CN204662922U - For the movable integral type scaffold of box-structure - Google Patents

For the movable integral type scaffold of box-structure Download PDF

Info

Publication number
CN204662922U
CN204662922U CN201520370738.7U CN201520370738U CN204662922U CN 204662922 U CN204662922 U CN 204662922U CN 201520370738 U CN201520370738 U CN 201520370738U CN 204662922 U CN204662922 U CN 204662922U
Authority
CN
China
Prior art keywords
standpipe
transverse tube
box
integral type
type scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520370738.7U
Other languages
Chinese (zh)
Inventor
何俨
杨洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201520370738.7U priority Critical patent/CN204662922U/en
Application granted granted Critical
Publication of CN204662922U publication Critical patent/CN204662922U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a kind of movable integral type scaffold for box-structure, it comprises the standpipe of the longitudinal setting of some rows and horizontally disposed transverse tube, transverse tube and the standpipe of each row are equipped with at least three row, described transverse tube is connected mutually with standpipe joint, form a cube, it is characterized in that, the lower end of every root standpipe is all provided with a carriage; The two ends of every root transverse tube and the upper end of standpipe are all provided with a telescoping drawbar, are all provided with a supporting plate above telescoping drawbar.The movable integral type scaffold for box-structure that the utility model obtains has to be convenient to move, and does not need the advantage repeating to set up scaffold when box-structure is constructed.

Description

For the movable integral type scaffold of box-structure
Technical field
The utility model relates to a kind of scaffold, especially for the movable integral type scaffold of box-structure.
Background technology
The scaffold support system adopted in current industry is set up mode and is generally: unwrapping wire, and---vertical standpipe---------install top cylinder---installation form---to reinforce horizon bar by bridging.In concrete engineering application example, when running into the construction longer box-structure of length, (above-mentioned box-structure has following features: breadth of section is generally less than 10 meters; This is axially the consistent curve of line style straight line or radian; Prolong each changes of section of axis little), adopt usual manner to have following shortcoming: 1, each construction section needs to repeat to set up scaffold, and scaffold can not be reused, and installation workload is large; 2, the transverse tube of scaffold and the length of standpipe are all fixing, can not do accommodation according to field condition, and steel pipe can not repeatability utilize, and wastage is very big; 3, when template horizontal plane jacking is conventional jacking, jacking easily loosens.
Summary of the invention
The purpose of this utility model is to solve the problem that existing scaffold installation workload is large, can not reuse, and a kind of movable integral type scaffold for box-structure provided.
To achieve these goals, the movable integral type scaffold for box-structure designed by the utility model, it comprises the standpipe of the longitudinal setting of some rows and horizontally disposed transverse tube, transverse tube and the standpipe of each row are equipped with at least three row, described transverse tube is connected mutually with standpipe joint, form a cube, it is characterized in that, the lower end of every root standpipe is all provided with a carriage; The two ends of every root transverse tube and the upper end of standpipe are all provided with a telescoping drawbar, are all provided with a supporting plate above telescoping drawbar.
Further, for the ease of adapting to setting up of the box-structure template of different in width and height, simultaneously, can adjust in real time according to the demand of scene height and width, described telescoping drawbar is included in transverse tube or standpipe and coordinates the adjustable mounting support installed, the screw rod matched with adjustable mounting support, and described adjustable mounting support comprises a mounting cylinder, be symmetricly set on mounting cylinder both sides and two of semicircular in shape buckles and be connected with mounting cylinder and be positioned at the setscrew nut of buckle; Described buckle is connected to the mounting cylinder left and right sides all turnably and end is fixedly connected with by bolt, after two buckles are closed cylindrically, for clamping standpipe or transverse tube; Described setscrew nut and transverse tube or standpipe socket-connect, and its centre bore and screw rod are threaded connection.
Further, be also provided with a telescoping drawbar in the lower end of every root standpipe, described pulley is by being connected by this telescoping drawbar standpipe corresponding thereto.This pulley and telescoping drawbar stable connection, can guarantee that scaffold is steadily quick when moving to next construction section.
Further, each pulley is all provided with one in the buckle being inverted U-shaped, the screw rod of the telescoping drawbar of every root lower riser end is all fixedly connected with an installing plate, and described buckle and installing plate are bolted to connection.This structure design can guarantee pulley and screw rod stable connection, is convenient to again later stage replacing pulley.
Further, in order to increase slide plane when scaffold moves, simultaneously, guarantee that scaffold remains at middle part in moving process, do not produce skew, the end of the telescoping drawbar of row's transverse tube is all fixedly connected with a spring bottom, is fixedly connected with a roller at the end of spring.
Further, in order to ensure the intensity of whole scaffold, the distance between adjacent two transverse tubes is 1-1.5m, and the distance of adjacent two standpipes is 0.8-1.2m.
Further, for the ease of fixing and unlatching buckle, in adjustable mounting support, all outwards bending of the end of each buckle, forms a bending part, is equipped with a through hole in the middle part of bending part, and described buckle is by closed together after bolt-through through hole.
Compared with prior art, the movable integral type scaffold tool for box-structure that the utility model obtains has the following advantages:
1, scaffold only need be installed once, in the different construction section repeated application of box-structure, can decrease time and the installation workload of scaffold building.
2, scaffold is all-in-one-piece, is also provided with pulley in the below of the every root standpipe of scaffold, is convenient to after a construction section completes, adopt draw-gear that scaffold is moved integrally next construction section, conveniently moving, simple, time saving and energy saving.
3, by descending most on row's transverse tube to arrange spring, and at the end of spring, roller is installed, not only can increase the slide plane of scaffold, impel scaffold to be more prone to slide, and by the roller at two ends can guarantee whole system move in plane positioning, avoid building face superior displacement.
Accompanying drawing explanation
Fig. 1 is the structural representation of movable integral type scaffold in embodiment;
Fig. 2 is the syndeton schematic diagram of embodiment neutral tube upper end and telescoping drawbar, supporting plate;
Fig. 3 is the syndeton schematic diagram of embodiment neutral tube lower end and telescoping drawbar, pulley, buckle;
Fig. 4 is the syndeton schematic diagram of transverse tube end and telescoping drawbar, spring and roller bottom in embodiment;
Fig. 5 is the structural representation in embodiment after telescoping drawbar installation;
Fig. 6 is structural representation when adjustable mounting support launches in embodiment;
Fig. 7 is movable integral type scaffold mobile status schematic diagram in construction works in embodiment.
In figure: standpipe 1, transverse tube 2, adjustable mounting support 3, mounting cylinder 31, buckle 32, setscrew nut 33, bolt 34, centre bore 35, bending part 36, through hole 37, screw rod 4, supporting plate 5, pulley 6, buckle 7, installing plate 8, spring 9, roller 10, draw-gear 11, wire rope 12.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further illustrated.
Embodiment:
The movable integral type scaffold for box-structure that the present embodiment provides, as shown in Fig. 1 ~ Fig. 6, it comprises standpipe 1 and the horizontally disposed transverse tube 2 of the longitudinal setting of some rows, transverse tube 2 and the standpipe 1 of each row are equipped with at least three row, described transverse tube 2 is connected mutually with standpipe 1 joint, form a cube, in the lower end of every root standpipe 1, a pulley 6 is all installed; At the two ends of every root transverse tube 2 and the upper end of standpipe 1, a telescoping drawbar is all installed, a supporting plate 5 is all installed above telescoping drawbar; Described telescoping drawbar comprises and coordinates the adjustable mounting support 3 installed, the screw rod 4 matched with adjustable mounting support 3 with transverse tube 1 or standpipe 2, and described adjustable mounting support 3 comprises a mounting cylinder 31, be symmetricly set on mounting cylinder 31 both sides and two of semicircular in shape buckles 32 and be connected with mounting cylinder 1 and be positioned at the setscrew nut 33 of buckle 32; Described buckle 32 is connected to mounting cylinder 31 left and right sides all turnably and end is fixedly connected with by bolt 34, after two buckles 32 are closed cylindrically, for clamping standpipe 1 or transverse tube 2; Described setscrew nut 33 socket-connects with transverse tube 1 or standpipe 2, and the centre bore 35 of setscrew nut 33 is threaded connection with screw rod 4.
In the present embodiment, in order to strengthen the adjustment of whole scaffold in short transverse, as shown in Figure 3, be also provided with a telescoping drawbar in the lower end of every root standpipe 1, pulley 6 is by being connected by this telescoping drawbar standpipe 1 corresponding thereto.
Above-mentioned pulley 6 with the concrete syndeton of standpipe 1 is: on each pulley 6, be all provided with one in the buckle 7 being inverted U-shaped, the screw rod 4 of the telescoping drawbar of every root standpipe 1 lower end is all fixedly connected with an installing plate 8, and described buckle 7 and installing plate 8 are bolted to connection.In the present embodiment, screw rod 4 and installing plate 8 are by being welded together.
As shown in Figure 4, be all fixedly connected with a spring 9 at the end of telescoping drawbar of row's transverse tube 2 bottom, be fixedly connected with a roller 10 at the end of spring 9.
In order to ensure the intensity of scaffold, the distance between adjacent two transverse tubes 2 is 1-1.5m, and the distance of adjacent two standpipes 1 is 0.8-1.2m.Meanwhile, the outer the inside of scaffold is also installed with multipair bridging (not marking in figure).
For the ease of opening and fastening buckle 32, the end of each buckle 32 all outwards bending in adjustable mounting support 3, form a bending part 36, be equipped with a through hole 37 in the middle part of bending part 36, described buckle 32 is closed together after running through through hole 37 by bolt 34.
Below, be explained as follows with regard to the concrete mounting method of movable integral type scaffold in the present embodiment:
The first step, support system has been set up by cross section at the first construction section, it specifically sets up process: (a, establishment standpipe are set up a little: building on shaping base plate, inwardly indicate along both sides shear wall the standpipe being parallel to this shear wall 300-500mm and set up line, then indicate the horizontal line setting up line intersecting vertical with standpipe according to the distance of construction section, what horizontal line and standpipe set up that line intersection is standpipe sets up a little; B, determine standpipe 1 set up position after, all telescoping drawbar is installed at the two ends of standpipe 1, and screw rod 4 end of one end telescoping drawbar installs pulley 6 wherein, the other end installs supporting plate 5, then one end of band pulley 6 is stood on the ground, and mobile standpipe 1, arrange standpipe 1 position, standpipe 1 arranges the brake of rear faster pulley 6; C, bottom standpipe 1, one row's transverse tube 2 is transversely set apart from 300mm-500mm place, ground, and at the two ends of this row's transverse tube 2, telescoping drawbar, spring 9 and roller 10 are installed, roller 10 is offseted with the shear wall inwall of bottom, then prolongs short transverse and set up transverse tube 2 successively).
In the specific implementation, pulley 9 adopts universal wheel, is convenient to fixing and mobile.Meanwhile, at the two ends of transverse tube 2, telescoping drawbar and supporting plate 5 also can be installed, thus realize the adjustment of scaffold lateral length.
All standpipes 1 lower end in the present embodiment is all provided with a pulley 6, in construction works, after a staged construction, multiple draw-gear 12 can be set at the rear of next construction section, and by wire rope 11, draw-gear 12 is connected with scaffold, then start draw-gear 12, drive scaffold to move integrally (as shown in Figure 7).
Simultaneously, the two ends of scaffold standpipe 1 are all provided with telescoping drawbar, and in telescoping drawbar, standpipe 1 is firmly held tightly after fastening by buckle 32, and setscrew nut 33 and screw rod 4 are threaded connection again, make standpipe 1 and screw rod 4 connect into an entirety, firm shape is good.Meanwhile, when standpipe 1 and transverse tube 2 length inadequate time, when supporting plate 5 can not press closer the template that the later stage sets up, by rotating setscrew nut 33, screw rod 4 is unclamped, then after moving up and down screw rod 4 to correct position, then rotate setscrew nut 33 screw rod 4 is held tightly, realize the object of adjustment.
Finally it should be noted that, above embodiment is only in order to illustrate the technical solution of the utility model but not restriction technologies scheme, although applicant has been described in detail the utility model with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, those are modified to the technical solution of the utility model or equivalent replacement, and do not depart from aim and the scope of the technical program, all should be encompassed in the middle of right of the present utility model.

Claims (7)

1. the movable integral type scaffold for box-structure, it comprises standpipe (1) and the horizontally disposed transverse tube (2) of the longitudinal setting of some rows, transverse tube (2) and the standpipe (1) of each row are equipped with at least three row, described transverse tube (2) is connected mutually with standpipe (1) joint, form a cube, it is characterized in that, in the lower end of every root standpipe (1), a pulley (6) is all installed; At the two ends of every root transverse tube (2) and the upper end of standpipe (1), a telescoping drawbar is all installed, a supporting plate (5) is all installed above telescoping drawbar.
2. the movable integral type scaffold for box-structure according to claim 1, it is characterized in that, described telescoping drawbar comprises and coordinates the adjustable mounting support (3) installed, the screw rod (4) matched with adjustable mounting support (3) with transverse tube (1) or standpipe (2), and described adjustable mounting support (3) comprises a mounting cylinder (31), be symmetricly set on mounting cylinder (31) both sides and two of semicircular in shape buckles (32) and be connected with mounting cylinder (1) and be positioned at the setscrew nut (33) of buckle (32); Described buckle (32) is connected to mounting cylinder (31) left and right sides all turnably and end is fixedly connected with by bolt (34), after two buckles (32) are closed cylindrically, for clamping standpipe (1) or transverse tube (2); Described setscrew nut (33) socket-connects with transverse tube (1) or standpipe (2), and its centre bore (35) and screw rod (4) are threaded connection.
3. the movable integral type scaffold for box-structure according to claim 1 and 2, it is characterized in that, also be provided with a telescoping drawbar in the lower end of every root standpipe (1), described pulley (6) is by being connected by this telescoping drawbar standpipe corresponding thereto (1).
4. the movable integral type scaffold for box-structure according to claim 1, it is characterized in that, each pulley (6) is all provided with one in the buckle (7) being inverted U-shaped, the screw rod (4) of the telescoping drawbar of every root standpipe (1) lower end is all fixedly connected with an installing plate (8), and described buckle (7) and installing plate (8) are bolted to connection.
5. the movable integral type scaffold for box-structure according to claim 1 and 2, it is characterized in that, the end of the telescoping drawbar of row's transverse tube (2) is all fixedly connected with a spring (9) bottom, is fixedly connected with a roller (10) at the end of spring (9).
6. the movable integral type scaffold for box-structure according to claim 1 and 2, is characterized in that, the distance between adjacent two transverse tubes (2) is 1-1.5m, and the distance of adjacent two standpipes (1) is 0.8-1.2m.
7. the movable integral type scaffold for box-structure according to claim 1, it is characterized in that, the end of each buckle (32) all outwards bending in adjustable mounting support (3), form a bending part (36), be equipped with a through hole (37) at bending part (36) middle part, it is closed together afterwards that described buckle (32) runs through through hole (37) by bolt (34).
CN201520370738.7U 2015-06-02 2015-06-02 For the movable integral type scaffold of box-structure Expired - Fee Related CN204662922U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520370738.7U CN204662922U (en) 2015-06-02 2015-06-02 For the movable integral type scaffold of box-structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520370738.7U CN204662922U (en) 2015-06-02 2015-06-02 For the movable integral type scaffold of box-structure

Publications (1)

Publication Number Publication Date
CN204662922U true CN204662922U (en) 2015-09-23

Family

ID=54133317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520370738.7U Expired - Fee Related CN204662922U (en) 2015-06-02 2015-06-02 For the movable integral type scaffold of box-structure

Country Status (1)

Country Link
CN (1) CN204662922U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989091A (en) * 2015-06-02 2015-10-21 中冶建工集团有限公司 Movable scaffold and construction process for pouring frame building through movable scaffold
CN108867418A (en) * 2018-07-23 2018-11-23 重庆建工市政交通工程有限责任公司 A kind of movable units support frame and the construction method for box-structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989091A (en) * 2015-06-02 2015-10-21 中冶建工集团有限公司 Movable scaffold and construction process for pouring frame building through movable scaffold
CN108867418A (en) * 2018-07-23 2018-11-23 重庆建工市政交通工程有限责任公司 A kind of movable units support frame and the construction method for box-structure

Similar Documents

Publication Publication Date Title
CN202731297U (en) Adjustable beam form support jacking bracket apparatus
CN203640309U (en) Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame
CN204174935U (en) A kind of outer wall of basement one side formwork supporting and protection structure
CN202467183U (en) Clamping and fixing device of reinforced concrete beam steel formwork
CN103586618A (en) Large pipe welding platform
CN104963412A (en) Hinge station plate-type support and mounting method thereof
CN203991789U (en) The special equipment for straightening of semi-automatic steel tubes
CN103397703A (en) Step type aluminum alloy node device and assembling method thereof
CN204662922U (en) For the movable integral type scaffold of box-structure
CN203867158U (en) Cantilever type scaffold structure with positioning plug for fixation
CN204603626U (en) The flange of steel tube tower and C template positioner
CN204609266U (en) A kind of Mobile operating platform for the construction of piping lane comprehensive pipeline
CN204703928U (en) A kind of formwork jumbo for tunnel sidewalls construction
CN204081475U (en) A kind of adjustable floor one-piece keel structure
CN204675785U (en) A kind of adjustable platform
CN204385628U (en) Bridge support frame
CN203429801U (en) Ladder type aluminum alloy node device
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN203380228U (en) Inner support device for production of pressure steel pipe
CN206693617U (en) A kind of building template securing device
CN203961092U (en) The anti-braced structures of a kind of suspension rod
CN205349372U (en) For a short time, construct to fold friendship tunnel controllable gate shaped steel frame apart from shield only
CN203795824U (en) Suspension type fastener scaffold erecting device
CN103276889B (en) Full hall fastener type steel pipe scaffold anti-side shifting method
CN203361596U (en) Auxiliary support of integrated lifting operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150923

Termination date: 20160602