CN204357088U - A kind of regularization pin hand structure - Google Patents

A kind of regularization pin hand structure Download PDF

Info

Publication number
CN204357088U
CN204357088U CN201420791609.0U CN201420791609U CN204357088U CN 204357088 U CN204357088 U CN 204357088U CN 201420791609 U CN201420791609 U CN 201420791609U CN 204357088 U CN204357088 U CN 204357088U
Authority
CN
China
Prior art keywords
platform
connecting rod
wall
regularization
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420791609.0U
Other languages
Chinese (zh)
Inventor
吴岳臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Civil Engineering and Architecture
Original Assignee
Beijing University of Civil Engineering and Architecture
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Civil Engineering and Architecture filed Critical Beijing University of Civil Engineering and Architecture
Priority to CN201420791609.0U priority Critical patent/CN204357088U/en
Application granted granted Critical
Publication of CN204357088U publication Critical patent/CN204357088U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

A kind of regularization pin hand structure, at least comprises platform beams, platform connecting rod, night bolt, seat in the plane hook, embedded nut, pre embedded bolt, load-bearing tripod and lower support bar; Described platform beams is arranged on platform small end; Described platform connecting rod left end is fixedly connected with body of wall; Described seat in the plane hook is arranged on platform beams and body of wall near side; Described pre embedded bolt is arranged in body of wall, and platform beams left end is fixedly connected with pre embedded bolt screw thread by embedded nut; Described heavy duty tripod bottom is connected with lower support bar, and its top is connected with the connecting rod of platform connecting rod bottom side; This modular regularization hanging feet hand, all adopts steel beam column preprocessing, and after installation on ground completes, be disposablely lifted into construction floor, in construction hoisting process, adopt tower crane whole to promote, centre need not be dismantled, and has saved the engineering time.

Description

A kind of regularization pin hand structure
Technical field
The utility model relates to hanging feet hand applied technical field, especially a kind of regularization pin hand structure.
Background technology
Traditional hand efficiency of carrying load or luggage is lower, cannot be through with hydraulic climbing formwork system, synchronously can not carry out, cannot meet this engineering construction requirement.Therefore, be necessary that between tower crane and metope, design a kind of simple and convenient construction support body solves the problem.
Prior art can not meet the needs of people, and for making up prior art deficiency, the utility model aims to provide a kind of regularization pin hand structure.
For achieving the above object, the utility model by the following technical solutions: a kind of regularization pin hand structure, at least comprises platform beams, platform connecting rod, night bolt, seat in the plane hook, embedded nut, pre embedded bolt, load-bearing tripod and lower support bar; Described platform beams is arranged on platform small end; Described platform connecting rod left end is fixedly connected with body of wall; Described seat in the plane hook is arranged on platform beams and body of wall near side; Described pre embedded bolt is arranged in body of wall, and platform beams left end is fixedly connected with pre embedded bolt screw thread by embedded nut; Described heavy duty tripod bottom is connected with lower support bar, and its top is connected with the connecting rod of platform connecting rod bottom side.
Further, described regularization scaffold is when arranging: hanging feet hand is divided into bottom tripod bearing system and steel superstructure operating platform frame, steel work operating platform totally 5 layers, 3 layers, bottom is template operation layer, 2 layers, top is reinforcing bar operation layer, its constructing operation layer is arranged consistent with hydraulic climbing formwork system height, thus it is through to realize operation layer, be convenient to trip's work carry out, operating platform frame load is delivered on 2 Pin tripods by bottom steel crossbeam, tripod carry, on wall pre-embedded bolt, forms firm system.
Compared with prior art, the beneficial effects of the utility model are: this modular regularization hanging feet hand, all adopt steel beam column preprocessing, after installation on ground completes, be disposablely lifted into construction floor, in construction hoisting process, employing tower crane whole promotes, and centre need not be dismantled, and has saved the engineering time.This modular regularization hanging feet hand has following features: hanging feet hand is modular, each unit independent stressed, and middle connected by turnover panel, be communicated with in construction, in process of climbing, turnover panel is opened; Overall structure is simple, practical, easily manufactured, is easy to promote the use of.
Utility model content
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present utility model;
Fig. 2 is finite element structure model of the present utility model;
Wherein: 1, platform beams, 2, platform connecting rod, 3, night bolt, 4, seat in the plane hook, 5, embedded nut, 6, pre embedded bolt, 7, load-bearing tripod, 8, lower support bar.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making other embodiments all obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Refer to Fig. 1, in the utility model embodiment, a kind of regularization pin hand structure, at least comprises platform beams 1, platform connecting rod 2, night bolt 3, seat in the plane hook 4, embedded nut 5, pre embedded bolt 6, load-bearing tripod 7 and lower support bar 8; Described platform beams 1 is arranged on platform connecting rod 2 upper end; Described platform connecting rod 2 left end is fixedly connected with body of wall; Described seat in the plane hook 4 is arranged on platform beams 1 with body of wall near side; Described pre embedded bolt 6 is arranged in body of wall, and platform beams 1 left end is fixedly connected with pre embedded bolt 6 screw thread by embedded nut 5; Described heavy duty tripod 7 bottom is connected with lower support bar 8, and its top is connected with the connecting rod of platform connecting rod 2 bottom side.
Further, described regularization scaffold is when arranging: hanging feet hand is divided into bottom tripod bearing system and steel superstructure operating platform frame, steel work operating platform totally 5 layers, 3 layers, bottom is template operation layer, 2 layers, top is reinforcing bar operation layer, its constructing operation layer is arranged consistent with hydraulic climbing formwork system height, thus it is through to realize operation layer, constructability is carried out, operating platform frame load is delivered on 2 Pin tripods by bottom steel crossbeam, tripod carry, on wall pre-embedded bolt, forms firm system.
Further technical scheme of the present utility model: this regularization hanging feet hand is modular setting, T1 has 5 hanging feet hand unit, after one deck of having constructed, it is risen to lower one deck respectively with tower crane, and fixing after being connected with pre-embedded bolt, standardized construction flow process is as follows:
Flow process one, builds n-th layer concrete, and now hanger is mounted on N-1 layer pre-embedded bolt;
Flow process two, between the ~ layer concrete curing time, colligation N+1 layer concrete reinforcing bar;
After the colligation of flow process three, N+1 layer concrete completes, now ~ layer concrete reaches predetermined strength, removes this layer of body of wall side form, adopts tower crane to promote each unit regularization hanging feet hand respectively, is buried on bolt by hanger carry after lifting in the ~ layer concrete.
Flow process four, the laminated mould of N+1, and build this layer concrete, so circulation enters next construction process.
To those skilled in the art, obvious the utility model is not limited to the details of above-mentioned one exemplary embodiment, and when not deviating from spirit of the present utility model or essential characteristic, can realize the utility model in other specific forms.Therefore, no matter from which point, all should embodiment be regarded as exemplary, and be nonrestrictive, scope of the present utility model is limited by claims instead of above-mentioned explanation, and all changes be therefore intended in the implication of the equivalency by dropping on claim and scope are included in the utility model.Any Reference numeral in claim should be considered as the claim involved by limiting.
The above; be only preferred embodiment of the present utility model; not in order to limit the utility model, every above embodiment is done according to technical spirit of the present utility model any trickle amendment, equivalently replace and improve, within the protection domain that all should be included in technical solutions of the utility model.

Claims (2)

1. a regularization pin hand structure, at least comprises platform beams (1), platform connecting rod (2), night bolt (3), seat in the plane hook (4), embedded nut (5), pre embedded bolt (6), load-bearing tripod (7) and lower support bar (8); It is characterized in that: described platform beams (1) is arranged on platform connecting rod (2) upper end; Described platform connecting rod (2) left end is fixedly connected with body of wall; Described seat in the plane hook (4) is arranged on platform beams (1) with body of wall near side; Described pre embedded bolt (6) is arranged in body of wall, and platform beams (1) left end is fixedly connected with pre embedded bolt (6) screw thread by embedded nut (5); Described heavy duty tripod (7) bottom is connected with lower support bar (8), and its top is connected with the connecting rod of platform connecting rod (2) bottom side.
2. a kind of regularization pin hand structure according to claim 1, it is characterized in that: hanging feet hand is divided into bottom tripod bearing system and steel superstructure operating platform frame, steel work operating platform totally 5 layers, 3 layers, bottom is template operation layer, 2 layers, top is reinforcing bar operation layer, its constructing operation layer is arranged consistent with hydraulic climbing formwork system height, thus it is through to realize operation layer, constructability is carried out, operating platform frame load is delivered on 2 Pin tripods by bottom steel crossbeam, tripod carry, on wall pre-embedded bolt, forms firm system.
CN201420791609.0U 2014-12-16 2014-12-16 A kind of regularization pin hand structure Expired - Fee Related CN204357088U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420791609.0U CN204357088U (en) 2014-12-16 2014-12-16 A kind of regularization pin hand structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420791609.0U CN204357088U (en) 2014-12-16 2014-12-16 A kind of regularization pin hand structure

Publications (1)

Publication Number Publication Date
CN204357088U true CN204357088U (en) 2015-05-27

Family

ID=53258566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420791609.0U Expired - Fee Related CN204357088U (en) 2014-12-16 2014-12-16 A kind of regularization pin hand structure

Country Status (1)

Country Link
CN (1) CN204357088U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984553A (en) * 2019-12-20 2020-04-10 浙江宝业建设集团有限公司 Detachable turnover high-altitude large-cantilever formwork and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984553A (en) * 2019-12-20 2020-04-10 浙江宝业建设集团有限公司 Detachable turnover high-altitude large-cantilever formwork and construction method

Similar Documents

Publication Publication Date Title
CN201850498U (en) Steel trestle in water
CN203451114U (en) Tower crane attaching device for bridge tower construction
CN103469735B (en) The mounting method of curve ultrahigh hollow column plate type pier top solid section template
CN104372961A (en) Anti-seismic integrated lightweight steel construction house
CN103410101A (en) Tower crane conversion method for construction of parabola-shaped ultrahigh pier
CN205604080U (en) Building construction platform
CN202483154U (en) High bearing capacity suspending scaffold
CN204001416U (en) For the assemble type truss of the factory building of constructing
CN204357088U (en) A kind of regularization pin hand structure
CN204225464U (en) A kind of regularization hanging feet hand structure
CN204311776U (en) A kind of integrated lightweight steel construction room of antidetonation
CN102995560A (en) Thin-wall hollow pier lifting frame and use method thereof
CN206467792U (en) A kind of modular architectural embeds floor and beam attachment structure
CN202577926U (en) Fixed operating platform for elevator shaft
CN203666706U (en) Simple two-wheel lever transportation tool
CN204038986U (en) For removing the fork truck of inner support steel pipe
CN203392111U (en) Prefabricated concrete wall plate transporting device
CN206385750U (en) A kind of mixed structure precast stair
CN202850471U (en) Lifting type operation platform for elevator well
CN206815861U (en) Assembled outfeed platforms
CN201843089U (en) Vertical lifting bin for overhauling overpass ramp bridge
CN207142643U (en) Skyscraper indoor equipment hoisting platform
CN203903792U (en) Gantry frame for placing equipment
CN203903793U (en) Gantry hoisting frame applied to heavy equipment
CN204212069U (en) Hanging basket for building construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150527

Termination date: 20161216