CN204454337U - A kind of building operation Multifunctional tower crane - Google Patents

A kind of building operation Multifunctional tower crane Download PDF

Info

Publication number
CN204454337U
CN204454337U CN201420760939.3U CN201420760939U CN204454337U CN 204454337 U CN204454337 U CN 204454337U CN 201420760939 U CN201420760939 U CN 201420760939U CN 204454337 U CN204454337 U CN 204454337U
Authority
CN
China
Prior art keywords
water pipe
crane arm
arm
suspension bracket
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420760939.3U
Other languages
Chinese (zh)
Inventor
宋星
许潘东
龚丽丽
谷李魁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sihong County Electromechanical Irrigation Management Master Station
Original Assignee
Sihong County Electromechanical Irrigation Management Master Station
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sihong County Electromechanical Irrigation Management Master Station filed Critical Sihong County Electromechanical Irrigation Management Master Station
Priority to CN201420760939.3U priority Critical patent/CN204454337U/en
Application granted granted Critical
Publication of CN204454337U publication Critical patent/CN204454337U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

The utility model discloses a kind of building operation Multifunctional tower crane, comprise pedestal, suspension bracket, equilibrium arm, operator's compartment and crane arm, the both sides of what described equilibrium arm and crane arm balanced respectively be erected at suspension bracket, erect in described suspension bracket and installed water pipe, horizontally in described crane arm be provided with water pipe, uniform multiple shower nozzle on water pipe horizontal in described crane arm, the forearm of described crane arm is provided with a carriage, described carriage is arranged with suspension hook, described suspension hook has hawser, described hawser is connected with concrete-agitating case, described crane arm end and suspension hook are provided with monitoring probe, the utility model is except having handling function, can also infiltrate to the cement concrete of building watering by spraying water smoke, cooling, or spray for dust suppression.

Description

A kind of building operation Multifunctional tower crane
Technical field
The utility model belongs to construction implement field, particularly a kind of building operation Multifunctional tower crane.
Background technology
Tower crane is a kind of weight-lifting equipment conventional in current building construction process, its structure is provided with equilibrium arm on suspension bracket, crane arm and operator's compartment, crane arm is provided with suspension hook, equilibrium arm is provided with counterweight, lift by crane comparatively heavy articles time, larger to the moment of flexure of ground, thus very high to the processing requirements of ground, general tower crane can only hang and get material, reinforcing bar, sheet material etc., the concreting work in high-altitude can not be carried out, and can not infiltrate for the cement concrete of building, cooling, the degree of utilization of tower crane is low, when skyscraper building site tower crane works, because distance ground is far away, generally to be worked in coordination with by surface personnel by interphone or visually substantially judge to operate, very not science, easily there is accident, cause casualties.
Utility model content
The purpose of this utility model is to provide a kind of building operation Multifunctional tower crane, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, the utility model provides following technical scheme:
A kind of building operation Multifunctional tower crane, comprise pedestal, suspension bracket, equilibrium arm, operator's compartment and crane arm, described suspension bracket is fixed on pedestal, described operator's compartment is arranged on suspension bracket, the both sides of what described equilibrium arm and crane arm balanced respectively be erected at suspension bracket, erect in described suspension bracket and installed water pipe, horizontally in described crane arm be provided with water pipe, uniform multiple shower nozzle on water pipe horizontal in described crane arm, in described tower crane, the perpendicular water pipe put is connected by swivel joint in operator's compartment with water pipe horizontal in crane arm, and junction is provided with pressure regulating valve, described equilibrium arm is provided with fixed weight and mobile counterweight, the forearm of described crane arm is provided with a carriage, described carriage is by pulley horizontal slip on the guide rail of crane arm, described carriage is arranged with suspension hook, described suspension hook has hawser, described hawser is connected with concrete-agitating case, the top of described concrete-agitating case is provided with cover cap, described concrete-agitating case inside is provided with mixing device, discharging opening is provided with bottom described concrete-agitating case, described discharging opening is connected with passage, described crane arm end and suspension hook are provided with monitoring probe, controller and monitor screen is provided with in described operator's compartment, described monitoring probe wireless connections monitor screen, described mixing device is connected with controller.
As further program of the utility model: one end of described water pipe connects running water inlet, is provided with shutoff valve and water pump between described running water inlet and water pipe.
As the utility model further scheme: described suspension hook is provided with safe tongue.
The invention also discloses a kind of manufacture method of building operation Multifunctional tower crane, comprise following technology and step:
1) with steel-pipe welding unit suspension bracket, suspension bracket is arranged on pedestal, lifting joint is set in the upper end of suspension bracket, lifting joint top arranges rotating mechanism, setting operation room above rotating mechanism, and operator's compartment front portion arranges crane arm, operator's compartment rear portion arranges equilibrium arm, crane arm and equilibrium arm are erected at the both sides of suspension bracket respectively, and as required, interval certain altitude arranges horizontal attachment arm connecting wall on suspension bracket;
2) the suspension bracket top that several wirerope is connected to operator's compartment top is set respectively on crane arm and equilibrium arm, equilibrium arm arranges fixed weight and mobile counterweight, the forearm of crane arm arranges a carriage, carriage is by pulley horizontal slip on the guide rail of crane arm, carriage arranges a weight controller, weight controller bottom arranges cable wire and connecting shackle, and suspension hook is provided with safe tongue;
3) on suspension hook, arrange hawser, hawser connects concrete-agitating case, and the top of concrete-agitating case is provided with cover cap, concrete-agitating case inside is provided with mixing device, mixing device is connected with controller, arranges discharging opening bottom concrete-agitating case, and discharging opening connects passage;
4) water pipe of connection segment is vertically set in suspension bracket, horizontally set water pipe in crane arm, uniform multiple shower nozzle on water pipe horizontal in crane arm, in suspension bracket, the perpendicular water pipe put is connected by swivel joint in operator's compartment with water pipe horizontal in crane arm, in junction, pressure regulating valve is set, water pipe in suspension bracket bottom connects running water inlet, arranges shutoff valve and water pump between running water inlet and water pipe;
5) on crane arm end and suspension hook, arrange monitoring probe, the monitor screen in monitoring probe wireless connections operator's compartment, described mixing device is connected with controller;
The invention also discloses a kind of construction method of building operation Multifunctional tower crane, comprise following technology and step:
1) during this multifunctional crane tower crane fortune weight, weight controller carries out check weighing to hung article, sounds and flashing light warning when exceeding predetermined weight in operator's compartment;
2), in handling process, the mobile counterweight be located on equilibrium arm is done corresponding mobile, to balance the weight of crane arm according to the weight of the carriage on crane arm and position;
3) in construction, suspension hook is connected with concrete-agitating case by hawser, being suspended to high-altitude by suspension hook needs the position of building to build, the image that monitoring probe on suspension hook is sent on monitor screen accurately can learn concrete-agitating case position, concrete-agitating case with mixing device both can stir cement concrete, prevent from it from placing in atmosphere causing too for a long time hardening or solidifying, also concrete output is contributed to, situation below monitoring probe monitoring tower crane, and by video signal wireless transmission on the monitor screen in operator's compartment, operator clearly can understand the situation below tower crane, improve the safety of operation,
4) in construction, can sprinkler water smoke on water pipe horizontal in crane arm infiltrate to the cement concrete of building watering, cooling by being arranged on, also fast spray for dust suppression is carried out to camp site.
Utility model advantage
Compared with prior art, the beneficial effects of the utility model are: diverse in function, simple to operate; The suspension hook arranged is connected with concrete-agitating case by hawser, and being suspended to high-altitude by suspension hook needs the position of building to build; The image that monitoring probe on suspension hook is sent on monitor screen accurately can learn concrete-agitating case position, and structure is simple, cost is low, be convenient to tower crane control staff safe in operation; Safe dead bolt on suspension hook can prevent cable wire landing in lifting process, configure two counterweight disperse weight, the deadweight of forearm when fixed weight is for balancing tower crane no-load, the weight that mobile counterweight is formed after being used for balancing crane arm lifting, reduce the moment of flexure that tower crane produces pedestal, suitably can improve the lifting weight of tower crane; Concrete-agitating case with mixing device both can stir cement concrete, prevented from it from placing in atmosphere causing too for a long time solidifying, and also contribute to concrete output, simple to operate, efficiency is high; Situation below monitoring probe monitoring tower crane, and by video signal wireless transmission on the monitor screen in operator's compartment, operator clearly can understand the situation below tower crane, improves the safety of operation; Can infiltrate to the cement concrete of building watering, lower the temperature by spraying water smoke, or spray for dust suppression.
Accompanying drawing explanation
Fig. 1 is the structural representation of building operation Multifunctional tower crane.
Fig. 2 is the enlarged diagram at A place in building operation Multifunctional tower crane.
Fig. 3 is the enlarged diagram at B place in building operation Multifunctional tower crane.
Fig. 4 is the structural representation of suspension hook in building operation Multifunctional tower crane.
In figure: 1-pedestal, 2-suspension bracket, 3-water pipe, 4-fixed weight, 5-equilibrium arm, 6-mobile counterweight, 7-operator's compartment, 8-crane arm, 9-shower nozzle, 10-monitoring probe, 11-move device, 12-suspension hook, 13-hawser, 14-concrete-agitating case, 15-discharging opening, 16-cover cap, 17-mixing device, 18-passage, 19-running water inlet, 20-shutoff valve, 21-water pump, 22-pressure regulating valve, 23-controller, 24-monitor screen, the safe tongue of 25-.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Embodiment 1: refer to Fig. 1 ~ 4, a kind of building operation Multifunctional tower crane, comprise pedestal 1, suspension bracket 2, equilibrium arm 5, operator's compartment 7 and crane arm 8, described suspension bracket 2 is fixed on pedestal 1, described operator's compartment 7 is arranged on suspension bracket 2, the both sides being erected at suspension bracket 2 that described equilibrium arm 5 and crane arm 8 balance respectively, erect in described suspension bracket 2 and installed water pipe 3, horizontally in described crane arm 8 be provided with water pipe 3, uniform multiple shower nozzle 9 on water pipe 3 horizontal in described crane arm 8, in described tower crane 2, the perpendicular water pipe 3 put is connected by swivel joint in operator's compartment 7 with water pipe 3 horizontal in crane arm 8, and junction is provided with pressure regulating valve 22, one end of described water pipe 3 connects running water inlet 19, shutoff valve 20 and water pump 21 is provided with between described running water inlet 19 and water pipe 3, described equilibrium arm 5 is provided with fixed weight 4 and mobile counterweight 6, the forearm of described crane arm 8 is provided with a carriage 11, described carriage 11 is by pulley horizontal slip on the guide rail of crane arm 8, described carriage 11 is arranged with suspension hook 12, described suspension hook 12 is provided with safe tongue 27, described suspension hook 12 has hawser 13, described hawser 13 is connected with concrete-agitating case 14, the top of described concrete-agitating case 14 is provided with cover cap 16, described concrete-agitating case 14 inside is provided with mixing device 17, discharging opening 15 is provided with bottom described concrete-agitating case 14, described discharging opening 15 is connected with passage 18, described crane arm 8 end and suspension hook are provided with monitoring probe 10, controller 23 and monitor screen 24 is provided with in described operator's compartment 7, described monitoring probe 10 wireless connections monitor screen 24, described mixing device 17 is connected with controller 23.
The suspension hook 12 that the utility model is arranged is connected with concrete-agitating case 14 by hawser 13, cement concrete can be injected to concrete-agitating case 14, then being suspended to high-altitude by suspension hook 12 needs the position of building to build, the image that monitoring probe 10 on suspension hook 12 is sent on monitor screen 24 accurately can learn concrete-agitating case 14 position, safe dead bolt 27 on suspension hook 12 can prevent cable wire landing in lifting process, the weight that mobile counterweight 6 is formed after being used for balancing crane arm 8 lifting, thus when tower crane works, the moment of flexure that pedestal 1 produces is reduced, suitably can improve the lifting weight of tower crane, concrete-agitating case 14 with mixing device 17 both can stir cement concrete, prevent from it from placing in atmosphere causing too for a long time solidifying, also concrete output is contributed to, when needing to build, operator can open the switch of mixing device 17 by operation control 22, cement concrete is imported to casting position by passage 18, and simple to operate, efficiency is high, monitoring probe 10 monitors the situation below tower crane, and by video signal wireless transmission on the monitor screen 23 in operator's compartment 7, operator clearly can understand the situation below tower crane, improves the safety of operation, opening stop valve 20, water is extracted out pressurization and is entered water pipe 3 by water pump 21, sprays form water smoke from shower nozzle 9, and adjustment pressure regulating valve 22 can infiltrate to the cement concrete of building watering, cooling, or spray for dust suppression.
The present embodiment also discloses a kind of manufacture method of building operation Multifunctional tower crane, comprises following technology and step:
1) with steel-pipe welding unit suspension bracket 2, suspension bracket 2 is arranged on pedestal 1, lifting joint is set in the upper end of suspension bracket 2, lifting joint top arranges rotating mechanism, setting operation room 7 above rotating mechanism, and operator's compartment front portion arranges crane arm, operator's compartment rear portion arranges equilibrium arm 5, crane arm 8 and equilibrium arm 5 are erected at the both sides of suspension bracket 2 respectively, and as required, interval certain altitude arranges horizontal attachment arm connecting wall on suspension bracket 2;
2) the suspension bracket top that several wirerope is connected to operator's compartment top is set respectively on crane arm 8 and equilibrium arm 5, equilibrium arm 5 arranges fixed weight 4 and mobile counterweight 6, the forearm of crane arm 8 arranges a carriage 11, carriage 11 is by pulley horizontal slip on the guide rail of crane arm 8, carriage 11 arranges a weight controller, weight controller bottom arranges cable wire and connecting shackle 12, and suspension hook 12 is provided with safe tongue 27;
3) hawser 13 is set on suspension hook 12, hawser 13 connects concrete-agitating case 14, the top of concrete-agitating case 14 is provided with cover cap 16, concrete-agitating case 14 inside is provided with mixing device 17, mixing device 17 is connected with controller 23, arrange discharging opening 15 bottom concrete-agitating case 14, discharging opening 15 connects passage 18;
4) water pipe 3 of connection segment is vertically set in suspension bracket 2, horizontally set water pipe 3 in crane arm 8, uniform multiple shower nozzle 9 on water pipe 3 horizontal in crane arm 8, in suspension bracket 2, the perpendicular water pipe 3 put is connected by swivel joint in operator's compartment 7 with water pipe 3 horizontal in crane arm 8, pressure regulating valve 22 is set in junction, connect running water inlet 19 at the water pipe 3 of suspension bracket bottom, shutoff valve 20 and water pump 21 are set between running water inlet 19 and water pipe 3;
5) monitoring probe 10 is set on crane arm 8 end and suspension hook, controller 23 and monitor screen 24 are set in operator's compartment 7, monitoring probe 10 wireless connections monitor screen 24;
The present embodiment also discloses a kind of construction method of building operation Multifunctional tower crane, comprises following technology and step:
1) during this multifunctional crane tower crane fortune weight, weight controller carries out check weighing to hung article, sounds and flashing light warning when exceeding predetermined weight in operator's compartment 7;
2), in handling process, the mobile counterweight 6 be located on equilibrium arm 5 is done corresponding mobile, to balance the weight of crane arm according to the weight of the carriage 11 on crane arm 8 and position;
3) in construction, suspension hook 12 is connected with concrete-agitating case 14 by hawser, being suspended to high-altitude by suspension hook needs the position of building to build, the image that monitoring probe 10 on suspension hook 12 is sent on monitor screen 24 accurately can learn concrete-agitating case 14 position, concrete-agitating case 14 with mixing device 17 both can stir cement concrete, prevent from it from placing in atmosphere causing too for a long time hardening or solidifying, also concrete output is contributed to, monitoring probe 10 monitors the situation below tower crane, and by video signal wireless transmission on the monitor screen 24 in operator's compartment 7, operator clearly can understand the situation below tower crane, improve the safety of operation,
4) in construction, can be sprayed by the shower nozzle 9 be arranged on water pipe 3 horizontal in crane arm 8 that water smoke infiltrates to the cement concrete of building watering, cooling, also fast spray for dust suppression be carried out to camp site.
To those skilled in the art, obvious the utility model is not limited to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present utility model or essential characteristic, can realize the utility model in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present utility model is limited by claims instead of above-mentioned explanation, and all changes be therefore intended in the implication of the equivalency by dropping on claim and scope are included in the utility model.Any Reference numeral in claim should be considered as the claim involved by limiting.
In addition, be to be understood that, although this specification sheets is described according to embodiment, but not each embodiment only comprises an independently technical scheme, this narrating mode of specification sheets is only for clarity sake, those skilled in the art should by specification sheets integrally, and the technical scheme in each embodiment also through appropriately combined, can form other embodiments that it will be appreciated by those skilled in the art that.

Claims (3)

1. a building operation Multifunctional tower crane, comprise pedestal (1), suspension bracket (2), equilibrium arm (5), operator's compartment (7) and crane arm (8), it is characterized in that, described suspension bracket (2) is fixed on pedestal (1), described operator's compartment (7) is arranged on suspension bracket (2), the both sides being erected at suspension bracket (2) that described equilibrium arm (5) and crane arm (8) balance respectively, erect in described suspension bracket (2) and installed water pipe (3), horizontally in described crane arm (8) be provided with water pipe (3), the upper uniform multiple shower nozzle (9) of water pipe (3) horizontal in described crane arm (8), in described suspension bracket (2), the perpendicular water pipe (3) put is connected by swivel joint in operator's compartment (7) with horizontal water pipe (3) in crane arm (8), and junction is provided with pressure regulating valve (22), described equilibrium arm (5) is provided with fixed weight (4) and mobile counterweight (6), the forearm of described crane arm (8) is provided with a carriage (11), described carriage (11) is by pulley horizontal slip on the guide rail of crane arm (8), described carriage (11) is arranged with suspension hook (12), described suspension hook (12) has hawser (13), described hawser (13) is connected with concrete-agitating case (14), the top of described concrete-agitating case (14) is provided with cover cap (16), described concrete-agitating case (14) inside is provided with mixing device (17), described concrete-agitating case (14) bottom is provided with discharging opening (15), described discharging opening (15) is connected with passage (18), described crane arm (8) end and suspension hook (12) are provided with monitoring probe (10), controller (23) and monitor screen (24) is provided with in described operator's compartment (7), described monitoring probe (10) wireless connections monitor screen (24), described mixing device (17) is connected with controller (23).
2. building operation Multifunctional tower crane according to claim 1, it is characterized in that, in described suspension bracket (2), perpendicular water pipe (3) lower end of putting connects running water inlet (19), is provided with shutoff valve (20) and water pump (21) between described running water inlet (19) and this water pipe (3).
3. building operation Multifunctional tower crane according to claim 1, is characterized in that, described suspension hook (12) is provided with safe tongue (27).
CN201420760939.3U 2014-12-07 2014-12-07 A kind of building operation Multifunctional tower crane Expired - Fee Related CN204454337U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420760939.3U CN204454337U (en) 2014-12-07 2014-12-07 A kind of building operation Multifunctional tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420760939.3U CN204454337U (en) 2014-12-07 2014-12-07 A kind of building operation Multifunctional tower crane

Publications (1)

Publication Number Publication Date
CN204454337U true CN204454337U (en) 2015-07-08

Family

ID=53661252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420760939.3U Expired - Fee Related CN204454337U (en) 2014-12-07 2014-12-07 A kind of building operation Multifunctional tower crane

Country Status (1)

Country Link
CN (1) CN204454337U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104477789A (en) * 2014-12-07 2015-04-01 苏州汇诚智造工业设计有限公司 Multifunctional tower crane for building construction and manufacturing and construction methods thereof
CN105540455A (en) * 2016-02-22 2016-05-04 桐乡市搏腾贸易有限公司 Multifunctional monitoring hoisting tower with gravity testing
CN106006095A (en) * 2016-07-29 2016-10-12 南通润邦重机有限公司 Energy-saving environment-friendly mobile ship loader
CN106081938A (en) * 2016-08-18 2016-11-09 无锡石油化工起重机有限公司 Multi-functional shifting expects derrick crane
CN107215790A (en) * 2017-07-20 2017-09-29 无锡石油化工起重机有限公司 Derrick crane with cleaning function

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104477789A (en) * 2014-12-07 2015-04-01 苏州汇诚智造工业设计有限公司 Multifunctional tower crane for building construction and manufacturing and construction methods thereof
CN105540455A (en) * 2016-02-22 2016-05-04 桐乡市搏腾贸易有限公司 Multifunctional monitoring hoisting tower with gravity testing
CN106006095A (en) * 2016-07-29 2016-10-12 南通润邦重机有限公司 Energy-saving environment-friendly mobile ship loader
CN106006095B (en) * 2016-07-29 2019-02-19 南通润邦重机有限公司 A kind of energy conservation and environmental protection mobile ship loader
CN106081938A (en) * 2016-08-18 2016-11-09 无锡石油化工起重机有限公司 Multi-functional shifting expects derrick crane
CN107215790A (en) * 2017-07-20 2017-09-29 无锡石油化工起重机有限公司 Derrick crane with cleaning function

Similar Documents

Publication Publication Date Title
CN104477789A (en) Multifunctional tower crane for building construction and manufacturing and construction methods thereof
CN204454337U (en) A kind of building operation Multifunctional tower crane
CN105668425A (en) Construction method of multifunctional tower crane used for building construction
CN204625039U (en) A kind of safe tower crane
CN202370235U (en) Intelligent controlled lifting scaffold
CN102671333B (en) Wall-climbing fire-fighting robot for high-rise buildings
CN109184175A (en) A kind of construction suspension platform and suspention auxiliary device
CN204643647U (en) A kind of safe tower crane with sprinkler
CN204582340U (en) High-level crane fire-fighting system
CN205222531U (en) GIS dismouting intelligence auxiliary platform
CN204434119U (en) A kind of tower crane with sprinkle water function
CN102602834A (en) Platform-free lifting method and system of installing large rectangular devices to high-rise buildings
CN108100880B (en) A kind of automatic changing-breadth system of wheeled crane control cabinl pulpit and method
CN103708360A (en) Swing arm tower crane, standard knot introduction system thereof and standard knot introduction method
CN204802883U (en) Crane for construction
CN202441045U (en) Rail-type electric attached lifting scaffold
CN204980940U (en) Multifunctional tower crane
CN203874306U (en) Rescue vehicle for climbing building
CN207158651U (en) Modular assembly formula automatic lifting tower crane attached wall workbench
CN201507113U (en) Electric climbing-formwork device used for building and construction
CN206720614U (en) A kind of safe tower crane
CN103977512B (en) One is climbed building and is sued and laboured car
CN212689494U (en) Construction platform for building construction
CN204384772U (en) A kind of highly effective and safe tower crane
CN108035530A (en) A kind of inner wall of oil tank construction hanging basket

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708

Termination date: 20151207

EXPY Termination of patent right or utility model