CN203813311U - Ground wire plugging tool - Google Patents

Ground wire plugging tool Download PDF

Info

Publication number
CN203813311U
CN203813311U CN201420251928.2U CN201420251928U CN203813311U CN 203813311 U CN203813311 U CN 203813311U CN 201420251928 U CN201420251928 U CN 201420251928U CN 203813311 U CN203813311 U CN 203813311U
Authority
CN
China
Prior art keywords
ground wire
sleeve pipe
hammer
earth connection
sledge hammer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420251928.2U
Other languages
Chinese (zh)
Inventor
刘赞良
吴志祥
吴晓光
任锋
刘立君
陈振雨
路铁宁
张来锁
寇马军
孙秋刚
冯正阳
刘哨飞
张卿
张建飞
李涛
宋海涛
刘晨
张汝松
孙铁超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical Hengshui Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority to CN201420251928.2U priority Critical patent/CN203813311U/en
Application granted granted Critical
Publication of CN203813311U publication Critical patent/CN203813311U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Manufacturing Of Electrical Connectors (AREA)

Abstract

The utility model belongs to the ground wire plugging tool technical field, and discloses a ground wire plugging tool comprising a sledge hammer, a pedestal, and a carrying sleeve pipe. The upper part of the carrying sleeve pipe is provided with an inserting rod, and the top end of the inserting rod is provided with a pressure-bearing semicircular pipe having an opening facing upwards. The inserting rod and the carrying sleeve pipe are connected together by a height adjustment mechanism. The side surface of the carrying sleeve pipe is provided with a sledge hammer handle fixing clamp, and the handle of the sledge hammer is fixedly disposed in the sledge hammer handle fixing clamp. The end part of the handle of the sledge hammer is provided with a fixing bolt, which is provided with a ground wire lifting suspension ring. During the construction, the ground wire can be hammered in the ground by the sledge hammer, and after the construction, the ground wire lifting suspension ring is hung on the cross bar of the ground wire, and then the handle of the sledge hammer is disposed on the pressure-bearing semicircular pipe in a pressed manner, and thereafter by using the lever principle, the ground wire can be pulled up, and therefore the construction efficiency can be improved, the labor intensity can be reduced, the damaging and the bending of the ground wire cannot be caused, the service lifetime of the ground wire can be prolonged, and the carrying is more convenient.

Description

Earth connection plug-pull tool
Technical field
The utility model belongs to electricity earthing cable plug-pull tool technical field, relates to specifically earth connection plug-pull tool.
Background technology
In the time of line maintenance, line upkeep, need to be by power circuit by ground connection, to avoid occurring Danger Electric shock risk.The earth connection end using is at present that " fourth " font is inserted ground Metallic rod, when use, needs to insert ground Metallic rod and inserts in soil, after having constructed, will insert ground Metallic rod and extract.Because soil property is different different with degree of drought, cause in the harder soil of earth connection plug difficulty, especially soil property.In the time pulling up earth connection, need to vibrate earth connection Metallic rod with hammer, or manually rock or front and back bending Metallic rod, manually earth connection Metallic rod is extracted, not only increase labour intensity, reduced efficiency, and in the process of vibration or bending earth connection Metallic rod, cause earth connection Metallic rod bending or fracture, shorten the useful life of earth connection, the Metallic rod after bending is upper more difficult while once inserting soil.
Utility model content
The technical problem that the utility model solves be just to provide a kind of property easy to use, safe good, extend earth connection useful life, earth connection is not easy bending, operating efficiency is high, labour intensity is little earth connection plug-pull tool.
For solving the problems of the technologies described above, the technical scheme the utility model proposes is: comprise sledgehammer, base and accept sleeve pipe, be provided with insertion rod described above accepting sleeve pipe, be provided with the pressure-bearing semi-circular tube of opening upwards on the top of this insertion rod, described insertion rod with described in accept sleeve pipe and be connected by height adjustment mechanism, be provided with hammer fixed card in the described sleeve pipe side of accepting, the hammer of described sledgehammer is being fixed on described hammer in fixed card, hammer at described sledgehammer is provided with set bolt end, is provided with ground wire and rises and pull out suspension ring on this set bolt.
Its additional technical feature is:
Described in described height adjustment mechanism is included in, accept outer adjustment hole, the interior adjustment hole mating with this outer adjustment hole arranging in described insertion rod and inserting bolt composition vertically on sleeve pipe, described inserting bolt is inserted in described outer adjustment hole and interior adjustment hole.
The earth connection plug-pull tool that the utility model provides, compared with the existing technology have the following advantages: one, owing to comprising sledgehammer, base and accept sleeve pipe, be provided with insertion rod described above accepting sleeve pipe, be provided with the pressure-bearing semi-circular tube of opening upwards on the top of this insertion rod, described insertion rod with described in accept sleeve pipe and be connected by height adjustment mechanism, be provided with hammer fixed card in the described sleeve pipe side of accepting, the hammer of described sledgehammer is being fixed on described hammer in fixed card, hammer at described sledgehammer is provided with set bolt end, on this set bolt, being provided with ground wire rises and pulls out suspension ring, in the time of construction, take out sledgehammer, earth connection is hammered in ground with sledgehammer, after having constructed, base is placed in to the side of earth connection, ground wire is risen and pulled out on the cross bar that suspension ring hang over earth connection, and hammer handle is pressed on pressure-bearing semi-circular tube, regulate as required height adjustment mechanism, make hammer that end is lower slightly, then the first side of hammer firmly, earth connection is partly pulled up, then by regulating height adjustment mechanism, pressure-bearing semi-circular tube is raise, continue the firmly first side of hammer, until earth connection is pulled up, sledgehammer is packed up, in the time extracting earth connection, beat earth connection without sledgehammer, also need not bend and rock earth connection, not only improve efficiency of construction, reduce labour intensity, can not cause earth connection damage and bending, extend the useful life of earth connection, make earth connection insertion next time ground wire easier, and all instruments place together, avoid instrument disappearance, carry convenient, they are two years old, because described height adjustment mechanism is accepted on sleeve pipe outer adjustment hole, the interior adjustment hole mating with this outer adjustment hole arranging in described insertion rod and inserting bolt composition vertically described in being included in, described inserting bolt is inserted in described outer adjustment hole and interior adjustment hole, regulates convenient.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model earth connection plug-pull tool;
Fig. 2 has been the use state diagram of pulling out earth connection.
Embodiment
Earth connection plug-pull tool the utility model being proposed below in conjunction with the drawings and specific embodiments is described further.
As depicted in figs. 1 and 2, the structural representation of the earth connection plug-pull tool providing for the utility model, this earth connection plug-pull tool comprises sledgehammer 2, base 1 and accept sleeve pipe 3, accept sleeve pipe 3 above be provided with insertion rod 4, be provided with the pressure-bearing semi-circular tube 5 of opening upwards on the top of this insertion rod 4, insertion rod 4 with accept sleeve pipe 3 and be connected by height adjustment mechanism 6, be provided with hammer in the side of accepting sleeve pipe 3 fixed card 7, the hammer of sledgehammer 1 is fixed on hammer in fixed card 7 21, hammer at sledgehammer 2 is provided with set bolt 8 21 ends, on this set bolt 8, being provided with ground wire rises and pulls out suspension ring 9.In the time of construction, take out sledgehammer 2, earth connection 10 use sledgehammers are hammered in ground, after having constructed, base 1 is placed in to the side of earth connection 10, ground wire is risen and pulled out on the cross bar 11 that suspension ring 9 hang over earth connection 10, and hammer is pressed on pressure-bearing semi-circular tube 5 21, regulate as required height adjustment mechanism 6, make hammer that end is lower slightly, then the first side of hammer firmly, earth connection 10 is partly pulled up, then by regulating height adjustment mechanism 6, pressure-bearing semi-circular tube 5 is raise, continue the firmly first side of hammer, until earth connection is pulled up, sledgehammer is packed up, in the time extracting earth connection, beat earth connection without sledgehammer, also need not bend and rock earth connection, not only improve efficiency of construction, reduce labour intensity, can not cause earth connection damage and bending, extend the useful life of earth connection, make earth connection insertion next time ground wire easier, and all instruments place together, avoid instrument disappearance, carry convenient.
Interior adjustment hole 62 and the inserting bolt 63 of mating with this outer adjustment hole 61 that height adjustment mechanism 6 is included in and accepts on sleeve pipe 3 outer adjustment hole 61 vertically, in insertion rod 4, arranges form, inserting bolt 63 is inserted in outer adjustment hole 61 and interior adjustment hole 62, regulates convenient.
The method that uses earth connection plug-pull tool plug earth connection, the method comprises the following steps:
The first step: take out sledgehammer 2
By the hammer of sledgehammer 2 21 from hammer interior fixed card 7 taking-up;
Second step: insert earth connection
Earth connection 10 lower ends are placed in to relevant position, the hand steered earth connection vertical rod of a people, another people impacts earth connection cross bar 11 with sledgehammer, and earth connection is inserted in ground;
The 3rd step: extract earth connection
After having constructed, base 1 is placed in to the side of earth connection 10, ground wire is risen and pulled out on the cross bar 11 that suspension ring 9 hang over earth connection, and hammer is pressed on pressure-bearing semi-circular tube 5 21, regulate as required height adjustment mechanism 6, make hammer that end is lower slightly, the first side of hammer of then exerting oneself, earth connection 10 is partly pulled up, then by regulating height adjustment mechanism 6, pressure-bearing semi-circular tube 5 is raise, continue the firmly first side of hammer, until earth connection is pulled up;
The 4th step: sledgehammer 2 is packed up, and will be hammered into shape and insert hammer in fixed card 7 21.
Protection range of the present utility model is not only confined to above-described embodiment, as long as structure is identical with the utility model earth connection plug-pull tool structure, just drops on the scope of the utility model protection.

Claims (2)

1. earth connection plug-pull tool, it is characterized in that: comprise sledgehammer, base and accept sleeve pipe, be provided with insertion rod described above accepting sleeve pipe, be provided with the pressure-bearing semi-circular tube of opening upwards on the top of this insertion rod, described insertion rod with described in accept sleeve pipe and be connected by height adjustment mechanism, be provided with hammer fixed card in the described sleeve pipe side of accepting, the hammer of described sledgehammer is being fixed on described hammer in fixed card, hammer at described sledgehammer is provided with set bolt end, is provided with ground wire and rises and pull out suspension ring on this set bolt.
2. earth connection plug-pull tool according to claim 1, it is characterized in that: described in described height adjustment mechanism is included in, accept outer adjustment hole, the interior adjustment hole mating with this outer adjustment hole arranging in described insertion rod and inserting bolt composition vertically on sleeve pipe, described inserting bolt is inserted in described outer adjustment hole and interior adjustment hole.
CN201420251928.2U 2014-05-16 2014-05-16 Ground wire plugging tool Expired - Lifetime CN203813311U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420251928.2U CN203813311U (en) 2014-05-16 2014-05-16 Ground wire plugging tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420251928.2U CN203813311U (en) 2014-05-16 2014-05-16 Ground wire plugging tool

Publications (1)

Publication Number Publication Date
CN203813311U true CN203813311U (en) 2014-09-03

Family

ID=51452020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420251928.2U Expired - Lifetime CN203813311U (en) 2014-05-16 2014-05-16 Ground wire plugging tool

Country Status (1)

Country Link
CN (1) CN203813311U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103956675A (en) * 2014-05-16 2014-07-30 国网河北省电力公司衡水供电分公司 Tool and method for inserting ground wire into soil and pulling ground wire out of soil

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103956675A (en) * 2014-05-16 2014-07-30 国网河北省电力公司衡水供电分公司 Tool and method for inserting ground wire into soil and pulling ground wire out of soil

Similar Documents

Publication Publication Date Title
CN103956675B (en) Tool and method for inserting ground wire into soil and pulling ground wire out of soil
CN203300821U (en) Grounding hammer drill
CN103259213B (en) A kind of wiring pile extractor
CN203813311U (en) Ground wire plugging tool
CN204289737U (en) Cable inspection earthing pricker
CN103618235A (en) Quick puller for temporary ground bar
CN201679005U (en) Steel puller
CN201730098U (en) Buried stand pipe artificial removing device
CN203289001U (en) Wiring pile extractor
CN203307805U (en) Spiral ground breaking earth anchor with earth anchor rotating operation rod
CN204326075U (en) A kind of drill steel extracting apparatus
CN203491599U (en) Insulator dismounting pin-withdrawing device
CN203722129U (en) Bird nest removing tool of power transmission facility
CN102832564B (en) A kind of extracting apparatus of rod power ground
CN202745462U (en) Clamping two-semicircle combined hoops for preventing rod from falling
CN203288999U (en) Special device for operation of grounding pin of power grounding wire
CN203430416U (en) Rope ladder ground fixer with oblique needle
CN207947577U (en) All-metal submersible pump cable protector
CN107394429A (en) Earthing pole
CN204068023U (en) Ground connection pricker assembling and disassembling device
CN104201598B (en) Device for mounting and demounting grounding drill rod
CN202363805U (en) Pin puller used for pulling all types of insulator connecting pins
CN205122965U (en) Ground rod pull -out device
CN204497660U (en) A kind of multi-functional pin pulling clamp of insulator R type pin
CN205614574U (en) Cable protector fixed pin takes out instrument

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant