CN203701104U - Connection structure for prefabricated open column and foundation pit - Google Patents

Connection structure for prefabricated open column and foundation pit Download PDF

Info

Publication number
CN203701104U
CN203701104U CN201420043528.2U CN201420043528U CN203701104U CN 203701104 U CN203701104 U CN 203701104U CN 201420043528 U CN201420043528 U CN 201420043528U CN 203701104 U CN203701104 U CN 203701104U
Authority
CN
China
Prior art keywords
foundation ditch
foundation pit
formed members
open column
members post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420043528.2U
Other languages
Chinese (zh)
Inventor
大卫·卡斯特尔·迪亚兹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Yu Tong Bao Machinery Equipment Co., Ltd.
Original Assignee
Practical Building Materials (linyi) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Practical Building Materials (linyi) Co Ltd filed Critical Practical Building Materials (linyi) Co Ltd
Priority to CN201420043528.2U priority Critical patent/CN203701104U/en
Application granted granted Critical
Publication of CN203701104U publication Critical patent/CN203701104U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model provides a connection structure for a prefabricated open column and a foundation pit. The connection structure is composed of the foundation pit, a steel bar framework and the prefabricated open column. The steel bar framework is composed of pre-buried steel bars arranged in the vertical direction and annular stirrups binding the pre-buried steel bars transversely. The prefabricated open column is hollow, and the top of the prefabricated open column is open. The prefabricated open column is arranged above the foundation pit. The steel bar framework penetrates through the portion between the hollow portion inside the prefabricated open column and the foundation pit. Reinforced steel bar nets composed of steel bars in the transverse direction and the vertical direction are respectively arranged on the top and the lower portion of the foundation pit. The portion among the foundation pit, the steel bar framework and the prefabricated open column is filled with grouting mud and fixed, and a concrete cushion layer is arranged on the bottom of the foundation pit.

Description

The syndeton of pre-formed members post and foundation ditch
Technical field
The utility model relates to building trade ground foundation engineering technical field, relates in particular to the syndeton of a kind of pre-formed members post and foundation ditch.
Background technology
In industrial production, the ground foundation engineering in existing building trade is the very concerned industry field with paying attention to always, how to make solid durable foundation, is unusual important field of research.
Along with the raising of expanding economy and the requirement of people's dwelling environment, building is built higher and higher in recent years, also more and more higher for foundation construction requirements, capital faces excavation of foundation pit, excavation of foundation pit is a complicated comprehensive geotechnical engineering, and the cutting depth of foundation ditch is also more and more darker, owing to being subject to the impact of the servicing units such as foundation ditch braced structures, adopt between which kind of construction method guarantee foundation ditch and column not only easy for installation and firm and durable, and economical, energy-conservation and environmental protection, seem particularly important.
Utility model content
For above-mentioned defect of the prior art and problem, the object of the utility model embodiment is to provide a kind of pre-formed members post of better reliability and the syndeton of foundation ditch, thereby improves steadiness.
In order to achieve the above object, the utility model embodiment provides following technical scheme:
A syndeton for pre-formed members post and foundation ditch, is made up of foundation ditch, cage of reinforcement and pre-formed members post, it is characterized in that, cage of reinforcement is made up of the embedded ribs vertically arranging, the ring-shaped stirrup that laterally bundlees embedded ribs; Pre-formed members post hollow and open top, and be positioned at foundation ditch top, cage of reinforcement runs through between the cavity and foundation ditch of whole pre-formed members post inside.
As technique scheme preferably, the top of foundation ditch and bottom are provided with the stiffener net being made up of the reinforcing bar of horizontal and vertical both direction respectively.
As technique scheme preferably, between foundation ditch, cage of reinforcement and pre-formed members post, fill up and fix by grouting pug.
As technique scheme preferably, the bottom of foundation ditch is provided with concrete cushion.
A kind of pre-formed members post that the utility model embodiment provides and the syndeton of foundation ditch, compared with prior art, advantage of the present utility model is just: once the grouting material pouring into solidifies, will between pre-formed members post and foundation ditch, form a perfect homogeneous is connected, its duty is as same entirety, not yielding and avalanche.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only embodiment more of the present utility model, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is the structural representation of the pre-formed members post of the utility model embodiment and the syndeton of foundation ditch.
The specific embodiment
Below in conjunction with accompanying drawing of the present utility model, the technical solution of the utility model is clearly and completely described, obviously, described embodiment is only the utility model part embodiment, rather than whole embodiment.Based on the embodiment in the utility model, those of ordinary skills are not making the every other embodiment obtaining under creative work prerequisite, all belong to the scope of the utility model protection.
As shown in Figure 1, the syndeton of a kind of pre-formed members post and foundation ditch, is made up of foundation ditch 1, cage of reinforcement and pre-formed members post 2, and cage of reinforcement is made up of the embedded ribs 31 vertically arranging, the ring-shaped stirrup 32 that laterally bundlees embedded ribs; Pre-formed members post 2 hollows and open top, and be positioned at foundation ditch 1 top, cage of reinforcement runs through between the cavity and foundation ditch 1 of whole pre-formed members post 2 inside, the top of foundation ditch 1 and bottom are provided with the stiffener net 4 being made up of the reinforcing bar of horizontal and vertical both direction respectively, between foundation ditch 1, cage of reinforcement and pre-formed members post 2, filled up and fixed by grouting pug, the bottom of foundation ditch is provided with concrete cushion 5.
Foundation ditch is a cube of solid, its top is the cage of reinforcement outside outstanding foundation ditch, to be connected with pre-formed members post, simultaneously with the buffering power that pillar was born, after once foundation ditch completes, pre-formed members post need be installed on foundation ditch, the cavity of pre-formed members post is inserted in the cage of reinforcement outside outstanding foundation ditch, next, use the flow grouting pug of shrinkage-void to pour into and fill up this post hole, this mud is a kind of high-intensity slurry, and intensity approximately can reach 60-70 MPas, specially for grouting or anchoring design.
Consequently, once the grouting material pouring into solidifies, will between pre-formed members post and foundation ditch, form a perfect homogeneous and be connected, its duty is as same entirety.
The above; it is only the specific embodiment of the present utility model; but protection domain of the present utility model is not limited to this; any be familiar with those skilled in the art the utility model disclose technical scope in; can expect easily changing or replacing, within all should being encompassed in protection domain of the present utility model.Therefore, protection domain of the present utility model should described be as the criterion with the protection domain of claim.

Claims (4)

1. a syndeton for pre-formed members post and foundation ditch, is made up of foundation ditch, cage of reinforcement and pre-formed members post, it is characterized in that, cage of reinforcement is made up of the embedded ribs vertically arranging, the ring-shaped stirrup that laterally bundlees embedded ribs; Pre-formed members post hollow and open top, and be positioned at foundation ditch top, cage of reinforcement runs through between the cavity and foundation ditch of whole pre-formed members post inside.
2. the syndeton of a kind of pre-formed members post according to claim 1 and foundation ditch, is characterized in that, the top of foundation ditch and bottom are provided with the stiffener net being made up of the reinforcing bar of horizontal and vertical both direction respectively.
3. the syndeton of a kind of pre-formed members post according to claim 1 and foundation ditch, is characterized in that, between foundation ditch, cage of reinforcement and pre-formed members post, is filled up and is fixed by grouting pug.
4. the syndeton of a kind of pre-formed members post according to claim 1 and foundation ditch, is characterized in that, the bottom of foundation ditch is provided with concrete cushion.
CN201420043528.2U 2014-01-23 2014-01-23 Connection structure for prefabricated open column and foundation pit Expired - Fee Related CN203701104U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420043528.2U CN203701104U (en) 2014-01-23 2014-01-23 Connection structure for prefabricated open column and foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420043528.2U CN203701104U (en) 2014-01-23 2014-01-23 Connection structure for prefabricated open column and foundation pit

Publications (1)

Publication Number Publication Date
CN203701104U true CN203701104U (en) 2014-07-09

Family

ID=51051560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420043528.2U Expired - Fee Related CN203701104U (en) 2014-01-23 2014-01-23 Connection structure for prefabricated open column and foundation pit

Country Status (1)

Country Link
CN (1) CN203701104U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350566A (en) * 2015-12-10 2016-02-24 国网四川省电力公司乐山供电公司 Ground pile structure of tower type electric power support
CN105386456A (en) * 2015-12-10 2016-03-09 国网四川省电力公司乐山供电公司 Ground pile structure of anti-incline tower-type electric bracket

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350566A (en) * 2015-12-10 2016-02-24 国网四川省电力公司乐山供电公司 Ground pile structure of tower type electric power support
CN105386456A (en) * 2015-12-10 2016-03-09 国网四川省电力公司乐山供电公司 Ground pile structure of anti-incline tower-type electric bracket

Similar Documents

Publication Publication Date Title
CN106869321A (en) The prefabricated regeneration concrete bean column node and its construction method of a kind of reinforcement
CN202626972U (en) Novel section precast concrete fender post
CN206737118U (en) A kind of prefabricated regeneration concrete bean column node of reinforcement
CN103321244A (en) Construction method for additionally arranged basement in existing building on sand foundation
CN104878835A (en) Strip-shaped foundation house rear basement structure
CN103938634A (en) Deep foundation pit supporting structure and construction method
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN203614107U (en) Composite retaining structure for horsehead
CN103790176B (en) A kind of construction method of pre-buried manomelia rod structure
CN103015414A (en) Precast concrete post grouting pile and grouting process
CN103122642B (en) Construction method of vertical post support change
CN203701104U (en) Connection structure for prefabricated open column and foundation pit
CN204282399U (en) A kind of subway space enclosing structure
CN203866852U (en) Anti-floating pile structure composited by deep spiral-spraying cement soil plate and anchor rod
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN218346208U (en) Permanent side slope supporting structure based on reinforced concrete pile
CN207003470U (en) A kind of pin-connected panel ecological anchor rod retaining wall structure
CN203821399U (en) Deep foundation pit supporting structure
CN107905805B (en) Reinforced supporting method for guaranteeing excavation molding of machine pit partition piers of underground powerhouse and machine pit partition pier structure of underground powerhouse
CN102535496A (en) Expanded pier structure and forming method thereof
CN206015511U (en) One implant post steel pipe column
CN205591210U (en) Formula cast member and construction assembly are spliced to underground
CN204959769U (en) Lower part has stagnant water centrifugation side of strutting stake envelope in clamping orient groove
CN204875851U (en) Underground structure's antidetonation reinforced structure
CN204112858U (en) The prefabricated enclosure wall of a kind of prestressed concrete

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180424

Address after: 100000 C136 1, No. 13 building, Lai Guang Ying Ying Qiu yuan, Chaoyang District, Beijing.

Patentee after: Beijing Yu Tong Bao Machinery Equipment Co., Ltd.

Address before: 276000 Linyi economic and Technological Development Zone, Zhongshan Road, Shandong and Foshan Road Interchange

Patentee before: Practical building materials (Linyi) Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140709

Termination date: 20190123