CN203546898U - Detachable clamp-fixing engineering scaffold for factory building installation - Google Patents
Detachable clamp-fixing engineering scaffold for factory building installation Download PDFInfo
- Publication number
- CN203546898U CN203546898U CN201320553721.6U CN201320553721U CN203546898U CN 203546898 U CN203546898 U CN 203546898U CN 201320553721 U CN201320553721 U CN 201320553721U CN 203546898 U CN203546898 U CN 203546898U
- Authority
- CN
- China
- Prior art keywords
- steel plate
- steel
- iron
- factory building
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a detachable clamp-fixing engineering scaffold for factory building installation. The detachable clamp-fixing engineering scaffold for factory building installation is used for connection for steel structure beams with large inter-beam spans and no connection beams, and comprises a fixed steel plate, a bolt and I-shaped steel, wherein the I-shaped steel is vertically arranged between the H-shaped steel structure beams of the roof of a factory building; the fixed steel plate is arranged between the I-shaped steel and a wall body; and flange steel plates are arranged on the lower flanges of the H-shaped steel structure beams at the both sides. According to the detachable clamp-fixing engineering scaffold for factory building installation disclosed by the utility model, the H-shaped steel structure beams with large inter-beam spans and no connection beams are connected by the I-shaped steel, the steel plates are used between the I-shaped steel and the H-shaped steel structure beams, and fixed by bolts, and various sectional steel supports can be installed on the steel plates. The detachable clamp-fixing engineering scaffold for factory building installation disclosed by the utility model is of a detachable structure, overheat burning brought by the traditional welding mode to the steel structure beams can be avoided; moreover, the prestress influence of the steel structure beams of the detachable clamp-fixing engineering scaffold for factory building installation disclosed by the utility model is less.
Description
Technical field
The utility model relates to a kind of engineering rack, and especially a kind of detachable clamp is fixed factory building installing engineering support.
Background technology
What general industry steel structural plant roof adopted is H type steel girder structure, between Liang Yuliang, span is larger, and without tie-beam, the supports such as air-conditioning water pipe, airduct, extinguishing pipe cannot fixedly mount, shape steel bracket and mounted steel structure girder directly weld, easily steel structure member is caused to overdo and burn, can have a strong impact on the prestressing force of steel structure girder, have very large potential safety hazard.
Utility model content
For solving shape steel bracket on H type steel constructed beam, cannot fixedly mount, the direct welding of shape steel bracket easily causes to overdo burns, has a strong impact on the prestressed problem of steel structure girder, the utility model provides one can lay multiple-type steel bracket, can not produce to overdo on steel structure girder and burn and steel structure girder prestressing force affects the fixing factory building installing engineering support of little detachable clamp.
Technical problem to be solved in the utility model is achieved through the following technical solutions:
The fixing factory building installing engineering support of a kind of detachable clamp, comprise fixation steel plate, bolt and i iron, described i iron is vertical between factory building roof H formed steel construction beam, between described i iron and body of wall, is provided with fixation steel plate, and the edge of a wing, described both sides H formed steel construction beam below is provided with edge of a wing steel plate.
When described i iron is connected with H formed steel construction beam, described H formed steel construction beam below wing plate has bottom surface steel plate, and described H formed steel construction beam below wing plate is provided with i iron, is provided with sandwich clad steel and bolt one between described i iron and bottom surface steel plate.
Described bolt one runs through i iron, sandwich clad steel and bottom surface steel plate, and described bolt one head and bottom nut are divided on i iron and bottom surface steel plate.
When described i iron and wall connecting, described fixation steel plate one side is vertically provided with i iron, and described fixation steel plate opposite side is located on body of wall, and described fixation steel plate is provided with bolt.
During the monolateral connection H of described i iron formed steel construction beam, described edge of a wing steel plate is provided with bolt two, and described bolt two runs through edge of a wing steel plate, sandwich clad steel and bottom surface steel plate, and described bolt two heads and bottom nut are divided on edge of a wing steel plate and bottom surface steel plate.
The beneficial effects of the utility model are:
The utility model adopt i iron be connected and fixed span large, without the H formed steel construction beam of tie-beam, between i iron and H formed steel construction beam, adopt steel plate, and by the fixing mode of bolt, can lay multiple-type steel bracket thereon, the utility model be demountable structure avoided that traditional welding way brings steel structure girder produced to overdo burn, and steel structure girder prestressing force of the present utility model impact is little.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the specific embodiment of the present utility model is described in further detail.
Fig. 1 is the monolateral johning knot composition of the utility model i iron;
Fig. 2 is the utility model i iron and connecting structure of wall figure.
In figure, 1. fixation steel plate, 3. i iron, 4. edge of a wing steel plate, 5. bottom surface steel plate, 6. sandwich clad steel, 7. bolt one, 8. bolt two.
The specific embodiment
As shown in Figure 1-2, the utility model detachable clamp is fixed factory building installing engineering support, fixation steel plate 1, bottom surface steel plate 5, sandwich clad steel 6, edge of a wing steel plate 4, i iron 3, bolt, bolt 1 and bolt 28, consists of.
Fixation steel plate 1, bottom surface steel plate 5, sandwich clad steel 6, edge of a wing steel plate 4 are preferably the steel plate processing and fabricating that 12mm is thick and form.
As shown in Figure 1, when i iron 3 is connected with H formed steel construction beam, H formed steel construction beam below wing plate bottom is laid bottom surface steel plate 5, i iron 3 is laid on wing plate upper strata, H formed steel construction beam below, bottom surface steel plate 5 and i iron 3 below wing plates fixedly step up to be positioned at middle H formed steel construction beam below wing plate, fixed sandwich steel plate 6 between i iron 3 and bottom surface steel plate 5, sandwich clad steel 6 is used for filling the height between bottom surface steel plate 5 and i iron 3 below wing plates, its packed height and H formed steel construction beam below wing plate consistency of thickness.
Wing plate both sides, sandwich clad steel 6 and bottom surface steel plate 5 relevant positions below i iron 3, symmetry is drilled with four bolts hole, and bolt hole size is corresponding with bolt one 7 sizes.Bolt 1 runs through the bolt hole on i iron 3, sandwich clad steel 6 and bottom surface steel plate 5, bolt one 7 heads and bottom nut be separately fixed on i iron 3 below wing plates and bottom surface steel plate 5 on.
During the monolateral connection H of i iron 3 formed steel construction beam, on the wing plate of H formed steel construction beam below, a side is laid i iron 3, and opposite side is laid edge of a wing steel plate 4, and edge of a wing steel plate 4 is drilled with bolt hole, and bolt hole size is corresponding with bolt 28 sizes.Bolt 28 runs through edge of a wing steel plate 4, sandwich clad steel 6 and bottom surface steel plate 5, and bolt 28 heads and bottom nut divide and be fixed on edge of a wing steel plate 4 and bottom surface steel plate 5.
As shown in Figure 2, when i iron 3 and wall connecting, i iron 3 connecting wall one end are vertically welded with fixation steel plate 1, fixation steel plate 1 is installed between brick wall and metope structure beam, and the metope structure beam partial response symmetry of fixation steel plate 1 be drilled with hole erection bolt, fixation steel plate 1 is fixed on body of wall.
Should be understood that, the above-mentioned specific embodiment of the present utility model is only for exemplary illustration or explain principle of the present utility model, and do not form restriction of the present utility model.Therefore any modification of, making, be equal to replacement, improvement etc., within all should being included in protection domain of the present utility model in the situation that not departing from spirit and scope of the present utility model.In addition, the utility model claims are intended to contain whole variations and the modification in the equivalents that falls into claims scope and border or this scope and border.
Claims (5)
1. the fixing factory building installing engineering support of detachable clamp, comprise fixation steel plate (1), bolt and i iron (3), it is characterized in that: described i iron (3) is vertical between factory building roof H formed steel construction beam, between described i iron (3) and body of wall, be provided with fixation steel plate (1), the edge of a wing, described both sides H formed steel construction beam below is provided with edge of a wing steel plate (4).
2. the fixing factory building installing engineering support of detachable clamp according to claim 1, it is characterized in that: when described i iron (3) is connected with H formed steel construction beam, described H formed steel construction beam below wing plate has bottom surface steel plate (5), described H formed steel construction beam below wing plate is provided with i iron (3), is provided with sandwich clad steel (6) and bolt one (7) between described i iron (3) and bottom surface steel plate (5).
3. the fixing factory building installing engineering support of detachable clamp according to claim 2, it is characterized in that: described bolt one (7) runs through i iron (3), sandwich clad steel (6) and bottom surface steel plate (5), described bolt one (7) head and bottom nut are divided on i iron (3) and bottom surface steel plate (5).
4. the fixing factory building installing engineering support of detachable clamp according to claim 1, it is characterized in that: when described i iron (3) and wall connecting, described fixation steel plate (1) one side is vertically provided with i iron (3), described fixation steel plate (1) opposite side is located on body of wall, and described fixation steel plate (1) is provided with bolt.
5. the fixing factory building installing engineering support of detachable clamp according to claim 3, it is characterized in that: during the monolateral connection H of described i iron (3) formed steel construction beam, described edge of a wing steel plate (4) is provided with bolt two (8), described bolt two (8) runs through edge of a wing steel plate (4), sandwich clad steel (6) and bottom surface steel plate (5), and described bolt two (8) heads and bottom nut are divided on edge of a wing steel plate (4) and bottom surface steel plate (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320553721.6U CN203546898U (en) | 2013-09-06 | 2013-09-06 | Detachable clamp-fixing engineering scaffold for factory building installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320553721.6U CN203546898U (en) | 2013-09-06 | 2013-09-06 | Detachable clamp-fixing engineering scaffold for factory building installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203546898U true CN203546898U (en) | 2014-04-16 |
Family
ID=50465033
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320553721.6U Expired - Fee Related CN203546898U (en) | 2013-09-06 | 2013-09-06 | Detachable clamp-fixing engineering scaffold for factory building installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203546898U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109210275A (en) * | 2018-11-05 | 2019-01-15 | 上海宝冶集团有限公司 | A kind of I-beam pipe installation bracket |
-
2013
- 2013-09-06 CN CN201320553721.6U patent/CN203546898U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109210275A (en) * | 2018-11-05 | 2019-01-15 | 上海宝冶集团有限公司 | A kind of I-beam pipe installation bracket |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103114681B (en) | High-altitude long-span reinforced concrete beam treat pouring structure | |
CN207728795U (en) | Crane span structure antidetonation suspension and support | |
CN102359180A (en) | Truss combined beam and upper and layer connected light steel structure and construction method thereof | |
CN104060542B (en) | Compound beam cable stayed bridge direction across bridge prestress application device and applying method thereof | |
CN202481960U (en) | Wall-attached frame of tower crane | |
CN203420477U (en) | Steel structure set-up platform for concrete pouring | |
CN203546898U (en) | Detachable clamp-fixing engineering scaffold for factory building installation | |
CN202706508U (en) | Overhanging strength bearing steel beam construction member of scaffold | |
CN209839352U (en) | Horizontal mounting bracket for heavy pipeline of steel structure building | |
CN208563657U (en) | A kind of assembling type steel pipe concrete diagonal brace steel plate shear force wall | |
CN204139631U (en) | The guard rail of building site fast demountable | |
CN207844882U (en) | Steel column and crane beam connecting structure | |
CN203795459U (en) | Foundation structure of tower crane for high-altitude roofs | |
CN209941512U (en) | Supporting shear part for lower cross beam of inclined tower of cable-stayed bridge | |
CN205329437U (en) | Two line track roof beams of rail formula track traffic are embraced in magnetic suspension | |
CN205329438U (en) | Two line track roof beams of rail formula track traffic are embraced in magnetic suspension | |
CN204850068U (en) | Connection structure of side column and crane beam tip in steel construction | |
CN204940662U (en) | A kind of hall suspended ceiling mounting structure | |
CN202913716U (en) | Temporary support structure for truss integral lifting | |
CN204139334U (en) | Girder steel and steel column weld temporary connecting structure entirely | |
CN203451109U (en) | I-shaped steel truss device for tower crane attachment | |
CN203878779U (en) | Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint | |
CN206053080U (en) | A kind of floor mounting structure for steel house | |
CN203222981U (en) | Suspended platform for steel reinforced concrete cantilever structure construction | |
CN202017257U (en) | Large-span transformational structure for high-rise building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140416 Termination date: 20140906 |
|
EXPY | Termination of patent right or utility model |