CN204252160U - Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore - Google Patents

Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore Download PDF

Info

Publication number
CN204252160U
CN204252160U CN201420716989.1U CN201420716989U CN204252160U CN 204252160 U CN204252160 U CN 204252160U CN 201420716989 U CN201420716989 U CN 201420716989U CN 204252160 U CN204252160 U CN 204252160U
Authority
CN
China
Prior art keywords
bucket
plank road
button
button bucket
cofferdam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420716989.1U
Other languages
Chinese (zh)
Inventor
闫传桂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420716989.1U priority Critical patent/CN204252160U/en
Application granted granted Critical
Publication of CN204252160U publication Critical patent/CN204252160U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cultivation Of Seaweed (AREA)

Abstract

The utility model discloses a kind of seashore to rise the ebb subsea construction plank road in area and cofferdam, it is made up of button bucket and guardrail, at the bottom of the upper end of button bucket is provided with barrel, lower end is provided with bung, the middle part at the bucket end is provided with discharge opening, the front end of button bucket is provided with connected positioning plate, the rear end of button bucket is provided with connection locating slot, the left side of button bucket is provided with left connected positioning plate, the right side of button bucket is provided with right connection locating slot, two herringbone stiffeners are provided with in button bucket, the left upper end of button bucket is provided with left junction plate, the upper right side of button bucket is provided with right junction plate, right junction plate is provided with connecting hole, the upper end of discharge opening is provided with discharging lid, the middle part of discharging lid is provided with setting-out hole, during use, plank road is arranged on button bucket, the junction plate bolt of plank road junction plate with button bucket upper end is assembled into one, build up by plank road.

Description

Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore
Technical field
The utility model relates to a kind of construction equipment of water-bed operation, is specifically rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore.
Background technology
China has and has wide coastline, builds power station by the sea, and utilizing natural resource to generate electricity is develop energy, the major action benefiting the people, but due to the mud in the seashore bottom and the indefinite tidewater of fluctuation, brings great difficulty to construction.
Summary of the invention
Therefore, there is great demand to the construction installation building power station by the sea in people, so far, also do not find about relevant report of the present invention, the present inventor, through research repeatedly, test, finally successfully works out plank road and the cofferdam of subsea construction, thus completes the present invention.
The purpose of this utility model is just to provide a kind of plank road and cofferdam of subsea construction, to develop natural resource, benefits the people.
Scheme of the present utility model is made up of button bucket and guardrail, button bucket makes cuboid by Plate Welding, at the bottom of the upper end of button bucket is provided with barrel, lower end is provided with bung, the middle part at the bucket end is provided with 3 discharge openings, discharge opening be circumferentially provided with inner bolt hole, the front end of button bucket is provided with two connected positioning plates in left and right, the lower end of connected positioning plate is provided with buckle pin slot, the rear end of button bucket is provided with two connection locating slots corresponding thereto, the lower end connecting locating slot is provided with pin buckle, the left side of button bucket is provided with left connected positioning plate, the right side of button bucket is provided with right connection locating slot, the lower end of left connected positioning plate is provided with buckle pin slot, the lower end of right connection locating slot is provided with pin buckle, two herringbone stiffeners are provided with in button bucket, herringbone stiffener is weldingly fixed on to be buckled in bucket, the left upper end of button bucket is provided with left junction plate, left junction plate is provided with left plate connecting hole, the upper right side of button bucket is provided with right junction plate, right junction plate is provided with right panel connecting hole, the upper end of discharge opening is provided with discharging lid, circumferentially being provided with of discharging lid is fixedly connected with hole, the middle part of discharging lid is provided with setting-out hole, the upper end of button bucket is provided with plank road support, the height of plank road support is according to the sea level height design after flood tide, should higher than the water surface 1.5-1.8 rice after flood tide, the lower end of plank road support is provided with bottom girder, the lower end of bottom girder is provided with plank road junction plate, plank road junction plate is provided with screw, the upper end of plank road support is provided with plank road, the both sides of plank road are provided with guardrail.During use, plank road is arranged on button bucket, the junction plate bolt of plank road junction plate with button bucket upper end is assembled into one, builds up by plank road.The front end of plank road is provided with cofferdam bucket, cofferdam bucket is set to arc bucket, at the bottom of the upper end of arc bucket is provided with barrel, lower end is provided with bung, the front end of staving is provided with fixed connecting plate, the lower end of fixed connecting plate is provided with fixing catching groove, the rear end of staving is provided with and is fixedly connected with groove, the bottom being fixedly connected with groove is provided with fixing pin buckle, be fixedly connected with in groove and be provided with sealing mat, rinforcement bar is provided with in staving, the upper end of staving is provided with guardrail rack, the upper end of guardrail rack is provided with guardrail, cofferdam road slab is provided with in guardrail rack, the bottom of cofferdam bucket is provided with setting-out hole, the upper end of ballast bucket is provided with hanger, the bottom of ballast bucket is provided with junction plate, junction plate is provided with screw, the lower right side of ballast bucket is provided with draining valve.
During construction, first the discharging lid of button bottom of the barrel is pulled down, the bung of button bucket is pressed in underwater sediment downward vertically, due to the change of the water-bed degree of depth, the water content of silt layer is fewer and feweri, hardness also strengthens thereupon, the speed that button bucket sinks is obstructed, when detaining bucket and stopping, crane can be opened, being lifted on by ballast bucket buckles on bucket, and to water filling in ballast bucket, with a button bucket of gaining in weight to pressing down, when detaining bucket and again stopping, the moisture silt in bucket is removed from discharging opening, recharging dry sandy soil continues toward pressing down, button bucket is again slack, now eliminate the sandy soil overflowed in discharging opening, by discharging cover plate shutoff discharging opening bolton, and close setting-out hole, the 2nd button bucket is press-fited again according to above-mentioned steps, and the connected positioning plate of button bucket front and back end is inserted connection locating slot fastening pin buckle, install successively, and the junction plate of button bucket upper end and plank road bolton are integrated, make it to be connected with cofferdam.Button bucket also can all around mutual abutting joint, and connect into large-scale platform, for pump truck and crane etc., mechanical personnel are stationed.
Dismounting after generating set installs: during dismounting cofferdam, first the setting-out hole disassembling bolts of bucket bottom, cofferdam, can load onto water inlet pipe, starts water pump and to draw water pressurization in button bucket, make button bucket increase and be convenient to lift by crane, the geology original appearance at the bottom of can also keeping barrel.
The utility model structure is simple, and reasonable in design, processing cost is low, easy to use, easy to operate, effective, promoting the use of of this product, will fill up blank of the same trade both at home and abroad.
Be described in further detail below in conjunction with accompanying drawing.
Accompanying drawing explanation
Fig. 1 is button barrel structure schematic diagram;
Fig. 2 is button bucket plan structure schematic diagram;
Fig. 3 is herringbone gusset plate structural representation;
Fig. 4 is discharging lid structural representation;
Fig. 5 is the left TV structure schematic diagram of button bucket;
Fig. 6 is plank road structural representation;
Fig. 7 is cofferdam barrel structure schematic diagram;
Fig. 8 is cofferdam plan structure schematic diagram;
Fig. 9 is ballast bucket schematic diagram.
Detailed description of the invention
Button bucket 3 shown in Fig. 1-5 makes cuboid by steel plate, at the bottom of the upper end of button bucket is provided with barrel, lower end is provided with bung, the middle part at the bucket end is provided with 3 discharge openings 11, discharge opening be circumferentially provided with inner bolt hole, the front end of button bucket is provided with two connected positioning plates 13 in left and right, the lower end of connected positioning plate is provided with buckle pin slot 17, the rear end of button bucket is provided with two connection locating slots 4 corresponding thereto, the lower end connecting locating slot is provided with pin buckle 10, the left side of button bucket is provided with left connected positioning plate 2, the right side of button bucket is provided with right connection locating slot 8, the lower end of left connected positioning plate is provided with buckle pin slot 1, the lower end of right connection locating slot is provided with pin buckle 9, two herringbone stiffeners 6 are provided with in button bucket, the left upper end of button bucket is provided with left junction plate 5, left junction plate is provided with left connecting hole 12, the upper right side of button bucket is provided with right junction plate 7, right junction plate is provided with right connecting hole 14, the upper end of discharge opening is provided with discharging lid 15, circumferentially being provided with of discharging lid is fixedly connected with hole, the middle part of discharging lid is provided with setting-out hole 16, the upper end of button bucket is provided with plank road support.
The lower end of the plank road support 19 shown in Fig. 6 is provided with bottom girder 18, and the lower end of bottom girder is provided with plank road junction plate 22, and plank road junction plate is provided with screw 23, and the upper end of plank road support is provided with plank road 21, and the both sides of plank road are provided with guardrail 20.During use, be arranged on by plank road on button bucket, the junction plate bolt of plank road junction plate with button bucket upper end is assembled into one, and build up by plank road, the front end of plank road is provided with cofferdam bucket.
Cofferdam bucket 26 shown in Fig. 7-8 is set to arc bucket, at the bottom of the upper end of arc bucket is provided with barrel, lower end is provided with bung, the front end of staving is provided with fixed connecting plate 25, the lower end of fixed connecting plate is provided with fixing catching groove 24, the rear end of staving is provided with and is fixedly connected with groove 31, the bottom being fixedly connected with groove is provided with fixing pin buckle 32, be fixedly connected with in groove and be provided with sealing mat, rinforcement bar 30 is provided with in staving, the upper end of staving is provided with guardrail rack 27, the upper end of guardrail rack is provided with guardrail 28, cofferdam road slab 29 is provided with in guardrail rack, the bottom of cofferdam bucket is provided with setting-out hole 33, fixed connecting plate is provided with the upper end being fixedly connected with groove and fixedly mounts hole 39, cofferdam bucket is installed successively and is combined into circular dam, seawater is isolated in outside dam, so that in dam safe construction.
The upper end of the bucket of ballast shown in Fig. 9 35 is provided with hanger 36, and the bottom of ballast bucket is provided with junction plate 38, and junction plate is provided with screw 34, and the lower right side of ballast bucket is provided with draining valve 37.

Claims (3)

1. rise the subsea construction plank road in ebb area and cofferdam in a seashore, be made up of button bucket and guardrail, it is characterized in that: described button bucket (3) makes cuboid by steel plate, at the bottom of the upper end of button bucket is provided with barrel, lower end is provided with bung, the middle part at the bucket end is provided with 3 discharge openings (11), discharge opening be circumferentially provided with inner bolt hole, the front end of button bucket is provided with two connected positioning plates (13) in left and right, the lower end of connected positioning plate is provided with buckle pin slot (17), the rear end of button bucket is provided with two connection locating slots (4) corresponding thereto, the lower end connecting locating slot is provided with pin buckle (10), the left side of button bucket is provided with left connected positioning plate (2), the right side of button bucket is provided with right connection locating slot (8), the lower end of left connected positioning plate is provided with buckle pin slot (1), the lower end of right connection locating slot is provided with pin buckle (9), two herringbone stiffeners (6) are provided with in button bucket, the left upper end of button bucket is provided with left junction plate (5), left junction plate is provided with left connecting hole (12), the upper right side of button bucket is provided with right junction plate (7), right junction plate is provided with right connecting hole (14), the upper end of discharge opening is provided with discharging lid (15), circumferentially being provided with of discharging lid is fixedly connected with hole, the middle part of discharging lid is provided with setting-out hole (16), the upper end of button bucket is provided with plank road support.
2. rise the ebb subsea construction plank road in area and cofferdam in seashore according to claim 1, it is characterized in that: the lower end of described plank road support (19) is provided with bottom girder (18), the lower end of bottom girder is provided with plank road junction plate (22), plank road junction plate is provided with screw (23), the upper end of plank road support is provided with plank road (21), the both sides of plank road are provided with guardrail (20), plank road is arranged on button bucket, plank road junction plate is assembled into one with the junction plate bolt of button bucket upper end, and the front end of plank road is provided with cofferdam bucket.
3. rise the ebb subsea construction plank road in area and cofferdam in seashore according to claim 2, it is characterized in that: described cofferdam bucket (26) is set to arc bucket, at the bottom of the upper end of arc bucket is provided with barrel, lower end is provided with bung, the front end of staving is provided with fixed connecting plate (25), the lower end of fixed connecting plate is provided with fixing catching groove (24), the rear end of staving is provided with and is fixedly connected with groove (31), the bottom being fixedly connected with groove is provided with fixing pin buckle (32), be fixedly connected with in groove and be provided with sealing mat, rinforcement bar (30) is provided with in staving, the upper end of staving is provided with guardrail rack (27), the upper end of guardrail rack is provided with guardrail (28), cofferdam road slab (29) is provided with in guardrail rack, the bottom of cofferdam bucket is provided with setting-out hole (33), fixed connecting plate and the upper end being fixedly connected with groove are provided with and fixedly mount hole (39).
CN201420716989.1U 2014-11-26 2014-11-26 Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore Expired - Fee Related CN204252160U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420716989.1U CN204252160U (en) 2014-11-26 2014-11-26 Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420716989.1U CN204252160U (en) 2014-11-26 2014-11-26 Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore

Publications (1)

Publication Number Publication Date
CN204252160U true CN204252160U (en) 2015-04-08

Family

ID=52956485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420716989.1U Expired - Fee Related CN204252160U (en) 2014-11-26 2014-11-26 Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore

Country Status (1)

Country Link
CN (1) CN204252160U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404981A (en) * 2014-11-26 2015-03-11 闫传桂 Sea bottom construction walkway and cofferdam in seaside rising/falling tide zone

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404981A (en) * 2014-11-26 2015-03-11 闫传桂 Sea bottom construction walkway and cofferdam in seaside rising/falling tide zone

Similar Documents

Publication Publication Date Title
CN104264704A (en) Combination type hexagon buoyancy tank foundation for seaborne anemometer tower
CN102839634B (en) Construction method for life-saving water bank ecological vegetation box
CN107972828A (en) A kind of offshore platform
CN104404981B (en) Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore
CN110155264A (en) Offshore wind turbine composite tube basis towage structure and method for towing
CN207392286U (en) A kind of eddy current type gas disturbs Fine Sediments in Estuaries dredger
CN202610825U (en) Prefabricated reinforced concrete-caisson-type offshore wind turbine foundation structure
CN204252160U (en) Rise the ebb subsea construction plank road in area and cofferdam in a kind of seashore
CN102535393A (en) Floating breakwater provided with wave power generating device and capable of being detached and installed fast
CN105019471A (en) Inclined type barrel-shaped foundation mooring system and construction method thereof
CN103088801A (en) One-step integral installation platform for offshore wind turbine and pile foundation
CN110758662A (en) Movable free-rising and sinking storm platform
CN204551504U (en) A kind of cofferdam of partly diving under water of repairing for channel side slopes lining project
CN211032946U (en) Movable free-rising and sinking storm platform
CN205205851U (en) Tilting bucket foundation mooring system
CN207670621U (en) A kind of offshore platform
CN203497139U (en) Amphibious platform for mining vertical pump
CN203238655U (en) Offshore wind power single pile foundation-based tidal current energy power generation foundation structure
CN203924089U (en) For the pile foundation of offshore wind farm facility
CN202451974U (en) Anti-floating structure of buried pipeline
CN203497140U (en) Amphibious platform for mining vertical pump
CN202644549U (en) Single-wall steel hanging box cofferdam
CN201817199U (en) Automatic leveling device for semisubmersible barge crane platform
CN207092031U (en) A kind of dam
CN206784354U (en) A kind of U-shaped casing seal installation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150408

Termination date: 20151126