CN203846407U - Fast-splicing type large-span bridge detecting and reinforcing operation platform - Google Patents
Fast-splicing type large-span bridge detecting and reinforcing operation platform Download PDFInfo
- Publication number
- CN203846407U CN203846407U CN201420261325.0U CN201420261325U CN203846407U CN 203846407 U CN203846407 U CN 203846407U CN 201420261325 U CN201420261325 U CN 201420261325U CN 203846407 U CN203846407 U CN 203846407U
- Authority
- CN
- China
- Prior art keywords
- fast
- span
- girder truss
- splicing
- truss beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
A fast-splicing type large-span bridge detecting and reinforcing operation platform comprises a fast-splicing truss beam which is spliced by a plurality unit modules. The lifting ends at two ends of the fast-splicing truss beam adopt cable structure anchoring systems. Two anchoring ends are disposed on the middle section of the fast-splicing truss beam. Two pairs of inhaul cables are transversely symmetrically disposed on the fast-splicing truss beam. Each cable structure anchoring system comprises a fixing support fixed on the truss beam and a tensioning mechanism mounted on the fixing support. A sleeve type spiral cable tensioning device is disposed at each tensioning mechanism. A pressure ring is mounted at each anchoring end. One ends of inhaul cables respectively penetrate the spiral cable tightening device to be connected with the tensioning mechanism, and the other ends thereof respectively penetrate pressing rings to be connected with the anchoring ends. The fast-splicing type large-span bridge detecting and reinforcing operation platform has the advantages that the inhaul cables are added to an existing hanging basket structure, mid-span deflection and mid-span moment can be reduced effectively by increasing the pre-tension of the inhaul cables, structural bearing cavity is increased, and large span is achieved.
Description
Technical field
The utility model belongs to building field, is specially a kind of fast spelling formula Longspan Bridge and detects reinforcing job platform.
Background technology
The blue job platform of conventional extension has been widely used in work China Democratic National Construction Association in external wall construction, but its span is less, generally between 8~24m, surpassed 24m just higher to hanging blue trussmember dimensional requirement, especially to being greater than 30m span truss extension indigo plant, need rigidity extremely to increase, mid-span deflection also can have increase, has affected the stability of structure, the increase that its steel using amount also can be a large amount of.
Utility model content
The purpose of this utility model provides a kind of fast spelling formula Longspan Bridge of realizing large span operation to detect and reinforces job platform, to solve the problem proposing in above-mentioned background technology.
To achieve these goals, the technical problem that the utility model solves realizes by the following technical solutions:
Fast spelling formula Longspan Bridge detects reinforces job platform, comprises fast spelling formula girder truss; Described fast spelling formula girder truss is spliced by a plurality of unit modules, and the lifting end of spelling soon formula girder truss two ends adopts Cable Structure anchoring system, and the stage casing of spelling soon formula girder truss is provided with two anchored end, spells soon formula girder truss and is furnished with two pairs of drag-lines along lateral symmetry; Described Cable Structure anchoring system comprises the fixed support that is fixed on girder truss and is arranged on the stretch-draw mechanism on fixed support, and stretch-draw mechanism place is provided with sleeve type helical Fastening device for cable; Described anchored end is equipped with pressure rings; One end of described drag-line is connected with stretch-draw mechanism through spiral Fastening device for cable respectively, and the other end of drag-line is connected with anchored end through pressure rings respectively.
Further, described unit module comprises upper chord, lower chord, web member and cross bar.
Further, the length of described unit module is 4mm, and each unit module end is all reserved with adjustable junction plate, and each unit module is spliced into one by high-strength bolt.
Further, be also equipped with lifting appliance, lifting appliance comprises elevator, auxiliary rope system and safety rope system and suspension.
Beneficial effect
The utility model is hung and in blue structure, has been increased stayed structure by increasing drag-line pretension at existing truss, and can effectively reduce to collapse middle amount of deflection and mid span moment have improved the supporting capacity of structure, have realized large span; Make the utility model reduce integrally-built steel using amount under equal span, and structure stress is rationally clear and definite, easy to operate; Be specially adapted to large-span truss formula job platform structure.
Accompanying drawing explanation
Fig. 1 is the utility model structural representation;
Fig. 2 is unit module structural representation described in the utility model;
Fig. 3 is the A part partial enlarged drawing of Fig. 1;
Fig. 4 is Figure 1B part partial enlarged drawing;
Fig. 5 is the utility model three-dimensional effect diagram;
Fig. 6 is the utility model lifting schematic diagram.
The specific embodiment
In order to make of the present utility modelly to realize technological means, creation characteristic, reach object and effect is easy to understand, below in conjunction with concrete diagram, further set forth the utility model.
As Figure 1-5, spell soon formula Longspan Bridge and detect reinforcing job platform, comprise fast spelling formula girder truss 1; Described fast spelling formula girder truss 1 agent structure adopts the unit module 1-1 of mono-of 4m, each unit module 1-1 end is reserved adjustable junction plate 1-2 all, adopt high-strength bolt 1-3 to be spliced to each unit module 1-1, the multiple span form of one-tenth capable of being combined, the lifting end at fast spelling formula girder truss 1 two ends is equipped with Cable Structure anchoring system 2, Cable Structure anchoring system 2 is installed after fast spelling formula girder truss 1 has spliced, the stage casing of fast spelling formula girder truss 1 is provided with two anchored end 3, spells soon formula girder truss and is furnished with two pairs of drag-lines 4 along lateral symmetry; Described Cable Structure anchoring system 2 comprises fixed support 2-1 and be fixed on the 2-2 of stretch-draw mechanism on fixed support, and the 2-2 of stretch-draw mechanism place is provided with sleeve type helical Fastening device for cable; Described anchored end 3 is equipped with pressure rings 3-1; One end of described drag-line 4 is connected with the stretch-draw mechanism of Cable Structure anchoring system 2 through spiral Fastening device for cable respectively, and the other end of drag-line 4 is connected with anchored end 3 through pressure rings 3-1 respectively, by pressure rings, can monitor in real time anchor cable value of thrust; According to different spans, binding isotherm parameter is adjusted the size of anchor cable pretension.
Wherein, unit module 1-1 comprises upper chord 1-11, lower chord 1-12, web member 1-13 and cross bar 1-14.
The utility model utilizes the loading characteristic of trussed construction and Cable Structure, on the basis of conventional truss-like job platform, increases Cable Structure stress system, makes to hang blue form a kind of suspension cable and synchronize force structure with girder truss; Can under identical cost condition, increase structural span like this, reduce structural deflection, or reduce steel using amount under identical span condition, reduce the object that cost reaches low-carbon (LC).This patent can be realized 36m large span job platform structure.
As shown in Figure 6, the utility model is also equipped with lifting appliance, and lifting appliance comprises elevator 5, auxiliary rope system and safety rope system 7 and suspension 8, in hoisting process, first laying groove rail mark, assembles suspension rod, fill up counterweight 6, then aluminium alloy ladder support is installed, steel guard rail 9 is installed, install people's steel cat ladder 10, aluminium alloy ladder 11 is installed, suspension 8 and safety rope system are installed, secondly, be joggle truss beam 1 and people from station guidance tape, anchor head is installed, drag-line 4 is installed; Last pretension rope. according to pressure rings 3-1, detect data adjustment, suspension centre is connected with suspension 8, examination is hung platform, up-down adjustment 3~5 times.
More than show and described basic principle of the present utility model and principal character and advantage of the present utility model.The technician of the industry should understand; the utility model is not restricted to the described embodiments; that in above-described embodiment and manual, describes just illustrates principle of the present utility model; do not departing under the prerequisite of the utility model spirit and scope; the utility model also has various changes and modifications, and these changes and improvements all fall within the scope of claimed the utility model.Claimed scope of the present utility model is defined by appending claims and equivalent thereof.
Claims (3)
1. fast spelling formula Longspan Bridge detects and reinforces job platform, comprises fast spelling formula girder truss; It is characterized in that, described fast spelling formula girder truss is spliced by a plurality of unit modules, the lifting end at fast spelling formula girder truss two ends adopts Cable Structure anchoring system, and the stage casing of spelling soon formula girder truss is provided with two anchored end, spells soon formula girder truss and is furnished with two pairs of drag-lines along lateral symmetry; Described Cable Structure anchoring system comprises the fixed support that is fixed on girder truss and is arranged on the stretch-draw mechanism on fixed support, and stretch-draw mechanism place is provided with sleeve type helical Fastening device for cable; Described anchored end is equipped with pressure rings; One end of described drag-line is connected with stretch-draw mechanism through spiral Fastening device for cable respectively, and the other end of drag-line is connected with anchored end through pressure rings respectively.
2. fast spelling formula Longspan Bridge according to claim 1 detects and reinforces job platform, it is characterized in that, described unit module comprises upper chord, lower chord, web member and cross bar.
3. fast spelling formula Longspan Bridge according to claim 1 detects and reinforces job platform, it is characterized in that, the length of described unit module is 4mm, and each unit module end is all reserved with adjustable junction plate, and each unit module is spliced into one by high-strength bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420261325.0U CN203846407U (en) | 2014-05-22 | 2014-05-22 | Fast-splicing type large-span bridge detecting and reinforcing operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420261325.0U CN203846407U (en) | 2014-05-22 | 2014-05-22 | Fast-splicing type large-span bridge detecting and reinforcing operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203846407U true CN203846407U (en) | 2014-09-24 |
Family
ID=51559444
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420261325.0U Expired - Fee Related CN203846407U (en) | 2014-05-22 | 2014-05-22 | Fast-splicing type large-span bridge detecting and reinforcing operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203846407U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113373787A (en) * | 2021-06-18 | 2021-09-10 | 中铁大桥勘测设计院集团有限公司 | Ultra-wide truss bridge structure system and design method thereof |
-
2014
- 2014-05-22 CN CN201420261325.0U patent/CN203846407U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113373787A (en) * | 2021-06-18 | 2021-09-10 | 中铁大桥勘测设计院集团有限公司 | Ultra-wide truss bridge structure system and design method thereof |
CN113373787B (en) * | 2021-06-18 | 2022-05-06 | 中铁大桥勘测设计院集团有限公司 | Ultra-wide truss bridge structure system and design method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103291076B (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
CN101537976B (en) | Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof | |
CN107989380B (en) | Steel truss gallery hydraulic synchronizing lifting construction technique | |
CN202090286U (en) | Traction system suitable for self-anchored type double cable plane suspension bridge | |
CN206521197U (en) | A kind of adjustable balance hoisting beam | |
CN104088467B (en) | A kind of large Steel Cantilever truss structure high-altitude construction Deformation monitoring method | |
CN202881856U (en) | Concrete pouring support prepressing device | |
CN207361649U (en) | Large-scale vestibule steel construction lifting device | |
CN201376848Y (en) | Large-scale double-tower automatic-elevation hoisting equipment | |
CN201506952U (en) | Temporary cable matched hanging basket building concrete cable stayed bridge without supporting frame | |
CN104631810A (en) | High-altitude movable hanging basket system and construction method thereof | |
CN102251483A (en) | Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane | |
CN104060835A (en) | Lifting-sliding construction method for single plane truss | |
CN203173749U (en) | Assembled integral type vertical self-jacking device of hydraulic double-type crane tower | |
CN203846407U (en) | Fast-splicing type large-span bridge detecting and reinforcing operation platform | |
CN103288002A (en) | Simple combination portal upper-air heavy-article hoisting device | |
CN203284126U (en) | Simple composite gantry high-altitude weight hoisting device | |
CN201284551Y (en) | Suspension type simple platform for work high above ground | |
CN102926330B (en) | Installation method of hanging basket suitable for bridge construction | |
CN105040592B (en) | Horizontal pull rope bridge and erection method thereof | |
CN113235435B (en) | Cable-first beam-second self-anchored suspension bridge system conversion construction method | |
CN103866691B (en) | A kind of Large scale cable crane track cable group anchor device | |
CN107237404A (en) | Overhanging steel structure of strip steel pull rod and mounting method thereof | |
CN203782567U (en) | Bearing cable anchor group device of large cable crane | |
CN210888045U (en) | Assembled lifting die |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140924 Termination date: 20150522 |
|
EXPY | Termination of patent right or utility model |