CN204040453U - A kind of novel scaffold Tiebar structure for civil construction project - Google Patents

A kind of novel scaffold Tiebar structure for civil construction project Download PDF

Info

Publication number
CN204040453U
CN204040453U CN201420415538.4U CN201420415538U CN204040453U CN 204040453 U CN204040453 U CN 204040453U CN 201420415538 U CN201420415538 U CN 201420415538U CN 204040453 U CN204040453 U CN 204040453U
Authority
CN
China
Prior art keywords
group
hookup
hole
connecting part
pull bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420415538.4U
Other languages
Chinese (zh)
Inventor
陈志云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiang Jianqiang
Jiangxi Zhejiang Eagle Construction Engineering Co ltd
Ou Feng
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420415538.4U priority Critical patent/CN204040453U/en
Application granted granted Critical
Publication of CN204040453U publication Critical patent/CN204040453U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a kind of novel scaffold Tiebar structure for civil construction project, comprise hookup and the rod assembly being located at hookup side, hookup side is provided with a perforation, rod assembly comprises group joint and pull bar, group joint is in order to cylinder lever connecting rod and hookup, group joint comprises head and is convexly equipped in the group connecting part of head one end, head is connected to inside hookup, group connecting part passes the perforation of hookup, one end that group connecting part protrudes perforation is also provided with the first through hole, one end of pull bar is socketed on outside group connecting part, pull bar is provided with the second through hole be communicated with the first through hole, coupling assembling connects group through the first through hole and the second through hole in order to group and connects pull bar and group connecting part.Pull bar of the present utility model is connected with group joint by coupling assembling, and then is fixed on the side of hookup, therefore easily assembles, can reduce manufacturing cost, be suitable for large-scale production, and does not affect overall rigidity, reduces energy consumption, has practicality.

Description

A kind of novel scaffold Tiebar structure for civil construction project
Technical field
The utility model relates to civil construction project technical field, refers to a kind of novel scaffold Tiebar structure for civil construction project especially.
Background technology
At present, scaffold is firmly erected at the outside of building, usually need to utilize multiple scaffold pull bar to connect scaffold steel pipe on wall.And scaffold pull bar on the market not only manufacturing cost is high, and need to rely on welding to be fixed, cause syndeton to lose efficacy if there is the situations such as rosin joint, there is larger potential safety hazard.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of novel scaffold Tiebar structure for civil construction project, to solve scaffold pull bar in prior art, not only manufacturing cost is high, and need to rely on welding to be fixed, cause syndeton to lose efficacy if there is the situations such as rosin joint, there is the problem of larger potential safety hazard.
For solving the problems of the technologies described above, embodiment of the present utility model provides a kind of novel scaffold Tiebar structure for civil construction project, comprise hookup and the rod assembly being located at hookup side, described hookup can supply clip scaffold steel pipe, described rod assembly can for the wall of connecting building thing, described hookup side is provided with a perforation, described rod assembly comprises group joint and pull bar, described group of joint is in order to cylinder lever connecting rod and hookup, described group of joint comprises head and is convexly equipped in the group connecting part of head one end, described head is connected to inside hookup, described group connecting part passes the perforation of hookup, one end that described group connecting part protrudes perforation is also provided with the first through hole, one end of described pull bar is socketed on outside group connecting part, described pull bar is provided with the second through hole be communicated with described first through hole, coupling assembling connects described group through described first through hole and the second through hole in order to group and connects pull bar and group connecting part.
Wherein, in a tubular form, described first through hole radial direction extension is arranged in group connecting part to described group connecting part.
Wherein, described second through hole radial direction extension is arranged in pull bar one end.
Wherein, described coupling assembling comprises bolt and nut, and described bolt is through described first through hole and the second through hole, and described nut is bolted in bolt end.
The beneficial effect of technique scheme of the present utility model is as follows:
In such scheme, novel scaffold Tiebar structure for civil construction project of the present utility model, its pull bar is connected with group joint by coupling assembling, and then be fixed on the side of hookup, therefore easily assemble, can manufacturing cost be reduced, be suitable for large-scale production, and do not affect overall rigidity, reduce energy consumption, there is practicality.
Accompanying drawing explanation
Fig. 1 is the structural representation of the novel scaffold Tiebar structure for civil construction project of the utility model embodiment.
Fig. 2 is the sectional view of the rod assembly of the utility model embodiment.
Detailed description of the invention
For making the technical problems to be solved in the utility model, technical scheme and advantage clearly, be described in detail below in conjunction with the accompanying drawings and the specific embodiments.
As depicted in figs. 1 and 2, a kind of novel scaffold Tiebar structure for civil construction project that the utility model embodiment provides, comprise hookup 1 and the rod assembly 2 being located at hookup 1 side, described hookup 1 can supply clip scaffold steel pipe, described rod assembly 2 can for the wall of connecting building thing, described hookup 1 side is provided with a perforation 11, described rod assembly 2 comprises group joint 21 and pull bar 22, described group of joint 21 is in order to cylinder lever connecting rod 22 and hookup 1, described group of joint 21 comprises head 211 and is convexly equipped in the group connecting part 212 of head 211 one end, described head 211 is connected to inside hookup 1, described group connecting part 212 passes the perforation 11 of hookup 1, one end that described group connecting part 212 protrudes perforation 11 is also provided with the first through hole 213, one end of described pull bar 22 is socketed on outside group connecting part 212, described pull bar 22 is provided with the second through hole 221 be communicated with described first through hole 213, coupling assembling 3 connects described group through described first through hole 213 and the second through hole 221 in order to group and connects pull bar 22 and group connecting part 212.
In a tubular form, described first through hole 213 radial direction extension is arranged in group connecting part to described group connecting part 212.
Described second through hole 221 radial direction extension is arranged in pull bar 22 one end.
Described coupling assembling 3 comprises bolt 31 and nut 32, and described bolt 31 is through described first through hole 213 and the second through hole 221, and described nut 32 is bolted in bolt 31 end.
In such scheme, novel scaffold Tiebar structure for civil construction project of the present utility model, its pull bar is connected with group joint by coupling assembling, and then be fixed on the side of hookup, therefore easily assemble, can manufacturing cost be reduced, be suitable for large-scale production, and do not affect overall rigidity, reduce energy consumption, there is practicality.
The above is preferred embodiment of the present utility model; should be understood that; for those skilled in the art; under the prerequisite not departing from principle described in the utility model; can also make some improvements and modifications, these improvements and modifications also should be considered as protection domain of the present utility model.

Claims (4)

1. the novel scaffold Tiebar structure for civil construction project, comprise hookup and the rod assembly being located at hookup side, described hookup can supply clip scaffold steel pipe, described rod assembly can for the wall of connecting building thing, it is characterized in that, described hookup side is provided with a perforation, described rod assembly comprises group joint and pull bar, described group of joint is in order to cylinder lever connecting rod and hookup, described group of joint comprises head and is convexly equipped in the group connecting part of head one end, described head is connected to inside hookup, described group connecting part passes the perforation of hookup, one end that described group connecting part protrudes perforation is also provided with the first through hole, one end of described pull bar is socketed on outside group connecting part, described pull bar is provided with the second through hole be communicated with described first through hole, coupling assembling connects described group through described first through hole and the second through hole in order to group and connects pull bar and group connecting part.
2. the novel scaffold Tiebar structure for civil construction project according to claim 1, is characterized in that, in a tubular form, described first through hole radial direction extension is arranged in group connecting part to described group connecting part.
3. the novel scaffold Tiebar structure for civil construction project according to claim 1, is characterized in that, described second through hole radial direction extension is arranged in pull bar one end.
4. the novel scaffold Tiebar structure for civil construction project according to Claims 2 or 3, it is characterized in that, described coupling assembling comprises bolt and nut, and described bolt is through described first through hole and the second through hole, and described nut is bolted in bolt end.
CN201420415538.4U 2014-07-25 2014-07-25 A kind of novel scaffold Tiebar structure for civil construction project Expired - Fee Related CN204040453U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420415538.4U CN204040453U (en) 2014-07-25 2014-07-25 A kind of novel scaffold Tiebar structure for civil construction project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420415538.4U CN204040453U (en) 2014-07-25 2014-07-25 A kind of novel scaffold Tiebar structure for civil construction project

Publications (1)

Publication Number Publication Date
CN204040453U true CN204040453U (en) 2014-12-24

Family

ID=52241136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420415538.4U Expired - Fee Related CN204040453U (en) 2014-07-25 2014-07-25 A kind of novel scaffold Tiebar structure for civil construction project

Country Status (1)

Country Link
CN (1) CN204040453U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284969A (en) * 2016-09-18 2017-01-04 广西钦州展兴建设工程有限公司 A kind of building buckle

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284969A (en) * 2016-09-18 2017-01-04 广西钦州展兴建设工程有限公司 A kind of building buckle

Similar Documents

Publication Publication Date Title
CN204551757U (en) The semi-rigid connection joints of steel structure of a kind of pin type
CN201129026Y (en) Telescopic tie bar for scaffold
CN204040453U (en) A kind of novel scaffold Tiebar structure for civil construction project
CN204252623U (en) A kind of easy-to-mount bracing wire sheath
CN204001667U (en) A kind of novel scaffold Tiebar structure for civil construction project
CN204000605U (en) A kind of steel bridge guardrail
CN204034785U (en) Roll squeezer reductor not damaged detaching structure
CN104006054A (en) Multifunctional u-shaped adjusting bolt
CN204326677U (en) Novel power transmission power line steel tuble pole
CN204640052U (en) A kind of Novel bolt spanner
CN204027773U (en) Tightness test frock
CN202273964U (en) Pull ring connecting piece
CN202280251U (en) Positioning mechanism
CN202348856U (en) Novel joint structure
CN204265232U (en) A kind of I-beam section uses stressed suspension rod
CN105443532A (en) Expansion bolt convenient to use
CN204061152U (en) A kind of hollow Wear-resisting plunger
CN204357353U (en) A kind of reaming bit
CN204876618U (en) Multi -functional limit protector that faces
CN202273601U (en) Heat insulation collar
CN204370688U (en) Beam column of steel structure
CN203397844U (en) Bell-type oil tank ground connection structure
CN203977288U (en) Convenient cap
CN203361326U (en) Main body framework for combined house
CN203834684U (en) Sleeve type round steel column-H type steel beam connection node structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: JIANG JIANQIANG

Effective date: 20150105

Free format text: FORMER OWNER: JIANG JIANQIANG

Effective date: 20150105

Owner name: OU FENG

Free format text: FORMER OWNER: CHEN ZHIYUN

Effective date: 20150105

Owner name: JIANGXI ZHEYING CONSTRUCTION PROJECT CO., LTD.

Free format text: FORMER OWNER: OU FENG

Effective date: 20150105

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 315100 NINGBO, ZHEJIANG PROVINCE TO: 335000 YINGTAN, JIANGXI PROVINCE

Free format text: CORRECT: ADDRESS; FROM: 315700 NINGBO, ZHEJIANG PROVINCE TO: 315100 NINGBO, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20150105

Address after: Five, Yingtan hi tech Zone, Jiangxi small and micro enterprise incubator building 335000 (opposite sunshine three District)

Patentee after: Jiangxi Zhejiang Eagle Construction Engineering Co.,Ltd.

Address before: 315100 Zhejiang city of Ningbo province Yinzhou District River Street Yongtai garden 40 building 119, room 103

Patentee before: Ou Feng

Patentee before: Jiang Jianqiang

Effective date of registration: 20150105

Address after: 315100 Zhejiang city of Ningbo province Yinzhou District River Street Yongtai garden 40 building 119, room 103

Patentee after: Ou Feng

Patentee after: Jiang Jianqiang

Address before: 315700 Xinfeng City, Ningbo province Dan Xiangshan City Road, No. 205,

Patentee before: Chen Zhiyun

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141224