CN203788401U - Unified video monitoring platform system of power grid - Google Patents
Unified video monitoring platform system of power grid Download PDFInfo
- Publication number
- CN203788401U CN203788401U CN201420012416.0U CN201420012416U CN203788401U CN 203788401 U CN203788401 U CN 203788401U CN 201420012416 U CN201420012416 U CN 201420012416U CN 203788401 U CN203788401 U CN 203788401U
- Authority
- CN
- China
- Prior art keywords
- network
- subsystem
- control
- video monitoring
- control center
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 47
- 238000004891 communication Methods 0.000 claims description 6
- 238000002955 isolation Methods 0.000 claims description 6
- 238000003780 insertion Methods 0.000 claims description 3
- 230000037431 insertion Effects 0.000 claims description 3
- 230000006855 networking Effects 0.000 claims description 3
- 238000012545 processing Methods 0.000 abstract description 5
- 230000008901 benefit Effects 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 2
- 230000011664 signaling Effects 0.000 abstract description 2
- 238000000926 separation method Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 5
- 230000005540 biological transmission Effects 0.000 description 3
- 238000012423 maintenance Methods 0.000 description 3
- 230000009466 transformation Effects 0.000 description 3
- 230000008030 elimination Effects 0.000 description 2
- 238000003379 elimination reaction Methods 0.000 description 2
- 230000004927 fusion Effects 0.000 description 2
- 230000005764 inhibitory process Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000007246 mechanism Effects 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000013507 mapping Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Landscapes
- Data Exchanges In Wide-Area Networks (AREA)
Abstract
A unified video monitoring platform system of a power grid comprises a master control center subsystem, a branch control center subsystem, a monitoring front end subsystem, control system network nodes and monitoring system network nodes. The master control center subsystem comprises a centralized control comprehensive video interchanger, an Ethernet interchanger, a master control command and dispatch terminal and a browsing terminal. The branch control center subsystem comprises a city dispatch center system and a county dispatch center system. The city dispatch center system and the county dispatch center system respectively comprise a branch control command and dispatch terminal and a branch control comprehensive video interchanger. The master control center subsystem and the branch control center subsystem are connected through the control system network nodes. The branch control center subsystem and the monitoring front end subsystem are connected through the monitoring system network nodes. The unified video monitoring platform system of the power grid has the advantages that through signaling and media data flow separation, multiple modules work in cooperation and conduct processing in parallel, the data processing performance of a platform is improved, the reliability is improved, and the practical effect of the platform is enhanced.
Description
Technical field
The utility model relates to monitor supervision platform system field, particularly a kind of electrical network unify video monitoring platform system.
Background technology
Each province (city), prefecture-level company are in the different times basis demand to video monitor separately, built setting video surveillance in the local environments such as part transformer station, transmission line, machine room, but do not have at present a set of unified platform to realize unified management, monitoring and operation to the video of full electric network.Existing video monitoring system exists following not enough: due to equipment vendors, of a great variety, have that system too much relies on that equipment, the mutual disunity of each equipment room, each system are not connected, resource not shared deficiency mutually so that form separately independently " information island "; Technical system lacks perspective, cannot give full play to UNICOM's advantage of core communication network; Be subject to limitation of the technology, can not adopt efficient distribution of media mechanism, easily form transmission bottleneck, cannot adapt to large-scale networked, towards large user group's needs.In addition,, along with other operation systems of company are built and promoted as power transmission and transformation equipment state monitoring system, emergency commading system, the unified of information operation and maintenance supervising system, the demand that video access and visual means are presented in related service system shows especially day by day.
Utility model content
The purpose of this utility model is for for video monitoring self-demand, and other operation systems are unified video monitoring platform to the demand Construction Company of video information, realize the whole network video source is carried out to unified management, spy provides a kind of electrical network to unify video monitoring platform system.
The utility model provides a kind of electrical network to unify video monitoring platform system, it is characterized in that: described electrical network is unified video monitoring platform system, comprises Master Control Center subsystem 1, distributed control center subsystem 2, front monitoring front-end subsystem 3, Control System NetWork node 4, supervisory control system network node 5; Master Control Center subsystem 1 comprises collection control comprehensive video switch 101, Ethernet switch 102, master control command scheduling terminal 103, browsing terminal 104; Distributed control center subsystem 2 comprises system 21He county of control centre of city control centre's system 22; System 21He county of control centre of city control centre's system 22, comprises respectively sub-control command scheduling terminal 201 and sub-control comprehensive video switch 202; Front monitoring front-end subsystem 3 comprises business hall watch-dog 31;
Wherein: Master Control Center subsystem 1 is connected by Control System NetWork node 4 with distributed control center subsystem 2, distributed control center subsystem 2 is connected by supervisory control system network node 5 with front monitoring front-end subsystem 3;
After collection control comprehensive video switch 101, Ethernet switch 102 are connected successively with master control command scheduling terminal 103, be connected by network with browsing terminal 104;
System 21He county of control centre of city control centre's system 22 is connected with Ethernet switch 102 by network respectively; Business hall watch-dog 31 is connected to the network by supervisory control system network node 5.
Described electrical network is unified video monitoring platform system, unified video monitoring platform image management server network using twocouese 100/1000Mb/s (10/100/1000MBASE) light/electrical interface access communication network, transformer station's end network insertion can adopt following two kinds of modes:
E1 interface: G.703 signal transmitting and receiving;
LAN interface: 10base-T (RJ45UTP) standard interface, meets IEEE802.3/ETHERNET standard;
100BASE-TX standard interface, meets IEEE802.3U/ETHERNET standard;
Transformer station's end system should preferentially adopt integrated data network, at least ensures 2M bandwidth while sharing bandwidth;
Transformer station holds to link between field apparatus, adopts anti-interference strong medium to realize;
The network interconnection of the each level of system should be used existing Internet resources;
Should meet the networking requirements such as IP network clean culture, multicast functionality, IP address assignment should meet each electric company related specifications; In network system, divide independent video monitoring system for substation private network, unified video monitoring platform, operation
The mutual physical link isolation of team and transformer station's end and other Network or employing VLAN mode realize the logic isolation of VPN.
Concrete meaning is mainly reflected in the following aspects:
Unify the construction of video monitoring software platform by electrical network, solve unified collecting, on the basis of management, exchange, interface standard many equipment, multisystem fusion, elimination " information island ", effectively utilize the network bandwidth, reduce system safety hidden danger, reduce the video monitor fields such as later maintenance cost and need badly the problem of solution;
Utilize existing network condition in addition specification and appropriateness transformation, set up video surveillance data net, meet the multimedia communication demand of intelligent grid high definition and low delay;
Meet that company intelligent grid is built and " three collection five are large " System Construction in send out, defeated, become, join, with and manage requirement and the expectation of each link to video monitoring, offer the each video requirement cell call in rear end in the mode of unified interface, data, for power scheduling, production, operation, manage other operation systems real-time video source be provided, and the system such as fire-fighting, gate inhibition, SCADA realizes between system and linking.
Advantage of the present utility model:
Electrical network described in the utility model is unified video monitoring platform system, separate by signaling, media data flow, propose multiple module cooperative work, parallel processing, implementation platform is active and standby, loading functional, improve platform data handling property, improved platform operational reliability; By multichannel buffer technology, design multi-task scheduling data processing algorithm, realizes concurrent task processing, has improved user concurrent access quantity; Utilize stream media technology, propose modular deployment method for designing, realize the longitudinal cascade of Streaming Media module, effectively reduce media data taking and demand Internet resources; Identify and buffer technology by media data frame, realize key frame data reparation, avoid losing and causing the phenomenons such as picture pause, mosaic, Hua Ping because of critical data, propose intrusion I frame algorithm, realize video pictures and obtain now, improve video request response promptness; Adopt polymer matrix algorithm, propose presetting bit competition arbitration and Resources Sharing Mechanism, realize cradle head preset positions dynamic mapping, improve Sharing degree, avoided competition and the conflict of multiservice system to limited resources, strengthened the practical effect of platform.
Brief description of the drawings
Below in conjunction with drawings and the embodiments, the utility model is described in further detail:
Fig. 1 is that electrical network is unified video monitoring platform system configuration schematic diagram.
Embodiment
Embodiment
The utility model provides a kind of electrical network to unify video monitoring platform system, it is characterized in that: described electrical network is unified video monitoring platform system, comprises Master Control Center subsystem 1, distributed control center subsystem 2, front monitoring front-end subsystem 3, Control System NetWork node 4, supervisory control system network node 5; Master Control Center subsystem 1 comprises collection control comprehensive video switch 101, Ethernet switch 102, master control command scheduling terminal 103, browsing terminal 104; Distributed control center subsystem 2 comprises system 21He county of control centre of city control centre's system 22; System 21He county of control centre of city control centre's system 22, comprises respectively sub-control command scheduling terminal 201 and sub-control comprehensive video switch 202; Front monitoring front-end subsystem 3 comprises business hall watch-dog 31;
Wherein: Master Control Center subsystem 1 is connected by Control System NetWork node 4 with distributed control center subsystem 2, distributed control center subsystem 2 is connected by supervisory control system network node 5 with front monitoring front-end subsystem 3;
After collection control comprehensive video switch 101, Ethernet switch 102 are connected successively with master control command scheduling terminal 103, be connected by network with browsing terminal 104;
System 21He county of control centre of city control centre's system 22 is connected with Ethernet switch 102 by network respectively; Business hall watch-dog 31 is connected to the network by supervisory control system network node 5.
Described electrical network is unified video monitoring platform system, unified video monitoring platform image management server network using twocouese 100/1000Mb/s (10/100/1000MBASE) light/electrical interface access communication network, transformer station's end network insertion can adopt following two kinds of modes:
E1 interface: G.703 signal transmitting and receiving;
LAN interface: 10base-T (RJ45UTP) standard interface, meets IEEE802.3/ETHERNET standard;
100BASE-TX standard interface, meets IEEE802.3U/ETHERNET standard;
Transformer station's end system should preferentially adopt integrated data network, at least ensures 2M bandwidth while sharing bandwidth;
Transformer station holds to link between field apparatus, adopts anti-interference strong medium to realize;
The network interconnection of the each level of system should be used existing Internet resources;
Should meet the networking requirements such as IP network clean culture, multicast functionality, IP address assignment should meet each electric company related specifications; In network system, divide independent video monitoring system for substation private network, unified video monitoring platform, operation
The mutual physical link isolation of team and transformer station's end and other Network or employing VLAN mode realize the logic isolation of VPN.
Concrete meaning is mainly reflected in the following aspects:
Unify the construction of video monitoring software platform by electrical network, solve unified collecting, on the basis of management, exchange, interface standard many equipment, multisystem fusion, elimination " information island ", effectively utilize the network bandwidth, reduce system safety hidden danger, reduce the video monitor fields such as later maintenance cost and need badly the problem of solution;
Utilize existing network condition in addition specification and appropriateness transformation, set up video surveillance data net, meet the multimedia communication demand of intelligent grid high definition and low delay;
Meet that company intelligent grid is built and " three collection five are large " System Construction in send out, defeated, become, join, with and manage requirement and the expectation of each link to video monitoring, offer the each video requirement cell call in rear end in the mode of unified interface, data, for power scheduling, production, operation, manage other operation systems real-time video source be provided, and the system such as fire-fighting, gate inhibition, SCADA realizes between system and linking.
Claims (2)
1. an electrical network is unified video monitoring platform system, it is characterized in that: described electrical network is unified video monitoring platform system, comprise Master Control Center subsystem (1), distributed control center subsystem (2), front monitoring front-end subsystem (3), Control System NetWork node (4), supervisory control system network node (5); Master Control Center subsystem (1) comprises collection control comprehensive video switch (101), Ethernet switch (102), master control command scheduling terminal (103), browsing terminal (104); Distributed control center subsystem (2) comprises control centre of city system (21) and control centre of county system (22); Control centre of city system (21) and control centre of county system (22), comprise respectively sub-control command scheduling terminal (201) and sub-control comprehensive video switch (202); Front monitoring front-end subsystem (3) comprises business hall watch-dog (31);
Wherein: Master Control Center subsystem (1) is connected by Control System NetWork node (4) with distributed control center subsystem (2), distributed control center subsystem (2) is connected by supervisory control system network node (5) with front monitoring front-end subsystem (3);
After collection control comprehensive video switch (101), Ethernet switch (102) are connected successively with master control command scheduling terminal (103), be connected by network with browsing terminal (104);
Control centre of city system (21) is connected with Ethernet switch (102) by network respectively with control centre of county system (22); Business hall watch-dog (31) is connected to the network by supervisory control system network node (5).
2. unify video monitoring platform system according to electrical network claimed in claim 1, it is characterized in that: described electrical network is unified video monitoring platform system, unified video monitoring platform image management server network using twocouese 100/1000Mb/s (10/100/1000MBASE) light/electrical interface access communication network, transformer station's end network insertion adopts following two kinds of modes:
E1 interface: G.703 signal transmitting and receiving;
LAN interface: 10base-T (RJ45UTP) standard interface, meets IEEE802.3/ETHERNET standard;
100BASE-TX standard interface, meets IEEE802.3U/ETHERNET standard;
Transformer station's end system should preferentially adopt integrated data network, at least ensures 2M bandwidth while sharing bandwidth;
Transformer station holds to link between field apparatus, adopts anti-interference strong medium to realize;
The network interconnection of the each level of system should be used existing Internet resources;
Should meet the networking requirements such as IP network clean culture, multicast functionality, IP address assignment should meet each electric company related specifications; In network system, divide independent video monitoring system for substation private network, the mutual physical link isolation of unified video monitoring platform, operation team and transformer station's end and other Network or employing VLAN mode realize the logic isolation of VPN.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420012416.0U CN203788401U (en) | 2014-01-08 | 2014-01-08 | Unified video monitoring platform system of power grid |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420012416.0U CN203788401U (en) | 2014-01-08 | 2014-01-08 | Unified video monitoring platform system of power grid |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203788401U true CN203788401U (en) | 2014-08-20 |
Family
ID=51324551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420012416.0U Expired - Lifetime CN203788401U (en) | 2014-01-08 | 2014-01-08 | Unified video monitoring platform system of power grid |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203788401U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104639893A (en) * | 2014-12-05 | 2015-05-20 | 国家电网公司 | Unified power transmission and transformation video monitoring system |
CN108848351A (en) * | 2018-07-20 | 2018-11-20 | 广东力田科技股份有限公司 | A kind of power distribution room video surveillance and accident positioning software |
-
2014
- 2014-01-08 CN CN201420012416.0U patent/CN203788401U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104639893A (en) * | 2014-12-05 | 2015-05-20 | 国家电网公司 | Unified power transmission and transformation video monitoring system |
CN108848351A (en) * | 2018-07-20 | 2018-11-20 | 广东力田科技股份有限公司 | A kind of power distribution room video surveillance and accident positioning software |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103763525A (en) | Unified video monitoring platform system of power grid | |
CN109640029A (en) | The method and apparatus that wall is shown on a kind of video flowing | |
CN107249121A (en) | A kind of video monitoring system based on cloud platform | |
CN105790990A (en) | Method and system for monitoring and managing power distribution and utilization communication business | |
CN107959818A (en) | The data processing method of integrated terminal and integrated terminal | |
CN202652239U (en) | Information integration intelligent management system of public security monitoring system | |
CN103683506B (en) | Comprehensively-integrated linkage safety system of power system transformer substations | |
CN202798146U (en) | Six-remote integrated digital terminal system of transformer substation | |
CN203788401U (en) | Unified video monitoring platform system of power grid | |
CN201750435U (en) | GOOSE and SV common-network process layer network structure in a digitized transformer station | |
CN103024071A (en) | Quantum stream media cloud computing based cloud aggregation community system | |
CN102938839A (en) | Monitoring front-end equipment and encoding server | |
CN101938412B (en) | Power Ethernet switcher for Ethernet data and asynchronous data insolated synchronous transmission | |
CN203406896U (en) | Power fiber to home core network system | |
CN102281191A (en) | Multicast label switching method for uncompressed video | |
CN207612365U (en) | Unattended field overhead line video monitoring apparatus | |
CN104168454A (en) | HSV-iDCN comprehensive intelligent video monitoring and processing platform | |
CN205142215U (en) | HSR looped netowrk of communicating between communication device station between standing | |
CN201388234Y (en) | Dual-network cable communication system host | |
CN104410835B (en) | A kind of substation isolating-switch equipment state identifying system of view-based access control model analysis | |
CN204231561U (en) | Based on the power network video monitoring intelligent analyzing and alarming system of regulation and control integration | |
CN108639890A (en) | A kind of elevator monitoring system and software architecture | |
CN208656775U (en) | A kind of anti-information leakage control device of the idle fibre core of optical signal amplification light splitting | |
CN208272702U (en) | One kind being based on cloud platform Direct Current Power Supervise Control System | |
CN202652404U (en) | High definition video processing and conference platform system based on cloud computing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20140820 |
|
CX01 | Expiry of patent term |