CN203517866U - Waste heat boiler with novel water wall roof tube through-wall structure - Google Patents

Waste heat boiler with novel water wall roof tube through-wall structure Download PDF

Info

Publication number
CN203517866U
CN203517866U CN201320529382.8U CN201320529382U CN203517866U CN 203517866 U CN203517866 U CN 203517866U CN 201320529382 U CN201320529382 U CN 201320529382U CN 203517866 U CN203517866 U CN 203517866U
Authority
CN
China
Prior art keywords
roof
water
tube
water wall
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320529382.8U
Other languages
Chinese (zh)
Inventor
吴金土
卞俊
张星群
何权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XINSHIJI ENERGY ENVIRONMENTAL PROTECTION ENGINEERING Co Ltd HANGZHOU
Original Assignee
XINSHIJI ENERGY ENVIRONMENTAL PROTECTION ENGINEERING Co Ltd HANGZHOU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINSHIJI ENERGY ENVIRONMENTAL PROTECTION ENGINEERING Co Ltd HANGZHOU filed Critical XINSHIJI ENERGY ENVIRONMENTAL PROTECTION ENGINEERING Co Ltd HANGZHOU
Priority to CN201320529382.8U priority Critical patent/CN203517866U/en
Application granted granted Critical
Publication of CN203517866U publication Critical patent/CN203517866U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a waste heat boiler with a novel water wall roof tube through-wall structure. According to the waste heat boiler with the novel water wall roof tube through-wall structure, a partition water wall connecting tube and a partition header can be reliably communicated, sealing performance and the rigidity of roof tubes can be effectively ensured, the structure is simple, and maintenance is convenient. According to the technical scheme, the waste heat boiler with the novel water wall roof tube through-wall structure comprises a flue gas pass composed of three perpendicular membrane type water wall channels and a perpendicular flue, wherein a water wall roof is arranged at the top ends of the water wall channels and the top end of the flue gas pass; according to the three water wall channels, a partition water wall is arranged between the first water wall channel and the second water wall channel; the top of a water wall tube is communicated with the partition header which is horizontally arranged. The waste heat boiler with the novel water wall roof tube through-wall structure is characterized in that a plurality of pairs of through holes are formed in the side walls on the two sides of the partition header, and are matched with the outer diameter of the roof tubes, the roof tubes penetrate through the through holes respectively in a one-to-one insertion and locating mode, and the positions of joints between the roof tubes and the through holes are sealed in a welding mode.

Description

The waste heat boiler with Novel water cooling wall roof tube structure through walls
Technical field
The utility model relates to a kind of waste heat boiler, specifically disposes the waste heat boiler of Novel water cooling wall roof tube structure through walls.
Background technology
Boiler is as a kind of heat-exchange apparatus, during work, must under subnormal ambient, move and possess good sealing property, otherwise boiler internal is very easy to suck extraneous air, thereby under the effect of crossing of hot and cold air, produce that exhaust gas volumn in the burn into stove of water-cooling wall increases, system power load strengthens and the problem such as combustion conditions variation, even also can reveal because malleation in stove causes flue gas, cause serious environmental pollution accident.
Existing boiler furnace structure (as shown in Figure 5), not only comprise the outer wall water-flow circuit being formed by roof tube 2, roof tube header 5, also be provided with independent internal water closed circuit, comprise partition wall water-cooling wall 4, be positioned at the partition wall header 1 of roof tube 2 tops and the water-cooling wall tube connector 3 that connects partition wall water-cooling wall and partition wall header; The high-temperature flue gas producing during boiler work is respectively by discharging from outlet after the first flue 6, the second flue 7, the 3rd flue 8, the 4th flue 9.
In the junction of roof tube and partition wall water-cooling wall tube connector, roof tube is necessary for partition wall water-cooling wall tube connector allows pipe (shape that inclination is bent upwards) can vertically pass through roof tube to guarantee partition wall water-cooling wall tube connector.For solving the problem of pipe position seal failure and roof tube stiffness degradation of allowing, must allow pipe position add seal closure and use girder steel 10 to support roof tubes.
But said structure is comparatively complicated, design, construction and maintenance all have more highly difficult, therefore need further solution.
Utility model content
The purpose of this utility model is the deficiency overcoming in above-mentioned background technology, the waste heat boiler of a kind of Novel water cooling wall roof tube structure through walls is provided, when the water-cooling wall roof tube structure in this waste heat boiler should be able to make partition wall water-cooling wall tube connector and partition wall header reliable connected, effectively guarantee roof tube sealing and rigidity, and simple in structure, easy to maintenance.
The technical scheme that the utility model provides is: the waste heat boiler with Novel water cooling wall roof tube structure through walls, comprise three vertical fin panel casing passages and a flue gas flow channel that vertical gas pass forms, the top of water-cooling wall passage and flue gas flow channel is the water-cooling wall ceiling that a plurality of roof tubes that are arranged parallel to each other form; In described three water-cooling wall passages, between first passage and second channel, be vertically to arrange by a plurality of water screen tubes the partition wall water-cooling wall forming; The top of water screen tube also communicates with horizontally disposed partition wall header by several water-cooling wall tube connectors that up stretch; It is characterized in that: on the both sides sidewall of described partition wall header, be shaped with the multipair and matched through hole of roof tube external diameter, described a plurality of roof tubes intert one by one respectively and are positioned in above-mentioned through hole, the equal welded seal of the seam areas of roof tube and through hole.
The axis of described partition wall header is substantially vertical with the axis of roof tube.
The beneficial effects of the utility model are:
The utility model is by being arranged on partition wall header and roof tube in same plane, allow partition wall header directly wear and be positioned on roof tube, can not only make like this partition wall water-cooling wall and roof tube still as two independent water-flow circuits, sealing property and the intensity that can also keep roof tube simultaneously, without adding seal closure and buckstay, thoroughly solved roof tube because allowing seal failure problem that pipe causes and the problem of stiffness degradation; In addition, of the present utility model relatively simple for structure, construction is all more convenient with maintenance.
Accompanying drawing explanation
Fig. 1 is main TV structure schematic diagram of the present utility model (the B portion structure for amplifying schematic diagram of Fig. 5).
Fig. 2 is the structure for amplifying schematic diagram of A portion in Fig. 1.
Fig. 3 is the plan structure schematic diagram of Fig. 2.
Fig. 4 is the main TV structure schematic diagram of existing structure through walls.
Fig. 5 is the structural representation of incinerator waste heat boiler.
The specific embodiment
Below in conjunction with Figure of description, the utility model is described in further detail, but the utility model is not limited to following examples.
Embodiment shown in Fig. 5 is the heat exchange section structural representation (waste incineration wherein is partly omitted) of incinerator waste heat boiler; Comprise three vertical fin panel casing passages (comprising the first flue 6, the second flue 7, the 3rd flue 8) and a flue gas flow channel (the 4th flue 9) that vertical gas pass forms, the top of water-cooling wall passage and flue gas flow channel is the water-cooling wall ceiling that a plurality of roof tubes that are arranged parallel to each other 2 form; Described three water-cooling wall passages form (each partition wall water-cooling wall is arranged and formed by a plurality of vertical water screen tubes) by 2 partition wall water-cooling wall intervals, the water screen tube in the partition wall water-cooling wall 4 between first passage and second channel wherein, also the several water-cooling wall tube connectors 3 that up stretch by top communicate with horizontally disposed partition wall header 1.The high temperature carbonated drink product producing in partition wall water-cooling wall is flowed in partition wall header and is formed internal water closed circuit by water-cooling wall tube connector; The high-temperature steam producing in roof tube flows in roof tube header and forms outer wall water-flow circuit; The axis of roof tube is basically perpendicular to the axis of partition wall header; In addition, shape α at a certain angle (as shown in Figure 2) between roof tube and horizontal plane, this angle is generally 2-10 degree.
Improvements of the present utility model are:
Partition wall header is moved down, and on the sidewall of both sides, be shaped with multipair through hole 1-1, the external diameter fit of the internal diameter of through hole and roof tube, a plurality of roof tubes intert respectively one by one in above-mentioned through hole; For guaranteeing the sealing of partition wall header, the equal welded seal of seam areas of roof tube and through hole.Therefore, the utility model is guaranteeing that two water-flow circuits are still independent operating in the situation that, not only improved the rigidity of roof tube, reinforcement material and operating expenses (without using girder steel, reinforcing) have been saved, and guaranteed the sealing property of roof tube, also without adding seal closure, avoided managing because roof tube allows the series of problems causing, obtained reasonable effect.
The operation principle of this embodiment is: the flue gas producing after the waste incineration on fire grate, tube connector (being furnished with the gap that allows flue gas to pass through between tube connector) by the first flue 6 outlets directly enters the second flue 7, through the separation of heat exchange and flying dust, the ash bucket of cooling flue gas through the second flue bottom enters the 3rd flue 8; In third channel, arranged successively convection current evaporimeter, high temperature superheater, medium temperature overheater and low temperature superheater, flue gas enters the 4th flue on the 3rd flue top, by discharging after the economizer in four-way and smoke air preheater.The saturated vapor of separating in each heat-exchanger rig enters Turbo-generator Set successively and generates electricity after low temperature superheater, medium temperature overheater, high temperature superheater.

Claims (2)

1. the waste heat boiler with Novel water cooling wall roof tube structure through walls, comprise three vertical fin panel casing passages and a flue gas flow channel that vertical gas pass forms, the top of water-cooling wall passage and flue gas flow channel is the water-cooling wall ceiling that a plurality of roof tubes that are arranged parallel to each other form; In described three water-cooling wall passages, between first passage (6) and second channel (7), be vertically to arrange by a plurality of water screen tubes the partition wall water-cooling wall (4) forming; The top of water screen tube also communicates with horizontally disposed partition wall header (1) by several water-cooling wall tube connectors (3) that up stretch; It is characterized in that: on the both sides sidewall of described partition wall header, be shaped with the multipair and matched through hole of roof tube external diameter (1-1), described a plurality of roof tubes intert one by one respectively and are positioned in above-mentioned through hole, the equal welded seal of the seam areas of roof tube and through hole.
2. the waste heat boiler with Novel water cooling wall roof tube structure through walls according to claim 1, is characterized in that: the axis of described partition wall header is substantially vertical with the axis of roof tube.
CN201320529382.8U 2013-08-15 2013-08-28 Waste heat boiler with novel water wall roof tube through-wall structure Expired - Lifetime CN203517866U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320529382.8U CN203517866U (en) 2013-08-15 2013-08-28 Waste heat boiler with novel water wall roof tube through-wall structure

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201320499364 2013-08-15
CN201320499364.X 2013-08-15
CN201320529382.8U CN203517866U (en) 2013-08-15 2013-08-28 Waste heat boiler with novel water wall roof tube through-wall structure

Publications (1)

Publication Number Publication Date
CN203517866U true CN203517866U (en) 2014-04-02

Family

ID=50376795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320529382.8U Expired - Lifetime CN203517866U (en) 2013-08-15 2013-08-28 Waste heat boiler with novel water wall roof tube through-wall structure

Country Status (1)

Country Link
CN (1) CN203517866U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105890159A (en) * 2016-05-10 2016-08-24 北京热华能源科技有限公司 Hot water circulation structure with built-in communicating pipes and multi-path circulating fluidized bed hot water boiler
CN108151055A (en) * 2017-11-08 2018-06-12 上海锅炉厂有限公司 A kind of partition wall positioning device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105890159A (en) * 2016-05-10 2016-08-24 北京热华能源科技有限公司 Hot water circulation structure with built-in communicating pipes and multi-path circulating fluidized bed hot water boiler
CN105890159B (en) * 2016-05-10 2018-08-21 北京热华能源科技有限公司 The hot water circuit structure of built-in communicating pipe and multipath circulating fluidized bed hot-water boiler
CN108151055A (en) * 2017-11-08 2018-06-12 上海锅炉厂有限公司 A kind of partition wall positioning device
CN108151055B (en) * 2017-11-08 2023-11-03 上海锅炉厂有限公司 Partition wall positioner

Similar Documents

Publication Publication Date Title
CN205403139U (en) Low nitrogen buggy boiler
CN103912893B (en) The boiler water wall protective device of anti-coking high temperature corrosion resistance
CN105042622A (en) Air preheater based one air-water heat exchange
CN104359098A (en) Three-return-stroke powder heat conduction oil boiler
CN203517866U (en) Waste heat boiler with novel water wall roof tube through-wall structure
CN204830454U (en) Many return strokes living beings hot -blast furnace
CN102679538A (en) Smoke and water counterflow split type efficient heating boiler
CN103542518A (en) Biomass double-heat-exchange reversal burning type hot-air furnace
CN208886739U (en) The low nitrogen vapor boiler of full premix combustion
CN204301027U (en) Verticle coal-burning stem boiler
CN110822402A (en) Horizontal gas corner tube boiler
CN103047638B (en) Horizontal type two-channel pulverized coal fired boiler
CN202403247U (en) Corner-tube waste heat boiler
CN212746547U (en) Combustible gas preheating device
CN112628724B (en) Industrial pulverized coal boiler with double horizontal hearths arranged in opposite flushing mode
RU2315918C2 (en) Steel sectional water-heating boiler disassembled from the front
CN204328984U (en) The hybrid radiant boiler of a kind of revolution shape
CN203550637U (en) Plate-type preheating device for aluminum-fusing shaft furnace
CN104677152B (en) Plate type air-air heat exchanger
CN203949146U (en) Combined screw thread pipe boiler
CN207907720U (en) A kind of electric-furnace exhaust heat boiler with Z-type heat exchanger tube
CN205102403U (en) Three -return -stroke powder heat conduction oil boiler
CN206320785U (en) Forced circulation burning coal powder hot-water boiler
CN205227289U (en) Cooler waste gas waste heat over heater who knows to cement plant kiln hood
CN205535709U (en) Flue waste heat utilization system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140402