CN204139642U - The additional elevator structure of old cell unit reveal - Google Patents

The additional elevator structure of old cell unit reveal Download PDF

Info

Publication number
CN204139642U
CN204139642U CN201420412423.XU CN201420412423U CN204139642U CN 204139642 U CN204139642 U CN 204139642U CN 201420412423 U CN201420412423 U CN 201420412423U CN 204139642 U CN204139642 U CN 204139642U
Authority
CN
China
Prior art keywords
newly
increased
balcony
elevator
original
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420412423.XU
Other languages
Chinese (zh)
Inventor
董有
谢建明
鞠树森
马凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING BLESS BUILDING Co Ltd
Original Assignee
BEIJING BLESS BUILDING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING BLESS BUILDING Co Ltd filed Critical BEIJING BLESS BUILDING Co Ltd
Priority to CN201420412423.XU priority Critical patent/CN204139642U/en
Application granted granted Critical
Publication of CN204139642U publication Critical patent/CN204139642U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model relates to the additional elevator structure of a kind of old cell unit reveal, belong to technical field of anti-seismic reinforcement, it is provided with additional elevator on original body of wall of old cell unit reveal, the side of additional elevator is connected with a newly-increased entrance garden, additional elevator opposite side is connected with elevator hall and newly-increased balcony successively, newly-increased entrance garden is connected with the original balcony outside an original bedroom, family, and newly-increased balcony is directly connected with original bedroom, another family; Additional elevator, newly-increased entrance garden, newly-increased balcony and elevator hall are steel framed structure; Additional elevator comprises hoistway and car; Hoistway, newly-increased entrance garden, newly-increased balcony and elevator hall are all formed primarily of newly-increased frame column and newly-increased Vierendeel girder, are also arranged with mounting bracket beam in parallel below the newly-increased Vierendeel girder of hoistway; Additional elevator, newly-increased entrance garden, newly-increased balcony and elevator hall are arranged on the foundation ditch of bottom, and are all connected with original wall outer side by newly-increased frame column.

Description

The additional elevator structure of old cell unit reveal
Technical field
The utility model relates to the additional elevator structure of a kind of old cell unit reveal, belongs to technical field of anti-seismic reinforcement.
Background technology
The masonry residential that the 80s and 90s in last century builds does not have lift-mounting mostly, and along with the quickening of aging population process and the raising day by day of Living consumption, aging blocks install elevator additional will become the common requirements of society gradually.From the current market demand, although it is increasing to require that aging blocks install the cry of elevator additional, difficulty is still not little.For the residential building that a building is common, basic, normal, high layer resident family interests differ, and position is also different, and the not relevant subsidy policy in some city, and resident's huge fund of being unwilling again installs elevator additional, therefore can cause the financing gap problem installing elevator additional.
Utility model content
For solving the problem, the utility model proposes a kind of under the prerequisite ensureing elevator using function and safety, the additional elevator structure of one old cell unit reveal that elevator cost and installation cost lower.Effectively solve the problem of old community resident trip.
The technical solution of the utility model is as follows:
The additional elevator structure of a kind of old cell unit reveal, original body of wall of old cell unit reveal is provided with additional elevator, the side of additional elevator is connected with a newly-increased entrance garden, additional elevator opposite side is connected with elevator hall and newly-increased balcony successively, described newly-increased entrance garden is connected with the original balcony outside an original bedroom, family, and newly-increased balcony is directly connected with original bedroom, another family; Described additional elevator, newly-increased entrance garden, newly-increased balcony and elevator hall are steel framed structure; Described additional elevator comprises hoistway and car; Described hoistway, newly-increased entrance garden, newly-increased balcony and elevator hall are all formed primarily of newly-increased frame column and newly-increased Vierendeel girder, are also arranged with mounting bracket beam in parallel below the newly-increased Vierendeel girder of described hoistway; Described additional elevator, newly-increased entrance garden, newly-increased balcony and elevator hall are all connected with original wall outer side by newly-increased frame column.
Further, be provided with family door between the original balcony outside the original bedroom of described newly-increased entrance garden and a family, between described elevator hall and described newly-increased balcony, be provided with family door.
Further, wherein, couplet on the door window is provided with between original bedroom at a family and original balcony; Described newly-increased balcony and another family are also provided with couplet on the door window between original bedroom.
Further, described newly-increased frame column and original body of wall adopt M10 crab-bolt and otic placode to be connected, and anchoring spacing is 500mm.Otic placode and newly-increased frame column weld together.
Further, between former staircase and elevator hall, offer hole, outside elevator hall, offer door or window.
Further, be connected with the reinforced concrete wall of bottom by junction steel plate and chemical bolt bottom described newly-increased frame column, be provided with reinforced concrete floor bottom reinforced concrete wall, below reinforced concrete floor, be provided with concrete cushion.
Further, described junction steel plate specification is 350 × 350 × 20mm; Described reinforced concrete base plate thickness is 500mm, and steel concrete wall thickness is 250mm; Described tunnel dimension is 1500mm × 1500mm, and car size is 800mm × 600mm; Described newly-increased frame column and newly-increased Vierendeel girder are square steel pipe, and sectional dimension is 150mm × 150mm × 8mm, and described mounting bracket trammel lattice are [24a; Chemical bolt is M20 chemical bolt.
Further, bottom described newly-increased frame column, periphery is provided with wing plate, and is connected with junction steel plate.
The construction method of the additional elevator structure of above-mentioned old cell unit reveal, concrete construction method is as follows
Step one: according to design drawing, removes original refuse chute of old cell unit reveal, and what have unit every to pile up neatly also needs dismounting;
Step 2: by drawing the additional elevator pre-installed position of old cell unit reveal and newly-increased entrance garden, newly-increased balcony and elevator hall pre-set position excavation pit;
Step 3: beat concrete cushion bottom foundation ditch, and upwards pouring reinforcement concrete base plate and reinforced concrete wall successively, bury junction steel plate and chemical bolt underground simultaneously on reinforced concrete wall;
Step 4: after above-mentioned steps completes, the newly-increased frame column forming additional elevator is arranged on cast-in-place concrete wall by junction steel plate, the newly-increased frame column being close to original body of wall side adopts crab-bolt to be connected with the constructional column in original body of wall or original body of wall, adopts newly-increased Vierendeel girder and mounting bracket beam to be welded to connect between newly-increased frame column;
Step 5: after the newly-increased frame column of additional elevator has been located, according to the method in step 4, newly-increased entrance garden, the newly-increased frame column increasing balcony and elevator hall newly and newly-increased Vierendeel girder are installed equally, carry out newly-increased entrance garden, increase the construction of balcony and elevator hall newly;
Step 6: make the window of original bedroom and newly-increased balcony junction into couplet on the door window, make the exterior window between former staircase and elevator hall into hole, and set up guardrail, newly-increased entrance garden, newly-increased balcony and elevator hall arrange floor and exterior wall, elevator hall's exterior wall arranges window;
Step 7: install car in hoistway;
Step 8: antirust, anti-corrosive process is carried out to steel framed structure.
Further, described floor is steel plate, and adopts bolt to be connected with newly-increased frame column and newly-increased Vierendeel girder.
Beneficial effect: adopt the additional elevator structure of old cell unit reveal of the present utility model and construction method, its most significant advantage is that elevator volume is little, and cost is low, be installed at cell gate side, exceed and take path space, and foundation ditch is relatively shallow, less on pipeline impact.
Accompanying drawing explanation
Fig. 1 is the additional elevator floor map of multi-storey building unit reveal;
Fig. 2 hoistway axonometric drawing;
Fig. 3 hoistway sectional drawing;
Fig. 4 suspension column connection layout;
Fig. 5 increases frame column and wall connecting figure newly;
In figure, 1: additional elevator; 2: newly-increased entrance garden; 3: newly-increased balcony 4: newly-increased frame column; 5: newly-increased Vierendeel girder; 6: mounting bracket beam; 7: original body of wall; 8, constructional column; 9: chemical bolt; 10: family door; 11: couplet on the door window; 12: foundation ditch; 13: concrete cushion; 14: cast-in-situ concrete base plate; 15: cast-in-place concrete wall; 16: junction steel plate; 17: wing plate; 18:M10 crab-bolt; 19: otic placode.
Detailed description of the invention
As Figure 1-5, the utility model is the additional elevator structure of a kind of old cell unit reveal, original body of wall 7 of multilayer old cell unit reveal is provided with additional elevator 1, the side of additional elevator 1 is connected with a newly-increased entrance garden 2, additional elevator 1 opposite side is connected with elevator hall and newly-increased balcony 3 successively, newly-increased entrance garden 2 is connected with the original balcony outside an original bedroom, family, and newly-increased balcony 3 is directly connected (as shown in Figure 1) with original bedroom, another family.Additional elevator 1, newly-increased entrance garden 2, newly-increased balcony 3 and elevator hall are steel framed structure.Additional elevator 1 comprises hoistway and car, hoistway, newly-increased entrance garden 2, newly-increased balcony 3 and elevator hall are all formed primarily of newly-increased frame column 4 and newly-increased Vierendeel girder 5, also be arranged with mounting bracket beam 6 (as shown in Figure 2) below the newly-increased Vierendeel girder 5 of hoistway in parallel, additional elevator 1, newly-increased entrance garden 2, newly-increased balcony 3 and elevator hall are all connected with outside original body of wall 7 by newly-increased frame column 4.Wherein, increase newly between the original balcony outside entrance garden 2 and original bedroom, a family and be provided with family door 10, between elevator hall and described newly-increased balcony 3, be provided with family door 10.Be provided with couplet on the door window 11 between original bedroom at one family and original balcony, increase newly and be also provided with couplet on the door window 11 between balcony 3 and original bedroom, another family.Newly-increased frame column 4 adopts M10 crab-bolt 18 and otic placode 19 to be connected (as shown in Figure 5) with original body of wall 7, and anchoring spacing is 500mm.Offer hole between former staircase and elevator hall, outside elevator hall, offer door or window.Be connected with the reinforced concrete wall 15 of bottom by junction steel plate 16 and chemical bolt 9 bottom newly-increased frame column 4, be provided with reinforced concrete floor 14 bottom reinforced concrete wall 15, reinforced concrete floor 14 is provided with concrete cushion 13 (as shown in Figure 3) below.Wherein, junction steel plate 16 specification is 350 × 350 × 20mm, reinforced concrete base plate 14 thickness is 500mm, reinforced concrete wall 15 is thick is 250mm, tunnel dimension is 1500mm × 1500mm, and car size is 800mm × 600mm, and newly-increased frame column 4 and newly-increased Vierendeel girder 5 are square steel pipe, sectional dimension is 150mm × 150mm × 8mm, and mounting bracket beam 6 specification is [24a; Chemical bolt 9 is M20 chemical bolt 9.In addition, bottom newly-increased frame column 4, periphery is also provided with wing plate 17, and is connected (as shown in Figure 4) with junction steel plate 16.
The construction method of the additional elevator structure of above-mentioned old cell unit reveal, concrete construction method is as follows
Step one: according to design drawing, removes original refuse chute of old cell unit reveal, and what have unit every to pile up neatly also needs dismounting;
Step 2: by drawing additional elevator 1 pre-installed position of old cell unit reveal and newly-increased entrance garden 2, newly-increased balcony 3 and elevator hall pre-set position excavation pit 12;
Step 3: beat concrete cushion 13 bottom foundation ditch 12, and upwards pouring reinforcement concrete base plate 14 and reinforced concrete wall 15 successively, bury junction steel plate 16 and chemical bolt 9 underground simultaneously on reinforced concrete wall 15;
Step 4: after above-mentioned steps completes, the newly-increased frame column 4 forming additional elevator 1 is arranged on cast-in-place concrete wall 15 by junction steel plate 16, the newly-increased frame column 4 being close to original body of wall 7 side adopts crab-bolt to be connected with the constructional column 8 in original body of wall 7 or original body of wall 7, adopts newly-increased Vierendeel girder 5 and mounting bracket beam 6 to be welded to connect between newly-increased frame column 4;
Step 5: after the newly-increased frame column 4 of additional elevator 1 has been located, according to the method in step 4, newly-increased entrance garden 2, the newly-increased frame column 4 increasing balcony 3 and elevator hall newly and newly-increased Vierendeel girder 5 are installed equally, carry out newly-increased entrance garden 2, increase the construction of balcony 3 and elevator hall newly;
Step 6: make the window of original bedroom and newly-increased balcony 3 junction into couplet on the door window 11, make the exterior window between former staircase and elevator hall into hole, and set up guardrail, newly-increased entrance garden 2, newly-increased balcony 3 and elevator hall arrange floor and exterior wall, elevator hall's exterior wall arranges window, wherein, floor is steel plate, and adopts bolt to be connected with newly-increased frame column 4 and newly-increased Vierendeel girder 5;
Step 7: install car in hoistway;
Step 8: antirust, anti-corrosive process is carried out to steel framed structure.
Be more than an exemplary embodiment of the present utility model, concrete enforcement of the present utility model is not limited thereto.

Claims (7)

1. the additional elevator structure of old cell unit reveal, it is characterized in that: on original body of wall (7) of old cell unit reveal, be provided with additional elevator (1), the side of additional elevator (1) is connected with a newly-increased entrance garden (2), additional elevator (1) opposite side is connected with elevator hall and newly-increased balcony (3) successively, described newly-increased entrance garden (2) is connected with the original balcony outside an original bedroom, family, hole is offered between described elevator hall and former staircase, door or window is offered outside elevator hall, newly-increased balcony (3) is directly connected with original bedroom, another family, described additional elevator (1), newly-increased entrance garden (2), newly-increased balcony (3) and elevator hall are steel framed structure, described additional elevator (1) comprises hoistway and car, described hoistway, newly-increased entrance garden (2), newly-increased balcony (3) and elevator hall are all formed primarily of newly-increased frame column (4) and newly-increased Vierendeel girder (5), and newly-increased Vierendeel girder (5) below of described hoistway is also arranged with mounting bracket beam (6) in parallel, described additional elevator (1), newly-increased entrance garden (2), newly-increased balcony (3) and elevator hall are all connected with original body of wall (7) outside by newly-increased frame column (4).
2. the additional elevator structure of old cell unit reveal according to claim 1, it is characterized in that: be provided with family door (10) between the original balcony outside described newly-increased entrance garden (2) and original bedroom, a family, between described elevator hall and described newly-increased balcony (3), be provided with family door (10).
3. the additional elevator structure of old cell unit reveal according to claim 1, is characterized in that: wherein, is provided with couplet on the door window (11) between original bedroom at a family and original balcony; Described newly-increased balcony (3) and another family are also provided with couplet on the door window (11) between original bedroom.
4. the additional elevator structure of old cell unit reveal according to claim 1, it is characterized in that: described newly-increased frame column (4) and original body of wall (7) adopt M10 crab-bolt (18) and otic placode (19) to be connected, and anchoring spacing is 500mm.
5. the additional elevator structure of old cell unit reveal according to claim 1, it is characterized in that: described newly-increased frame column (4) bottom is connected with the reinforced concrete wall (15) of bottom by junction steel plate (16) and chemical bolt (9), reinforced concrete wall (15) bottom is provided with reinforced concrete floor (14), and reinforced concrete floor (14) is provided with concrete cushion (13) below.
6. the additional elevator structure of old cell unit reveal according to claim 5, is characterized in that: described junction steel plate (16) specification is 350 × 350 × 20mm; Described reinforced concrete base plate (14) thickness is 500mm, and reinforced concrete wall (15) is thick is 250mm; Described tunnel dimension is 1500mm × 1500mm, and car size is 800mm × 600mm; Described newly-increased frame column (4) and newly-increased Vierendeel girder (5) are square steel pipe, and sectional dimension is 150mm × 150mm × 8mm, and described mounting bracket beam (6) specification is [24a; Chemical bolt (9) is M20 chemical bolt (9).
7. the additional elevator structure of old cell unit reveal according to claim 6, is characterized in that: periphery, described newly-increased frame column (4) bottom is provided with wing plate (17), and is connected with junction steel plate (16).
CN201420412423.XU 2014-07-24 2014-07-24 The additional elevator structure of old cell unit reveal Expired - Fee Related CN204139642U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420412423.XU CN204139642U (en) 2014-07-24 2014-07-24 The additional elevator structure of old cell unit reveal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420412423.XU CN204139642U (en) 2014-07-24 2014-07-24 The additional elevator structure of old cell unit reveal

Publications (1)

Publication Number Publication Date
CN204139642U true CN204139642U (en) 2015-02-04

Family

ID=52416337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420412423.XU Expired - Fee Related CN204139642U (en) 2014-07-24 2014-07-24 The additional elevator structure of old cell unit reveal

Country Status (1)

Country Link
CN (1) CN204139642U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196257A (en) * 2014-07-24 2014-12-10 北京筑福国际工程技术有限责任公司 Additionally-arranged elevator structure located on cell gate side of old community and construction method thereof
CN108277997A (en) * 2018-02-27 2018-07-13 同济大学 Modular assembly formula elevator-integrated system of balcony with complementary antidetonation/vibration absorption unit
CN108457370A (en) * 2018-02-27 2018-08-28 同济大学 Prefabricated assembled modularization self-supporting elevator-balcony system with connection vibration absorption unit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196257A (en) * 2014-07-24 2014-12-10 北京筑福国际工程技术有限责任公司 Additionally-arranged elevator structure located on cell gate side of old community and construction method thereof
CN108277997A (en) * 2018-02-27 2018-07-13 同济大学 Modular assembly formula elevator-integrated system of balcony with complementary antidetonation/vibration absorption unit
CN108457370A (en) * 2018-02-27 2018-08-28 同济大学 Prefabricated assembled modularization self-supporting elevator-balcony system with connection vibration absorption unit

Similar Documents

Publication Publication Date Title
CN103510640B (en) A kind of fabricated shear wall and assembly method thereof
CN103362317B (en) Story adding and stair adding structure of existing masonry building, and construction method thereof
CN104196257B (en) The additional elevator structure of old cell unit reveal and construction method
CN204139642U (en) The additional elevator structure of old cell unit reveal
CN206467788U (en) A kind of concrete floor magnetic bolts attachment structure
CN105386464B (en) Inlet and outlet part for maintenance of intelligent urban underground comprehensive pipe gallery
CN205224733U (en) Prefabricated assembled open caisson underground garage structure
CN208294122U (en) A kind of structure installing elevator additional on the outside of existing building
CN104314105B (en) The connection vertical piece structure of the basement wall and cast-in-place buttress and construction method
CN203922362U (en) Build-up type modularization steel structure lift shaft
CN203394096U (en) Layer-adding and ladder-adding structure for existing masonry building
CN212866010U (en) Prefabricated assembly type case becomes basis
CN105888281A (en) Method for utilizing jacking storey-adding technique to promote integrated function of community
KR101566528B1 (en) Basement extension construction method using underground structure
CN211115052U (en) Shaft type underground stereo garage structure
CN103243931B (en) Multi-story masonry unit-door external elevator structure and construction method thereof
CN103352579B (en) Adopt strengthening reconstruction masonry structure and the construction method of additional shelter bridge and additional elevator
CN204703190U (en) A kind of underground shallow layer automatic parking garage storehouse body structure
CN208167799U (en) A kind of ripple steel composites structure and the double storehouse pipe galleries of reinforced concrete combination assembled
CN203546944U (en) Assembly type shear wall
CN103046779B (en) Multi-layer air garage
CN203394094U (en) Reinforced and reconstructed masonry structure using external gallery bridge and external elevator
CN204919989U (en) Collect steel - concrete combination special -shaped post of heat preservation bearing in an organic whole
CN211114642U (en) Connection structure of security protection door and main wall body
CN103255834A (en) Prefabricated heat-preservation balcony suitable for industrial production and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150204

Termination date: 20190724

CF01 Termination of patent right due to non-payment of annual fee