Along with the development of national economy, China builds Hydraulic and Hydro-Power Engineering in a large number, dam is the water retaining structure of multi-purpose project, in the design process for strengthening the process of basic seepage flow, usually in dam foundation arranging multiplayer curtain grouting hole, basic seepage flow is stopped by each layer curtain grouting basis of formation curtain; If there are many larger weak low-angle dip disturbed belts in basis, curtain grouting is poor for larger weak low-angle dip disturbed belt sealing effect, under the effect of high water head, still may there is larger seepage discharge along disturbed belt, bring potential safety hazard to the permanent operation of dam.
The processing mode of prior art as shown in Figure 1, run into the above-mentioned rock matter basis that there is larger weak low-angle dip disturbed belt, usually can adopt the design of the disturbed belt 5 on basic curtain axis being arranged and cutting and oozing hole 10, and in the 6-1 of curtain hole, upper strata, bore curtain grouting hole through cutting the processing method of oozing hole; Said method need ensure curtain boring through cut ooze hole, to boring required precision high, if and the disturbed belt number of plies is more, what dam foundation inside need be arranged cut, and to ooze hole also more, corresponding increase hole is dug and concrete backfill engineering quantity, and hole is dug explosion and can be caused the lax of periphery rock mass thus affect base rock integrality, increase curtain grouting difficulty.
Summary of the invention
The technical problems to be solved in the utility model is: provide a kind of curtain hole and cut the dam foundation containing many disturbed belts oozing hole Combined Protection; be intended to pass through co-design; thus realize ensureing on basis to the seepage preventing effect of weak low-angle dip disturbed belt, reach reduce dam foundation cavern quantity, speed up the work, the object of cost saving.
The technical scheme that the utility model adopts is: the dam foundation containing many disturbed belts of hole Combined Protection is oozed in a kind of curtain hole with cutting; in basement rock below dam top, different elevation distributes many weak low-angle dip disturbed belts; it is characterized in that: on described weak low-angle dip disturbed belt, arrange curtain hole and Jian Jieshen hole, curtain hole; be connected by grouted cut off wall between each layer curtain hole or between curtain hole with Jian Jieshen hole, curtain hole, the lower end of grouted cut off wall is positioned at lower floor's hole upstream side 5 ~ 10m scope and is connected by the level overlap joint curtain in lower floor hole.
The lining thickness in Jian Jieshen hole, described curtain hole is 1 ~ 1.5m.
At the bottom of upstream side excavation hole and the distance controlling of weak low-angle dip disturbed belt between 1.5 ~ 2.0m.
The beneficial effects of the utility model are: ooze the combination in hole by curtain hole with cutting, can reduce and ooze hole quantity containing cutting of many weak low-angle dip disturbed belt dam rock matter bases, thus reduce hole and dig the lax impact of explosion on basis, increase the globality of the dam foundation; Curtain hole is doubled as and oozes hole be arranged in grouted cut off wall downstream for cutting, dual section can be formed to weak low-angle dip disturbed belt and ooze protection (grouted cut off wall+curtain hold concurrently section ooze hole).By dam foundation curtain hole being doubled as the co-design of cutting and oozing hole, ensure that the seepage preventing effect of the weak low-angle dip disturbed belt of the dam foundation, and effectively reduce cavern's quantity in the dam foundation thus speed up the work, cost saving, what this technology can be a large amount of are applied to exists many weaknesses and delays in the design of Hydraulic and Hydro-Power Engineering scheme selection of the disturbed belt that inclines.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model background technology.
Fig. 2 is that the utility model curtain (cut and ooze) hole is along dam foundation curtain line spread figure.
Fig. 3 is that the utility model curtain (cut and ooze) hole is along dam foundation sectional drawing (A-A section).
Fig. 4 is the utility model curtain (cut and ooze) hole typical section figure.
Detailed description of the invention
As shown in Figure 2, the present embodiment comprises original place upper thread 1, dam foundation face 2, dam top 3 and dam transverse joint 4 containing the dam foundation of many disturbed belts, and in the basement rock of dam top less than 3, different elevation is distributed with three weak low-angle dip disturbed belts 5.The present embodiment is arranged at the dam foundation and three curtain hole 6-1 and weak low-angle dip disturbed belt 5 is arranged three curtain holes Jian Jieshen hole 6-2.
As shown in Figure 3, be connected by grouted cut off wall 7 between each layer curtain hole 6-1 or between curtain hole 6-1 with Jian Jieshen hole, curtain hole 6-2, grouted cut off wall 7 extends within the scope of the upstream side 5 ~ 10m in lower floor hole at the bottom of the hole in hole, upper strata, and the bottom of grouted cut off wall 7 is overlapped with lower floor hole by the level overlap joint curtain 8 in lower floor hole again.
As shown in Figure 4, described curtain hole 6-1 and Jian Jieshen hole, curtain hole 6-2 all adopts C30 concrete lining, wherein the lining thickness of curtain hole Jian Jieshen hole 6-2 is that 1 ~ 1.5m (thickeies lining cutting raising section and oozes seepage paths, ensure seepage preventing effect), all the other curtain hole 6-1 lining thicknesses are 0.5m.
Except adopting, label is C30 to Jian Jieshen hole, curtain hole 6-2, seepage-resistant grade is except the graduation two concrete of W10, upstream side excavates at the bottom of hole and the distance of weak low-angle dip disturbed belt also should control between 1.5 ~ 2.0m, to ensure that cutting of lining concrete oozes seepage paths length.

Claims (3)

1. a curtain hole with cut the dam foundation containing many disturbed belts oozing hole Combined Protection, in the following basement rock of dam top (3), different elevation distributes many weak low-angle dip disturbed belts (5), it is characterized in that: in described weak low-angle dip disturbed belt (5) upper layout curtain hole (6-1) and Jian Jieshen hole, curtain hole (6-2), be connected by grouted cut off wall (7) between each layer curtain hole (6-1) or between curtain hole (6-1) with Jian Jieshen hole, curtain hole (6-2), the lower end of grouted cut off wall (7) is positioned at lower floor's hole upstream side 5 ~ 10m scope and is connected by level overlap joint curtain (8) in lower floor hole.
2. curtain hole according to claim 1 with cut ooze hole Combined Protection containing the dam foundation of many disturbed belts, it is characterized in that: the lining thickness in Jian Jieshen hole, described curtain hole (6-2) is 1 ~ 1.5m.
3. curtain hole according to claim 1 and 2 with cut ooze hole Combined Protection containing the dam foundation of many disturbed belts, it is characterized in that: at the bottom of upstream side excavation hole and the distance controlling of weak low-angle dip disturbed belt between 1.5 ~ 2.0m.
CN201520230733.4U 2015-04-16 2015-04-16 The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting Active CN204676578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520230733.4U CN204676578U (en) 2015-04-16 2015-04-16 The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520230733.4U CN204676578U (en) 2015-04-16 2015-04-16 The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting

Publications (1)

Publication Number Publication Date
CN204676578U true CN204676578U (en) 2015-09-30

Family

ID=54176283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520230733.4U Active CN204676578U (en) 2015-04-16 2015-04-16 The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting

Country Status (1)

Country Link
CN (1) CN204676578U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970966A (en) * 2016-05-17 2016-09-28 中国电建集团华东勘测设计研究院有限公司 Excavation construction method for weak disturbed belt at foundation of super-high arch dam
CN109440790A (en) * 2018-11-30 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The deep understable high rock slope comprehensive strengthening method of off-load
CN109914459A (en) * 2019-04-17 2019-06-21 黄河勘测规划设计研究院有限公司 A kind of ultra-deep dam foundation grout curtain structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105970966A (en) * 2016-05-17 2016-09-28 中国电建集团华东勘测设计研究院有限公司 Excavation construction method for weak disturbed belt at foundation of super-high arch dam
CN105970966B (en) * 2016-05-17 2018-02-02 中国电建集团华东勘测设计研究院有限公司 A kind of excavation construction method of extra-high arch dam foundation weakness disturbed belt
CN109440790A (en) * 2018-11-30 2019-03-08 中国电建集团华东勘测设计研究院有限公司 The deep understable high rock slope comprehensive strengthening method of off-load
CN109440790B (en) * 2018-11-30 2024-01-26 中国电建集团华东勘测设计研究院有限公司 Comprehensive reinforcement method for deep unloading understable rock high slope
CN109914459A (en) * 2019-04-17 2019-06-21 黄河勘测规划设计研究院有限公司 A kind of ultra-deep dam foundation grout curtain structure
CN109914459B (en) * 2019-04-17 2024-03-12 黄河勘测规划设计研究院有限公司 Ultra-deep dam foundation grouting curtain structure

Similar Documents

Publication Publication Date Title
CN103291325B (en) The preventing control method of Coal-mining Above Confined-water floor strata gushing water
CN107956509B (en) Method for preventing wind leakage by stages in roof cutting gob-side entry retaining
CN204023501U (en) A remove dangerous and consolidate prevention of seepage processing structure for earth and rockfill dam
CN103835723B (en) Pit shaft passes through the comprehensive pre-administering method on stratum, goaf
CN107762533A (en) A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel
CN103899350B (en) Fully mechanized coal face frame carries top coal gas drainage system
CN204676578U (en) The dam foundation containing many disturbed belts of hole Combined Protection is oozed in curtain hole with cutting
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN103291313A (en) Arch crown pressure supporting system of excavation of earth pressure shield and construction method thereof
CN102797468B (en) Minimum over-burden originating method for shield tunnel
CN105544508A (en) Cast-in-place pile applicable to karst region having communicating channels
CN105715277A (en) Construction device and method for shield tunnel
CN205894027U (en) Structure is oozed in cutting of power station underground factory building
CN103291312A (en) Shield tunneling machine capable of realizing three-dimensional grouting
CN105909265A (en) Heaving-prevention retrusive deep-hole grouting system and method for passing through existing shield tunnel
CN105155472A (en) Dam foundation anti-seepage structure of deep overlying layer earth-rock dam and construction method of dam foundation anti-seepage structure
CN103114602B (en) Foundation pit waterproof curtain achieving secondary melting mending through seepage dipping poly condensation bonding bodies and construction method
CN203515594U (en) Additive injection port of shield tunneling machine cutter head
CN204212168U (en) Dam water retaining structure for jointly building dam by utilizing karst cave
CN203835412U (en) Underwater-roadway leakage processing structure
CN203347799U (en) Shield tunneling machine capable of achieving three-dimensional grouting
CN202131603U (en) Seepage interception structure applied to weak interbed or fracture zone in batholite
CN112832821B (en) Fracture surface supporting method based on high pressure water fault fracture zone rheological research
CN202323899U (en) Arrangement structure for underground gate chambers of diversion tunnels
CN204782797U (en) Multiinjector drill bit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant