CN204266133U - A kind of pier stud reinforcing cage whole lifting structure - Google Patents

A kind of pier stud reinforcing cage whole lifting structure Download PDF

Info

Publication number
CN204266133U
CN204266133U CN201420752918.7U CN201420752918U CN204266133U CN 204266133 U CN204266133 U CN 204266133U CN 201420752918 U CN201420752918 U CN 201420752918U CN 204266133 U CN204266133 U CN 204266133U
Authority
CN
China
Prior art keywords
reinforcing cage
pier stud
frame
stud reinforcing
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420752918.7U
Other languages
Chinese (zh)
Inventor
叶成诚
江辉
李一帆
郭乐
张新水
朱德军
刘琳
周向国
陆海锋
滕传杰
鲁文元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
First Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
First Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, First Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201420752918.7U priority Critical patent/CN204266133U/en
Application granted granted Critical
Publication of CN204266133U publication Critical patent/CN204266133U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of pier stud reinforcing cage whole lifting structure, it is characterized in that: be bolted formation one with Two bors d's oeuveres channel-section steel and close and enclose frame, the neck that frame is fixed on pier stud reinforcing cage vase pier is enclosed to close, and to form the Two bors d's oeuveres channel-section steel closing and enclose frame as vase pier stirrup cross-arm; Arrange each hanger closed enclosing on frame, hoisting wirerope is located in each hanger, and lifting appliance utilizes hoisting wirerope to lift by crane and closes and encloses frame and make pier stud reinforcing cage be vertical handling, closes the shape of enclosing frame and pier stud reinforcing cage vase pier and matches; Cable wind rope for drawing pier stud reinforcing cage is fixedly connected on and is positioned over ground concrete precast block.The utility model makes pier stud reinforcing cage handling put in place fast, and guarantees that the integral hoisting of pier stud reinforcing cage is indeformable, thus ensures programming, improves workmanship.

Description

A kind of pier stud reinforcing cage whole lifting structure
Technical field
The hoisting structure of a kind of pier stud reinforcing cage of the utility model, be more particularly a kind of when being applied in cushion cap pier stud integrated construction in pier stud reinforcing cage whole lifting structure.
Background technology
Cushion cap pier stud integrated construction is that one can greatly reduce construction operation amount on construction supplementary structure and bridge, thus the technique significantly improving working conditions, speed up the work, save the operation of manually taking and tearing pier shaft scaffold open, reduce high-rise working risk; Reduce the duration, simple to operate, save labour, save consumptive material and drop into.
Pier stud reinforcing cage has top vase pier usually and the external diameter that connects with vase pier is less than the neck of vase pier, cushion cap pier stud integrated construction is in construction bearing platform process, will by the integral hoisting of pier stud reinforcing cage in cushion cap reinforcing bar, and can guarantee that pier stud reinforcing cage is indeformable in handling, but, the open report of not relevant integral hoisting method so far, because pier stud reinforcing cage overall weight and volume are all very large, suspension centre is directly set on pier stud reinforcing cage and is difficult to ensure that pier stud steel bar overall is indeformable.
Such as, in the elevated project in line interval, Beijing Metro swallow room, this project interval is all ground elevated project, and substructure is pile foundation, cushion cap and pier stud, without bent cap.In cushion cap reinforcement construction, show in conjunction with Beijing meteorological data, local wind-force rank reaches 3 ~ 4 grades, each pier stud reinforcing cage weight is between 7.546t ~ 24.567t, if conveniently the direct mode lifted pier stud reinforcing cage will cause pier stud reinforcing bar hoisting process to produce distortion, meanwhile, cannot lift in enormous quantities, therefore programming is affected.
Utility model content
The utility model is the weak point for avoiding existing for above-mentioned prior art, provides a kind of pier stud reinforcing cage whole lifting structure, pier stud reinforcing cage can be put in place fast in handling, and guarantee that pier stud reinforcing bar is indeformable, thus ensure programming, improve workmanship.
The utility model is that technical solution problem adopts following technical scheme:
The feature of the utility model pier stud reinforcing cage whole lifting structure is: be bolted formation one with Two bors d's oeuveres channel-section steel and close and enclose frame (4), the neck that frame (4) is fixed on pier stud reinforcing cage vase pier (1) is enclosed with described closing, and to form the closed stirrup cross-arm of Two bors d's oeuveres channel-section steel as vase pier (1) enclosing frame (4); Described closed enclosing on frame (4), each hanger is set, hoisting wirerope (2) is located in described each hanger, lifting appliance utilizes described hoisting wirerope (2) to lift by crane and closes and encloses frame (4) and make pier stud reinforcing cage (6) in vertical handling, and the described shape of enclosing frame (4) and described pier stud reinforcing cage vase pier (1) of closing matches; Cable wind rope (5) for drawing pier stud reinforcing cage (6) is fixedly connected on and is positioned over ground concrete precast block (10).
The feature of the utility model pier stud reinforcing cage whole lifting structure is also:
The square that described concrete precast block (10) is the length of side is 1.5m, weight is 8.5 tons, arrange suspension ring in the surrounding of described concrete precast block (10), cable wind rope (5) is fixedly connected on described suspension ring.
Described closed enclosing in frame (4), " ten " word is provided with dowel (7), keep closing that to enclose frame (4) indeformable with the booster action of described dowel (7), described dowel (7) adopts fining twisted steel.
For pier stud reinforcing cage vase pier (1) that end face is rectangular, described closing encloses frame (4) rectangle frame also for matching.
Compared with the prior art, the utility model beneficial effect is embodied in:
1, the utility model is hung by pier stud reinforcing cage with channel-section steel cross-arm, lifting transhipment is carried out with hanger, the frame that encloses that its shaped steel is formed ensure that pier stud reinforcing cage is firmly integrally-built, enclose between frame and pier stud reinforcing cage and form multiple origin of force, effectively ensure that in pier stud reinforcing cage handling process indeformable; Concrete precast block is adopted to fix cable wind rope, safe and reliable, can be used for the more location of underground utilities, need not earth anchor be set up.
2, the utility model can be reused, and substantially increases operating efficiency, provides sound assurance for coordinating programming;
3, the pier stud reinforcing cage vase pier in handling is enclosed in and encloses on cross-arm that frame formed by closing by the utility model, and handling process safety is reliable; Its structure is simple, easy to implement.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of the utility model;
Fig. 2 closes in the utility model to enclose frame floor map;
Fig. 3 closes in the utility model to enclose frame and coordinate schematic front view with hoisting wirerope;
Fig. 4 is that the utility model utilizes shoulder pole to carry out the lifting structural representation of transition;
Number in the figure: 1 vase pier, 2 hoisting wireropes, 3 shoulder poles, 4 close enclose frame, 4A crossbeam, 4B end carriage, 5 cable wind ropes, 6 pier stud reinforcing cages, 7 dowels, 8 lifting wire rope, 9 cushion caps, 10 concrete precast blocks.
Detailed description of the invention
See Fig. 1, Fig. 2 and Fig. 3, the present embodiment pier stud reinforcing cage whole lifting structure is bolted formation one with Two bors d's oeuveres channel-section steel to close and enclose frame 4, the neck that frame 4 is fixed on the vase pier 1 of pier stud reinforcing cage 6 is enclosed to close, and to form the closed stirrup cross-arm of Two bors d's oeuveres channel-section steel as vase pier 1 enclosing frame; Closed enclosing on frame 4, each hanger is set, hoisting wirerope 2 is located in each hanger, lifting appliance utilizes hoisting wirerope 2 to lift by crane and closes and encloses frame 4 and make pier stud reinforcing cage 6 in vertical handling above cushion cap 9, and the closed frame 4 that encloses matches with the shape of pier stud reinforcing cage vase pier 1.
In concrete enforcement, " ten " word is provided with dowel 7 closing to enclose in frame 1, keeps closing that to enclose frame 4 indeformable with the booster action of dowel 7, dowel 7 adopts fining twisted steel.
As shown in Figure 2, for the pier stud reinforcing cage vase pier 1 that end face is rectangular in the present embodiment, it closes the rectangle frame enclosing frame 4 and be set to match, and is specifically bolted by the pair of beams 4A be arranged in parallel and a pair end carriage 4B and makes; In order to guaranteed strength, the dowel 7 in rectangle frame is twice " ten " word muscle, and two fining twisted steels intersected in " ten " misplace in different elevation, to ensure that fining twisted steel is straight muscle.
In order to ensure that lifting steadily, for the rectangle frame shown in Fig. 2, both sides hoisting wirerope 2 can be independently set for both sides crossbeam 4A, both sides lifting rope 2 shares the two ends at the shoulder pole 3 in level, and lifting appliance carries out lifting by the lifting wire rope 8 being arranged on the two ends of shoulder pole 3 at the two ends of shoulder pole 3.
Cable wind rope 5 for drawing pier stud reinforcing cage in the present embodiment is fixedly connected on and is positioned over ground concrete precast block 10, the square that concrete precast block 10 is length of sides is 1.5m, weight is 8.5 tons, the steel mesh reinforcement of two-layer Φ 14 is set in concrete precast block 10, suspension ring being set in the surrounding of concrete precast block 10, establishing cable wind rope 5 for drawing.Draw and set cable wind rope 5 to be impacts as ensureing pier stud reinforcing cage not by wind, earth anchor can be set up when usual cable wind rope is fixed on ground, but in the location that underground utilities are more, arrange earth anchor and probably damage underground utilities, the utility model adopts concrete precast block to address this problem.
Assembling and handling process: be transported to pier stud construction location after the colligation of pier stud reinforcing cage completes, fix by loop wheel machine supporting leg, hoisting structure installation, lifting, joint bar, cable wind rope.

Claims (4)

1. a pier stud reinforcing cage whole lifting structure, it is characterized in that: be bolted formation one with Two bors d's oeuveres channel-section steel and close and enclose frame (4), the neck that frame (4) is fixed on pier stud reinforcing cage vase pier (1) is enclosed with described closing, and to form the closed stirrup cross-arm of Two bors d's oeuveres channel-section steel as vase pier (1) enclosing frame (4); Described closed enclosing on frame (4), each hanger is set, hoisting wirerope (2) is located in described each hanger, lifting appliance utilizes described hoisting wirerope (2) to lift by crane and closes and encloses frame (4) and make pier stud reinforcing cage (6) in vertical handling, and the described shape of enclosing frame (4) and described pier stud reinforcing cage vase pier (1) of closing matches; Cable wind rope (5) for drawing pier stud reinforcing cage (6) is fixedly connected on and is positioned over ground concrete precast block (10).
2. pier stud reinforcing cage whole lifting structure according to claim 1, it is characterized in that: the square that described concrete precast block (10) is the length of side is 1.5m, weight is 8.5 tons, arrange suspension ring in the surrounding of described concrete precast block (10), cable wind rope (5) is fixedly connected on described suspension ring.
3. pier stud reinforcing cage whole lifting structure according to claim 1, it is characterized in that: described closed enclosing in frame (4), " ten " word is provided with dowel (7), keep closing that to enclose frame (4) indeformable with the booster action of described dowel (7), described dowel (7) adopts fining twisted steel.
4. pier stud reinforcing cage whole lifting structure according to claim 1, is characterized in that: for pier stud reinforcing cage vase pier (1) that end face is rectangular, and described closing encloses frame (4) rectangle frame also for matching.
CN201420752918.7U 2014-12-03 2014-12-03 A kind of pier stud reinforcing cage whole lifting structure Expired - Fee Related CN204266133U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420752918.7U CN204266133U (en) 2014-12-03 2014-12-03 A kind of pier stud reinforcing cage whole lifting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420752918.7U CN204266133U (en) 2014-12-03 2014-12-03 A kind of pier stud reinforcing cage whole lifting structure

Publications (1)

Publication Number Publication Date
CN204266133U true CN204266133U (en) 2015-04-15

Family

ID=52801005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420752918.7U Expired - Fee Related CN204266133U (en) 2014-12-03 2014-12-03 A kind of pier stud reinforcing cage whole lifting structure

Country Status (1)

Country Link
CN (1) CN204266133U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842602A (en) * 2018-07-16 2018-11-20 浙江交工集团股份有限公司 A kind of hyperboloid vase pier framework of steel reinforcement
CN109667226A (en) * 2018-12-14 2019-04-23 中建八局第四建设有限公司 A kind of cable wind rope construction method
CN111676817A (en) * 2020-06-01 2020-09-18 中铁八局集团第二工程有限公司 Construction method of pier column type bridge upright column movable cable rope device
CN113944099A (en) * 2021-10-29 2022-01-18 中交路桥建设有限公司 Gate-type pier capping beam built-in anti-seismic reinforcing steel bar structure and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842602A (en) * 2018-07-16 2018-11-20 浙江交工集团股份有限公司 A kind of hyperboloid vase pier framework of steel reinforcement
CN109667226A (en) * 2018-12-14 2019-04-23 中建八局第四建设有限公司 A kind of cable wind rope construction method
CN111676817A (en) * 2020-06-01 2020-09-18 中铁八局集团第二工程有限公司 Construction method of pier column type bridge upright column movable cable rope device
CN113944099A (en) * 2021-10-29 2022-01-18 中交路桥建设有限公司 Gate-type pier capping beam built-in anti-seismic reinforcing steel bar structure and construction method thereof
CN113944099B (en) * 2021-10-29 2023-09-26 中交路桥建设有限公司 Built-in anti-seismic steel bar structure of door pier capping beam and construction method thereof

Similar Documents

Publication Publication Date Title
CN204266133U (en) A kind of pier stud reinforcing cage whole lifting structure
CN204185120U (en) Mobile unit dolly in place
CN203451050U (en) Pile foundation reinforcing cage lifting rib
CN204080650U (en) A kind of end bay for road and bridge construction closes up suspension bracket
CN205114843U (en) Prefabricated post hoist device with unhook function
CN203593556U (en) High safety tower crane
CN104060836B (en) The lifting installation method of high curved surface rack
CN203200665U (en) Prestressing steel strand threading device for bridge construction
CN203474231U (en) Steel bar tower safety hoisting device
CN206298286U (en) A kind of wet electrical dust precipitator body equipment integral hoisting aids in hanging beam
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN203569872U (en) Same layer lifting type cantilever frame device
CN202988556U (en) Special lifting appliance for angle-steel type frame body
CN203716062U (en) Integral type pier body decorating hanging basket
CN206625585U (en) A kind of carrying pole device of purlin installation
CN205575534U (en) Lattice formula groined type support body lifting means
CN211473342U (en) Overhanging scaffold upright rod with anti-skid device
CN208965547U (en) A kind of hangs muscle device that novel simplicity can be recycled
CN202658874U (en) Flexible wall connecting piece device
CN206529934U (en) A kind of fabricated shear wall edge member
CN206395707U (en) A kind of boom hoisting bolt type connector
CN204080639U (en) A kind of device for installing the main muscle of pier stud
CN206309111U (en) A kind of line bar location and installation component
CN204825670U (en) Inclined to one side hanging beam frame device is prevented turning round by eccentric case roof beam
CN204960280U (en) Scaffold capable of being integrally hoisted and repeatedly used

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150415

CF01 Termination of patent right due to non-payment of annual fee