CN203783827U - Novel longitudinal joint structure of wind power generation prefabricated concrete tower component - Google Patents

Novel longitudinal joint structure of wind power generation prefabricated concrete tower component Download PDF

Info

Publication number
CN203783827U
CN203783827U CN201420185674.9U CN201420185674U CN203783827U CN 203783827 U CN203783827 U CN 203783827U CN 201420185674 U CN201420185674 U CN 201420185674U CN 203783827 U CN203783827 U CN 203783827U
Authority
CN
China
Prior art keywords
longitudinal joint
steel pipe
positioning key
joint structure
concrete tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420185674.9U
Other languages
Chinese (zh)
Inventor
杨静安
申宽育
黄天润
罗林
***
杨鑫平
李振作
张鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Northwest Engineering Corp Ltd
Original Assignee
PowerChina Northwest Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Northwest Engineering Corp Ltd filed Critical PowerChina Northwest Engineering Corp Ltd
Priority to CN201420185674.9U priority Critical patent/CN203783827U/en
Application granted granted Critical
Publication of CN203783827U publication Critical patent/CN203783827U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model discloses a novel longitudinal joint structure of a wind power generation prefabricated concrete tower component. The novel longitudinal joint structure comprises a first cylinder wall and a second cylinder wall. The longitudinal joint contact faces of the first cylinder wall and the second cylinder wall are respectively provided with locating keys distributed at intervals. A locating key groove matched with the corresponding locating key is arranged between every two adjacent locating keys. A connecting hole channel is reserved in each locating key. A steel pipe is buried in the hole channel. After the locating keys are aligned with the locating key grooves, steel pipes in all the hole channels in the locating keys are located at the same vertical position, and through holes in the steel pipes vertically penetrate in the vertical direction. A steel bar is inserted in the through hole penetrating through each steel pipe. Finally, the integral component is formed through a whole through a grouting form; the key grooves are formed in the longitudinal joint faces, good connection of longitudinal joints can be ensured, the assembling schedule of the component is shortened, and the precision of butt joint is improved; the contact faces are coated with epoxy resin, the requirement for the strength is met, and the days for construction are saved; as the wedge-shaped locating keys can adjust the contact faces into folded lines, the contact area among structures is increased, and the stress condition of the structure is good.

Description

A kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure
Technical field
The utility model belongs to wind turbine tower field, is specifically related to a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure.
Background technique
The sternness of global energy anxiety and amblent air temperature problem, impels the development and utilization of various countries' pay attention to day by day to renewable energy sourcess such as wind energies.The wind speed of hinterland is conventionally much lower than coastal area, for the wind energy turbine set in low wind speed area in giving provides more generated energy, there are two kinds of main selections in blower fan supplier: they both can select to install the blower fan with larger wind wheel, also can be not having transformed unit to be arranged on higher wind tower.The selection of high tower only need increase appropriate investment, just can significantly improve power stage.Because the limitation of steel tower material behavior and cost have determined the inevitable of high concrete pylon, the cast-in-place concrete pylon construction time is longer, is difficult to meet wind field rapid construction requirement, and precast concrete pylon arises at the historic moment.Due to the restriction of communications and transportation to pylon structure size, pylon is spliced by a plurality of precast units, and therefore, the seam between member has become to control the key position of pylon safe operation.
Seam is a special tectonic of prefabricated staged construction structure, is the weakest link of precast reinforced concrete structure.The stress performance of precast spliced structure and working condition (anti-seismic performance, integrity and stability) and the intensity of splicing seam crossing and the reliability being connected, depend primarily on the quality that seam connects.
Application number is that 201310112541.9 patent document discloses a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure, its scheme is to be connected with high-strength bolt by pre-buried anchor plate, by sleeve, connect high-strength bolt, both sides sleeve is connected into integral body, finally by turnbarrel, realizes tightening up of precast units.Shortcoming is that component assembly is slower, and the area of contact between structure is little, and stress condition is bad.
Summary of the invention
The purpose of this utility model is to provide a kind of assembled progress that can accelerate precast units, saves time, and method of construction is simple, and structure stress is with favourable conditions, a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure of easy construction.
The utility model is to realize like this, a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure, comprise barrel one, barrel two, on the longitudinal joint surface of contact of barrel one and barrel two, be provided with positioning key spaced apart, it between adjacent positioning key, is the positioning spline matching with positioning key, the reserved duct that connects in described positioning key, and in duct, be embedded with steel pipe, after described positioning key and positioning spline contraposition, steel pipe in each positioning key inner duct is in same vertical position, and the through hole vertical direction in steel pipe runs through up and down, in the through hole running through in each steel pipe, be plugged with a rod iron.
Described steel pipe is externally connected with fixing joint bar vertical with steel pipe, and the described joint bar the other end extends in positioning key.
On described positioning spline, smear the epoxy resin that positioning key is gluedd joint in thick being used for of 1~2mm.
Described positioning key and positioning spline are at least two pairs, and after contraposition, seam surface of contact is broken line.
Described positioning key is for being wedge-type shape, the long 400mm in bottom, the long 207mm in top, the high 145mm of key; The long 210mm in positioning spline bottom, the long 403mm in top, groove depth 145mm, the thickness of barrel one and barrel two is 30cm~50cm.
The long 302mm of described steel pipe, diameter 42mm, thickness 2mm.
Described rod iron adopts HRB400, diameter 30mm, long 3.6m.
The beneficial effects of the utility model are: by embedded steel tube, be connected with high-strength steel bar, both sides tower cylinder is connected into integral body, finally by grouting form, guarantees that member forms integral body; Longitudinal joint face arranges keyway, can guarantee the good connection of longitudinal joint, has accelerated component assembly progress and merging precision, saved the time, method of construction is simple, easy construction, construction time does not recycle the equipment such as welding, smears epoxy resin can meet requirement of strength at surface of contact, can save the duration again; It is broken line that wedge shape positioning key capable of regulating surface of contact is set, thereby increases the area of contact between structure, better to the stress condition of structure.
Accompanying drawing explanation
Below in conjunction with embodiment's accompanying drawing, the utility model is described further:
Fig. 1 is longitudinal joint schematic diagram;
Fig. 2 is longitudinal joint Connecting format schematic diagram;
In figure: 1. longitudinal joint; 2. joint bar; 3. steel pipe; 4. rod iron; 5. duct; 6. positioning key; 7. positioning spline; 8. marine glue; 9-1. barrel one; 9-2. barrel two.
Embodiment
Embodiment 1:
A kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as depicted in figs. 1 and 2, comprise and on longitudinal joint 1 surface of contact of barrel one 9-1 and barrel two 9-2, be provided with positioning key 6 spaced apart, it between adjacent positioning key 6, is the positioning spline 7 matching with positioning key 6, the interior reserved connection of described positioning key 6 duct 5, and in duct 5, be embedded with steel pipe 3, after described positioning key 6 and positioning spline 7 contrapositions, steel pipe 3 in each positioning key 6 inner ducts 5 is in same vertical position, and the through hole vertical direction in steel pipe 3 runs through up and down, in the through hole running through in each steel pipe 3, be plugged with a rod iron 4.
Steel pipe is externally connected with fixing joint bar vertical with steel pipe, and the described joint bar the other end extends in positioning key.
For guaranteeing that component assembly is stressed good and evenly, positioning key 6 and the positioning spline 7 on barrel both sides match, positioning key 6 and positioning spline 7 are at least two pairs and be uniformly distributed.The described positioning key 6 long 400mm in bottom, the long 207mm in top, the high 145mm of key; The positioning spline 7 long 210mm in bottom, the long 403mm in top, groove depth 145mm, barrel thickness is 30cm~50cm; The long 302mm of steel pipe 3 used, diameter 42mm, thickness 2mm.
During construction, on positioning spline 7, smear the epoxy resin that positioning key 6 is gluedd joint in thick being used for of 1~2mm.After positioning key 6 is accurately docked with positioning spline 7, insert diameter 30mm, the rod iron 4 of long 3.6m is fixing, finally utilizes high-strength cement slurry that duct perfusion is closely knit, guarantees that member forms integral body.
Positioning key 6 is for being wedge-type shape, and capable of regulating surface of contact is broken line, thereby increases the area of contact between barrel, better to the stress condition of structure.
For proof strength, the rod iron of insertion adopts HRB400.
The beneficial effects of the utility model are, by embedded steel tube, are connected with high-strength steel bar, and both sides tower cylinder is connected into integral body, finally by grouting form, guarantees that member forms integral body; Longitudinal joint face arranges keyway, can guarantee the good connection of longitudinal joint, has accelerated component assembly progress and merging precision, saved the time, method of construction is simple, easy construction, construction time does not recycle the equipment such as welding, smears epoxy resin can meet requirement of strength at surface of contact, can save the duration again; It is broken line that wedge shape positioning key capable of regulating surface of contact is set, thereby increases the area of contact between structure, better to the stress condition of structure.

Claims (7)

1. a novel wind-power electricity generation precast concrete tower member longitudinal joint structure, comprise barrel one (9-1), barrel two (9-2), it is characterized in that: on longitudinal joint (1) surface of contact of barrel one (9-1) and barrel two (9-2), be provided with positioning key (6) spaced apart, it between adjacent positioning key (6), is the positioning spline (7) matching with positioning key (6), the reserved duct (5) that connects in described positioning key (6), and in duct (5), be embedded with steel pipe (3), after described positioning key (6) and positioning spline (7) contraposition, steel pipe (3) in each positioning key (6) inner duct (5) is in same vertical position, and the through hole vertical direction in steel pipe (3) runs through up and down, in the through hole running through in each steel pipe (3), be plugged with a rod iron (4).
2. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as claimed in claim 1, it is characterized in that: described steel pipe (3) is externally connected with and the vertical fixing joint bar of steel pipe (3) (2), described joint bar (2) the other end extends in positioning key (6).
3. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as claimed in claim 1, is characterized in that: on described positioning spline (7), smear thick being used for of 1~2mm and glued joint the epoxy resin of positioning key (6).
4. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as claimed in claim 1, is characterized in that: described positioning key (6) is at least two pairs with positioning spline (7), and after contraposition, seam surface of contact is broken line.
5. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as described in claim 1 or 3, is characterized in that: described positioning key (6) is for being wedge-type shape, the long 400mm in bottom, the long 207mm in top, the high 145mm of key; The long 210mm in positioning spline (7) bottom, the long 403mm in top, groove depth 145mm, the thickness of barrel one (9-1) and barrel two (9-2) is 30cm~50cm.
6. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as claimed in claim 1, is characterized in that: the long 302mm of described steel pipe, diameter 42mm, thickness 2mm.
7. a kind of novel wind-power electricity generation precast concrete tower member longitudinal joint structure as claimed in claim 1, is characterized in that: described rod iron adopts HRB400, diameter 30mm, long 3.6m.
CN201420185674.9U 2014-04-17 2014-04-17 Novel longitudinal joint structure of wind power generation prefabricated concrete tower component Expired - Lifetime CN203783827U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420185674.9U CN203783827U (en) 2014-04-17 2014-04-17 Novel longitudinal joint structure of wind power generation prefabricated concrete tower component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420185674.9U CN203783827U (en) 2014-04-17 2014-04-17 Novel longitudinal joint structure of wind power generation prefabricated concrete tower component

Publications (1)

Publication Number Publication Date
CN203783827U true CN203783827U (en) 2014-08-20

Family

ID=51320020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420185674.9U Expired - Lifetime CN203783827U (en) 2014-04-17 2014-04-17 Novel longitudinal joint structure of wind power generation prefabricated concrete tower component

Country Status (1)

Country Link
CN (1) CN203783827U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104265582A (en) * 2014-09-26 2015-01-07 国电联合动力技术有限公司 Structure adopting wedged ring for connection and wind turbine generator tower barrel including same
CN106087706A (en) * 2016-07-22 2016-11-09 中铁第四勘察设计院集团有限公司 Precast body wet seam attachment structure and wet connecing thereof dry make construction method
CN106438214A (en) * 2016-10-08 2017-02-22 霍尔果斯新国金新能源科技有限公司 Tower drum used for wind driven generator
CN106640538A (en) * 2016-10-08 2017-05-10 霍尔果斯新国金新能源科技有限公司 Tower tube component and grouting method thereof
CN106949017A (en) * 2017-05-05 2017-07-14 同济大学建筑设计研究院(集团)有限公司 A kind of prefabricated mixing pylon of Wind turbines bottom burst
CN107023442A (en) * 2017-06-08 2017-08-08 北京建筑大学 A kind of connected mode of precast concrete tower
EP3502466A1 (en) 2017-12-19 2019-06-26 Nordex Energy Spain, S.A.U. Wind turbine tower with reinforcing elements

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104265582A (en) * 2014-09-26 2015-01-07 国电联合动力技术有限公司 Structure adopting wedged ring for connection and wind turbine generator tower barrel including same
CN106087706A (en) * 2016-07-22 2016-11-09 中铁第四勘察设计院集团有限公司 Precast body wet seam attachment structure and wet connecing thereof dry make construction method
CN106087706B (en) * 2016-07-22 2018-04-03 中铁第四勘察设计院集团有限公司 The wet seam attachment structure of precast body and its wet connect dry make construction method
CN106438214A (en) * 2016-10-08 2017-02-22 霍尔果斯新国金新能源科技有限公司 Tower drum used for wind driven generator
CN106640538A (en) * 2016-10-08 2017-05-10 霍尔果斯新国金新能源科技有限公司 Tower tube component and grouting method thereof
CN106949017A (en) * 2017-05-05 2017-07-14 同济大学建筑设计研究院(集团)有限公司 A kind of prefabricated mixing pylon of Wind turbines bottom burst
CN107023442A (en) * 2017-06-08 2017-08-08 北京建筑大学 A kind of connected mode of precast concrete tower
EP3502466A1 (en) 2017-12-19 2019-06-26 Nordex Energy Spain, S.A.U. Wind turbine tower with reinforcing elements
US10895089B2 (en) 2017-12-19 2021-01-19 Nordex Energy Spain, S.A.U. Wind turbine tower with reinforcing elements

Similar Documents

Publication Publication Date Title
CN203783827U (en) Novel longitudinal joint structure of wind power generation prefabricated concrete tower component
CN102767303B (en) Precast concrete tower and construction method thereof
US10030792B2 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof
CN203569582U (en) Connecting structure of concrete pipe pile and bearing platform
CN105201530A (en) Repairing and strengthening method for large cracks on rock tunnel lining
CN204098065U (en) A kind of can the precast assembly pipe gallery of stretch-draw in body
CN103195668B (en) Novel wind power generation precast concrete tower component seaming structure and method
CN203175133U (en) Prefabricated concrete fan tower
CN103590414A (en) Structure for connecting concrete tubular pile with bearing platform
CN203229965U (en) 10 kV box-type substation basic standard module
CN206035500U (en) Adopt prestressing steel's section of jurisdiction connecting device
CN102352630A (en) Full-thread fiber resin rod body soil nailing wall and construction method thereof
CN202768012U (en) Tunnel primary lining prefabricated concrete block assembly
CN206503608U (en) A kind of contractibility assembled steel board mount
CN108331263A (en) Self-locking mechanical branch sleeve
CN205188954U (en) Novel reinforced concrete prefabrication side stake pile extension structure
CN203452195U (en) Double-pre-buried-plate opposite-pulling-type built-in fitting
CN106979635A (en) A kind of earth-source hot-pump system underground heat-transfer pipe construction method
CN103291110B (en) A kind of have the power transmission rod waved with Self-resetting function
CN203783826U (en) Novel cross joint structure of wind power generation prefabricated concrete tower component
CN212316969U (en) Tubular pile composite tower
CN106677809A (en) Contractible fabricated steel plate support
CN203189209U (en) Novel seam-joint structure of wind power generation precast concrete tower components
CN202227350U (en) Soil nailing wall made of fully-threaded fiber resin rods
CN104153630A (en) Transition connection method of hybrid wind power towers

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140820

CX01 Expiry of patent term