CN204010000U - A kind of steel construction tracking control of full process system - Google Patents

A kind of steel construction tracking control of full process system Download PDF

Info

Publication number
CN204010000U
CN204010000U CN201420011936.XU CN201420011936U CN204010000U CN 204010000 U CN204010000 U CN 204010000U CN 201420011936 U CN201420011936 U CN 201420011936U CN 204010000 U CN204010000 U CN 204010000U
Authority
CN
China
Prior art keywords
steel structure
structure member
active rfid
half active
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420011936.XU
Other languages
Chinese (zh)
Inventor
廖选茂
李春田
蔡玉龙
邵则振
范彩霞
廖彪
温小勇
孔维拯
刘为飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Steel Structure Engineering Co Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201420011936.XU priority Critical patent/CN204010000U/en
Application granted granted Critical
Publication of CN204010000U publication Critical patent/CN204010000U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model is applicable to building field, a kind of steel construction tracking control of full process system is provided, has comprised and be fixed with the steel structure member of half active RFID tag, some half active RFID identification terminal and terminal devices that is distributed in each operation that steel structure member will flow through; Described half active RFID identification terminal all described half active RFID tag is identified, upgraded to described half active RFID tag in each operation stage of described steel structure member in canned data, and position up-to-date steel structure member and status information are sent to described terminal device; Described terminal device is connected with described half active RFID identification terminal, for receiving and store the residing position of steel structure member and status information.Described steel construction tracking control of full process system can realize steel structure member from making, be transported to the information system management that overall process is installed, and energy real-time follow-up, carries out in time the correction of construction period and carries out engineering design change management.

Description

A kind of steel construction tracking control of full process system
Technical field
The utility model belongs to building field, relates in particular to a kind of steel construction tracking control of full process system.
Background technology
Construction steel structure member complexity, of a great variety, node is complicated, structure manufacture and installment work are very loaded down with trivial details, the steel structure member of particularly using on a certain branch of some engineerings or subitem is very similar, or just some differences of size, for distinguishing and Comparison of Management trouble of they, need Unified number to carry out tracing management.
Construction steel structure making at present and existing installation component coding are fairly simple, in various member, extremely easily chaotic, also need to consume a large amount of man power and materials and from numerous members, find a certain member simultaneously.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of steel construction tracking control of full process method and tracker, is intended to solve the problem that steel structure member is difficult to management in making and installation process.
The utility model is achieved in that a kind of steel construction tracking control of full process system, comprising: be fixed with the steel structure member of half active RFID tag, some half active RFID identification terminal and terminal devices that is distributed in each operation that steel structure member will flow through;
Described half active RFID identification terminal all described half active RFID tag is identified, upgraded to described half active RFID tag in each operation stage of described steel structure member in canned data, and position up-to-date steel structure member and status information are sent to described terminal device;
Described terminal device is connected with described half active RFID identification terminal, for receiving and store the residing position of steel structure member and status information.
Further, described terminal device is connected with Internet of Things tracker management platform by Internet of Things, and residing steel structure member position and status information are sent to described Internet of Things tracker management platform.
Further, described half active RFID identification terminal is arranged on respectively: stockyard, steel structure member lifting place and the steel structure member of steel structure member packaging technology place, steel structure member welding technology place, steel structure member means of transport, steel structure member are proofreaied and correct place.
The utility model compared with prior art, beneficial effect is: by adopt mode that half active RFID tag combines with half active RFID identification terminal to each root steel structure member accurately search, locate, monitoring and real-time follow-up, realize steel structure member from making, be transported to the information system management that overall process is installed, improved scientific and technical information management level and operating efficiency.
Brief description of the drawings
Fig. 1 is the structural representation of the steel construction tracking control of full process system that provides of the utility model embodiment;
Fig. 2 is the steel construction overall process platform of internet of things framework schematic diagram that the utility model embodiment provides.
Embodiment
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein is only in order to explain the utility model, and be not used in restriction the utility model.
Shown in Fig. 1, Fig. 2, a kind of steel construction tracking control of full process system, comprises the following steps: S1, half active RFID (Radio Frequency Identification, radio-frequency (RF) identification) label 101 is set on each root steel structure member; The build-in attribute information and the variableness information that in described half active RFID tag 101, include steel structure member, described variableness information was upgraded according to the residing operation of the steel structure member stage; S2, all identify by double active RFID tag of half active RFID identification terminal 101 in each operation stage of described steel structure member, and upgrade the variableness information of the steel structure member that wherein comprises, to determine the residing position of described steel structure member and status information and position and status information transmitted.
In step S2, specifically comprise: half active RFID identification terminal 102 sends to the Internet of Things tracker management platform in terminal device 103 by Internet of Things the data of described position and state.In the tracking of construction steel structure member, adopt mode that Internet of Things and half active RFID combine can be within the scope of certain distance detection and identify to the data of half active RFID tag 101, in implementing at the scene, be easy to manipulation, identification work need not manual intervention.Half active RFID identification terminal 102 both can support read-only mode of operation also can support reading writing working pattern, and without contact or aiming, can under various rugged surroundings, freely work, and short-range radio frequency product is not afraid of the rugged environment such as oil stain, contamination by dust.For example, be used in tracking object on the streamline of starting material stockyard Search and Orientation and structure steel fabrication; Length is used in component conveying traffic apart from radio frequency products, and decipherment distance can reach tens meters, also can be used for having member stockyard to find member etc.
In step S1, half active RFID tag 101 is made up of build-in attribute information and the variableness information of steel structure member.The build-in attribute information of half active RFID tag 101 is project member numbering, and this numbering is consistent with the numbering of project construction drawing.Described variableness information for by steel structure member whether in the manufacture craft type of the cutting of manufacturing plant, member or group technology type, member, member whether in haulage stage, the transportation base information that be transported to, whether at the construction field (site), concrete heap field information and the residing concrete installation procedure at Specific construction scene combine.
Preferably, half active RFID tag 101 can be made up of 16 bit numbers, and this 16 bit number comprises changeless numbering and can change the variable numbering of following variation, reactive means state real-time follow-up intuitively along with steel structure member status.Such as, steel structure member is numbered GZ16212242051200, and GZ16 is that project member numbering, 2 is for whether member is in manufacturing plant or from factory; 12 for member cutting or group technology, 24 for structure manufacture technique, 2 for member whether be in the haulage stage, 05 for member be transported to which website, 1 for member whether at the construction field (site), 2 for member at the construction field (site) which stockyard, 00 be member installation procedure flow process of living in.Project member numbering is aimed at attribute number, is clearly identified on RFID label, stamps this numbering steel seal to check on the member completing simultaneously, and this numbering is consistent with the numbering of project construction drawing.Particularly, once first to fourth of steel structure member numbering has just been fixed up after determining, numbering, from the 5th to sixteen bit, is upgraded variation along with member status.When starting material sheet material is also when Wei Jin processing factory, the 5th bit number should be 0, and member should be 1 while making in factory, during from factory, should be 2.The six or seven bit number is member cutting or group technology, and group technology is divided into cutting, is combined as web, is combined as flange plate, is combined as stiffener, is combined as otic placode etc., and these are carried out to sorting code number.The eight or nine bit number is structure manufacture technique, and technique is numbered to have out respectively cut, correction, welding, boring, weldering peg, ball blast, spray paint etc., and carries out line production tracking.The tenth bit number be member whether in the haulage stage, also entrucking time numbering not should be 0, member should be 1 in the time of the haulage stage, member should be 2 after unloading.The ten one the 12 bit number is component conveying site number, has respectively member entrucking, transport post house and the member flow process such as unload to encode.The 13 bit number be member whether at the construction field (site) and be numbered, also do not number and should be 0 to working-yard, at the construction field (site) 1.The 14 bit number is which stockyard member is numbered at the construction field (site), and it is specifically located.The 15 sixteen bit is numbered member installation process flow of living in coding, has respectively the installation procedures such as lifting, in place, correction, welding and flaw detection.All steel constructions by above-mentioned rule are encoded, be combined into Quick Response Code and carry out data transmission.
In step S2, adopt half active RFID identification terminal 102 to identify half active RFID tag 101.When the residing position of described steel structure member or state change, half active RFID identification terminal 102 can write new data by double active RFID tag 101.
Comprise steel structure member packaging technology 200, steel structure member welding technology 300, steel structure member transport 400, steel structure member stockyard 500, steel structure member lifting 600, steel structure member correction 700 etc. in the construction stage described in S2.
For The Design of Steel Structure Buildings, structure manufacture have a series of approval process to installing, as quality self-assessment, over contract examination & approval, project supervision supervision and check, owner's written instructions etc.If steel structure member is not by examination & verification in a upper operation stage, half active RFID identification terminal 102 cannot upgrade the variableness information of steel structure member.Now, Internet of Things tracker is set a concrete management account, cura specialis personnel just have account to enter information bank to carry out the up-to-standard examination & verification of steel structure member, the flow processs such as management examination & approval, common components state upgrades does not need to enter this system, operator holds half active RFID terminal just can real-time update, therefore, each tracing process of construction steel structure overall process Internet of Things has a remarks record entry, whether be used for recording the steel structure member stage of living in by corresponding examination and approval procedures, if not by corresponding examination and approval procedures, this " warning " information can be reacted in the whole system of Internet of Things or half active RFID terminal, or can inquire by half active RFID terminal or computer.And, arrange by Internet of things system, if a upper flow process or operation be not by a certain particular audit or written instructions, next operation just cannot be carried out, even if carried out next-step operation, and the also residing state of new structural member more of operator, and half active RFID terminal can be information response on whole system, allow managerial personnel's real-time follow-up steel structure member status and process in time feedback information, thus realize high efficiency visual, information system management steel structure member.
Simultaneously, need to process if having to change, handled changed content is mainly changed the change of the technique such as making, installation causing by steel construction drawing, after the information-change in management platform, the techniques such as structure steel fabrication, installation or flow process need to replace simultaneously, increase or the change such as minimizing.Specific people also can pass through Internet of things system, by to a certain member remarks record entry, the simple technique that changes of narration, scene has the managerial personnel of half active RFID terminal or operator and just can know and know which member needs to change, or again in place, or adjust and change etc., the variableness information of half active RFID tag also changes along with the variation of modification information in Internet of Things tracker management platform simultaneously.The change of information is accurate and efficient, and can do the synchronous of reason information-change.Managerial personnel or operator also can bring because understanding error error, and Construction of Steel Structure project management can realize operated from a distance or monitoring.
A kind of steel construction tracking control of full process system, comprising: be fixed with the steel structure member of half active RFID tag 101, some half active RFID identification terminal 102 and terminal devices 103 that is distributed in each operation that steel structure member will flow through.Half active RFID identification terminal 102 all half active RFID tag 101 is identified, upgraded to described half active RFID tag 101 in each operation stage of described steel structure member in canned data, and position up-to-date steel structure member and status information are sent to described terminal device; Terminal device 103 is connected with half active RFID identification terminal 102, for receiving and store the residing position of steel structure member and status information.
Terminal device 103 is connected with Internet of Things tracker management platform by Internet of Things, and the residing position of steel structure member receiving from half active RFID identification terminal 102 and status information are sent to described Internet of Things tracker management platform.In the time that half active RFID identification terminal 102 is identified described half active RFID tag 101, if steel structure member is not by examination & verification in the upper operation stage, half active RFID identification terminal 102 cannot upgrade the variableness information of steel structure member.
In half active RFID tag, include build-in attribute information and the variableness information of steel structure member, described variableness information was upgraded according to the residing operation of the steel structure member stage, comprise member whether in manufacturing plant or from the travel position of the manufacture craft of the cutting of the state of factory, member or group technology, member, member, transportation base state, whether at the construction field (site), concrete heap field information and the residing installation procedure flow process at Specific construction scene.Preferably, the build-in attribute information of half active RFID tag 101 is fixed number, and variableness information is variable numbering composition.
Half active RFID identification terminal 102 is arranged on respectively each construction stage: steel structure member packaging technology 200, steel structure member welding technology 300, steel structure member transport 400, steel structure member stockyard 500, steel structure member lifting 600 and steel structure member proofread and correct 700.Each construction stage is identified each member by half active RFID identification terminal, can avoid the steel structure member in closely close construction, away from construction explosive area, and the member that also convenient construction personnel searching need to be used simultaneously.
The utility model adopts half active RFID tag 101 and half active RFID identification terminal 102 to follow the tracks of steel structure member and has the following advantages: read convenient and swift: the reading without light source of data, even can see through external packing and carry out, effectively decipherment distance can reach more than 30 meters; Recognition speed is fast: label one enters magnetic field, and identification terminal just can read information wherein immediately, and can process multiple labels simultaneously, realizes batch identification; Data capacity is large: what RFID identification terminal can be according to user need to extend to tens of K; Long service life, applied range: its wireless communication mode, make it still can normally work in dust, the contour contaminated environment of greasy dirt and radioactive environment, staff needn't be in wherein; Label data capable of dynamic change: utilize the programmable device can data writing, thereby give the function of RFID label interactive portable data file, and the write time than Print Label still less; Better security: not only can embed or be attached on the product of difformity, type, and can cryptoguard be set for the read-write of terminal data, thereby there is higher security; Dynamically real-time Communication for Power: half active RFID tag communicates with frequency and the plug-in reader of 50~100 times per second, as long as the accompanying object of half active RFID tag appears in effective identification range of identification terminal, just can its position be followed the trail of dynamically and be monitored.
Described steel construction tracking control of full process method and tracker, can collect each member status, also can gather all steel structure member status, is transported in the BIM of company model by Internet of Things, carries out the management of BIM model visualization.Also realize simultaneously to its accurately search, locate, monitoring, real-time follow-up and warning function, and for the production schedule and various decision-making provide reliable Data support, improve scientific and technical information management level and operating efficiency, there is objective economic benefit.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all any amendments of doing within spirit of the present utility model and principle, be equal to and replace and improvement etc., within all should being included in protection domain of the present utility model.

Claims (2)

1. a steel construction tracking control of full process system, is characterized in that, comprising: be fixed with the steel structure member of half active RFID tag, some half active RFID identification terminal and terminal devices that is distributed in each operation that steel structure member will flow through;
The variableness information that described half active RFID identification terminal is stored in all described half active RFID tag is identified, upgraded to described half active RFID tag in each operation stage of described steel structure member, and position up-to-date steel structure member and status information are sent to described terminal device;
Described terminal device is connected with described half active RFID identification terminal, for receiving and store the residing position of steel structure member and status information;
Described terminal device is also connected with Internet of Things tracker management platform by Internet of Things, and residing steel structure member position and status information are sent in the BIM model of described Internet of Things tracker management platform, carries out the management of BIM model visualization.
2. steel construction tracking control of full process system according to claim 1, it is characterized in that, described half active RFID identification terminal is arranged on respectively: stockyard, steel structure member lifting place and the steel structure member of steel structure member packaging technology place, steel structure member welding technology place, steel structure member means of transport, steel structure member are proofreaied and correct place.
CN201420011936.XU 2014-01-09 2014-01-09 A kind of steel construction tracking control of full process system Expired - Lifetime CN204010000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420011936.XU CN204010000U (en) 2014-01-09 2014-01-09 A kind of steel construction tracking control of full process system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420011936.XU CN204010000U (en) 2014-01-09 2014-01-09 A kind of steel construction tracking control of full process system

Publications (1)

Publication Number Publication Date
CN204010000U true CN204010000U (en) 2014-12-10

Family

ID=52049971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420011936.XU Expired - Lifetime CN204010000U (en) 2014-01-09 2014-01-09 A kind of steel construction tracking control of full process system

Country Status (1)

Country Link
CN (1) CN204010000U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563297A (en) * 2014-12-27 2015-04-29 华北水利水电大学 BIM (Building Information Modeling)-based steel structure universal positioning connection device
CN104563301A (en) * 2014-12-27 2015-04-29 华北水利水电大学 BIM (Building Information Modeling)-based cylindrical steel structure flat oblique crossing positioning connection device
CN106296014A (en) * 2016-08-15 2017-01-04 上海宝冶集团有限公司 Steel construction based on BIM and Quick Response Code produces delivery system
CN106845919A (en) * 2016-12-16 2017-06-13 上海建工集团股份有限公司 Construction information collection processing method
CN106845576A (en) * 2017-01-13 2017-06-13 中国葛洲坝集团三峡建设工程有限公司 Construction installation unit identifying system and method
CN112766856A (en) * 2021-01-25 2021-05-07 杭州友电科技有限公司 Supply chain digital management method and device, computer equipment and storage medium

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563297A (en) * 2014-12-27 2015-04-29 华北水利水电大学 BIM (Building Information Modeling)-based steel structure universal positioning connection device
CN104563301A (en) * 2014-12-27 2015-04-29 华北水利水电大学 BIM (Building Information Modeling)-based cylindrical steel structure flat oblique crossing positioning connection device
CN104563301B (en) * 2014-12-27 2016-08-24 华北水利水电大学 The flat oblique locating connector of cylindrical steel structure based on BIM
CN104563297B (en) * 2014-12-27 2017-01-04 华北水利水电大学 Steel structure universal locating connector based on BIM
CN106296014A (en) * 2016-08-15 2017-01-04 上海宝冶集团有限公司 Steel construction based on BIM and Quick Response Code produces delivery system
CN106845919A (en) * 2016-12-16 2017-06-13 上海建工集团股份有限公司 Construction information collection processing method
CN106845576A (en) * 2017-01-13 2017-06-13 中国葛洲坝集团三峡建设工程有限公司 Construction installation unit identifying system and method
CN106845576B (en) * 2017-01-13 2023-10-31 中国葛洲坝集团三峡建设工程有限公司 Construct installation unit identification system and method
CN112766856A (en) * 2021-01-25 2021-05-07 杭州友电科技有限公司 Supply chain digital management method and device, computer equipment and storage medium
CN112766856B (en) * 2021-01-25 2024-01-19 杭州友电科技有限公司 Supply chain digital management method, device, computer equipment and storage medium

Similar Documents

Publication Publication Date Title
CN103793783A (en) Steel-structure overall-process tracking method and system
CN204010000U (en) A kind of steel construction tracking control of full process system
CN111539668B (en) Warehousing system based on radio frequency technology and control method
CN102646221B (en) To the real-time follow-up of discrete manufacturing process logistics and review the system and method for quality
CN100458823C (en) Automatic crusing robot system based on radio-frequency identification technology
CN101866172B (en) RFID technology based concrete quality monitoring system and working method thereof
Ergen et al. Life-cycle data management of engineered-to-order components using radio frequency identification
CN108776884A (en) A kind of intelligent storage operational method
CN103530827A (en) Assembly type building component intelligent management system based on BIM (building information modeling)
CN110733825A (en) automatic storage system and operation method thereof
CN103984346A (en) System and method for intelligent warehousing checking
CN103971220A (en) Intelligent hazardous chemical substance warehouse management system
CN103325030A (en) Robot-based method for managing goods in internet of things
CN201689313U (en) Concrete quality monitoring system based on RFID technology
CN103530664A (en) Production management system of tunnel segment
CN203503006U (en) BIM-based intelligent management system of assembly type building components
Sun et al. Research on RFID Applications in Construction Industry.
CN105160370A (en) Management system of cable carrying RFID chip
CN115392853A (en) Operation system of transparent intelligent factory
CN107341531A (en) A kind of electric power equipment management and alignment system
CN104504539A (en) Full life cycle management system of internet of things in discrete manufacturing industry
CN104766190A (en) Mining underground logistics management system and method based on RFID technology
CN103325026A (en) Operation spare parts library management method based on RFID
CN205080572U (en) Automatic change logistics management record warehouse
Park et al. Development of Smart Mining Technology Level Diagnostics and Assessment Model for Mining Sites

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Overall process tracking system for steel structures

Effective date of registration: 20180129

Granted publication date: 20141210

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

PE01 Entry into force of the registration of the contract for pledge of patent right
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20221207

Granted publication date: 20141210

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

PC01 Cancellation of the registration of the contract for pledge of patent right
TR01 Transfer of patent right

Effective date of registration: 20221226

Address after: Room 1908, Chengtou Xin Times Building, No. 2009, Pingshan Avenue, Liulian Community, Pingshan Street, Pingshan District, Shenzhen 518000

Patentee after: China Construction Steel Engineering Co.,Ltd.

Address before: 3801, 38 / F, China Construction Science and engineering building, No. 3331, Weilan Coast Community Central Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: China Construction Science And Industry Co.,Ltd.

TR01 Transfer of patent right
CX01 Expiry of patent term

Granted publication date: 20141210

CX01 Expiry of patent term