CN203515454U - Quick hole packer - Google Patents
Quick hole packer Download PDFInfo
- Publication number
- CN203515454U CN203515454U CN201320612394.7U CN201320612394U CN203515454U CN 203515454 U CN203515454 U CN 203515454U CN 201320612394 U CN201320612394 U CN 201320612394U CN 203515454 U CN203515454 U CN 203515454U
- Authority
- CN
- China
- Prior art keywords
- capsule
- pipe
- gas
- hole
- hole packer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002775 capsule Substances 0.000 claims abstract description 49
- 238000007789 sealing Methods 0.000 claims description 31
- 238000005259 measurement Methods 0.000 claims description 12
- 238000003032 molecular docking Methods 0.000 claims description 6
- 238000012856 packing Methods 0.000 abstract 5
- 210000001503 joint Anatomy 0.000 abstract 1
- 239000003245 coal Substances 0.000 description 7
- 238000012360 testing method Methods 0.000 description 7
- 238000000605 extraction Methods 0.000 description 6
- 238000005553 drilling Methods 0.000 description 2
- 238000004140 cleaning Methods 0.000 description 1
- 239000002817 coal dust Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000008034 disappearance Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003063 flame retardant Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
Images
Landscapes
- Sampling And Sample Adjustment (AREA)
Abstract
The utility model discloses a quick hole packer which comprises a measuring chamber pipe, a capsule hole packing pipe and an air guiding pipe, wherein the measuring chamber pipe, the capsule hole packing pipe and the air guiding pipe are sequentially connected in a butt joint mode. An expansion capsule is wound on the outer circle of a pipe surrounding the capsule hole packing pipe, the two end openings of the expansion capsule are fixed on the two sides of the capsule hole packing pipe in a sealed mode respectively, and the expansion capsule is connected with an inflation pipe. The quick hole packer is simple in structure, quick in operation and good in hole packing effect.
Description
Technical field
The utility model belongs to mine gas prevention and control field, is specifically related to a kind of rapid hole packer for gas testing bore holes and interim extraction borehole.
Background technology
Coal and Gas Outburst are one of natural calamities the most serious under coal mine, and Accurate Prediction coal and Gas Outburst have important function to control coal and Gas Outburst.Drilling gas is gushed out initial velocity as one of important indicator of forecasting coal and Gas Outburst, and the agility of the rapid hole packer operation that it adopts, the quality of sealing of hole effect directly affect measurement result.
In addition, when the interim extraction of coal-bed gas, the quality of the agility of rapid hole packer and sealing of hole effect also affects extracting result.Therefore, a kind of novel rapid hole packer for gas testing bore holes and interim extraction borehole swift to operate, that sealing of hole is effective of design invention is significant.
Utility model content
The purpose of this utility model is to provide the rapid hole packer that a kind of result is simple, swift to operate, sealing of hole is effective.
For achieving the above object, the utility model adopts following technical scheme: rapid hole packer, the measurement chamber pipe, capsule hole sealing tube and the wireway that comprise docking successively, pipe outer ring around capsule hole sealing tube is wound with expanded capsule, the two-port of expanded capsule is sealingly fastened in respectively the both sides of capsule hole sealing tube, and expanded capsule is connected with gas tube.
Described gas tube is provided with pressure meter, and the end of gas tube connects source of the gas.
Described source of the gas is inflator.
Described source of the gas is down-hole air line.
The shutoff of measurement chamber pipe one end, the other end connect described capsule hole sealing tube, and the pipe shaft of measurement chamber pipe is provided with several air vents.
Described wireway arranges several, and several wireways are for docking by snap joint between docking and adjacent two wireways successively.
Rapid hole packer described in the utility model, rapid hole sealing that can be to gas testing bore holes and interim extraction borehole, the utility model is simple in structure, simple and quick, sealing of hole good sealing effect, can derive fast gas in coal seam.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
The specific embodiment
Rapid hole packer as shown in Figure 1, comprise the measurement chamber pipe 10, capsule hole sealing tube 9 and the wireway 6 that dock successively from front to back, wireway 6 arranges several, several wireways 6 dock successively for front and back, and by snap joint 7, dock (snap joint 7 is prior art, therefore do not describe in detail) between adjacent two wireways 6.Measurement chamber pipe 10 front end sealings, rear end connect described capsule hole sealing tube 9, the pipe shaft of measurement chamber pipe 10 is provided with several air vents 1, the rear port of measurement chamber pipe 10 docks with the front port of capsule hole sealing tube 9, the rear port of capsule hole sealing tube 9 docks with the front port of first wireway 6, and the rear port of last wireway 6 is by joint 8 connecting test sebific duct or drainage tubes.Gas can enter by air vent 1 capsule hole sealing tube 9 and each wireway 6 of hole packer, finally enter test sebific duct or drainage tube, wherein wireway 6 quantity are determined according to hole depth, can constantly increase wireway 6 by connecting snap joint 7, to increase the overall length of wireway 6.
Pipe outer ring around capsule hole sealing tube 9 is wound with expanded capsule 2, and expanded capsule 2 has the features such as antistatic, fire-retardant, durable.The forward and backward two-port of expanded capsule 2 is sealingly fastened in respectively the both sides, front and back of capsule hole sealing tube 9, the front port of expanded capsule 2 and rear port can be fixed on respectively the both sides of capsule hole sealing tube 9 by two clip sealings, expanded capsule 2 is connected with gas tube 3, described gas tube 3 is provided with pressure meter 4, one end of gas tube 3 connects expanded capsule 2, the other end connects source of the gas, and source of the gas is inflator 5.Expanded capsule 2 is harmomegathus structure, because expanded capsule 2 two-port are closed in the both sides of capsule hole sealing tube 9, between expanded capsule 2 and capsule hole sealing tube 9, form airtight inflatable chamber, when source of the gas is filled with gas between expanded capsule 2 and capsule hole sealing tube 9, expanded capsule 2 bulges and blocks up real boring, and pressure meter 4 can show the pressure value in gas tube 3 and capsule.
Certainly, the utility model is not limited to above-mentioned form, and described source of the gas also can be down-hole air line.
Rapid hole packer described in the utility model, utilizes expanded capsule 2 to expand and blocks up real boring, and the principle that in coal seam, gas is discharged by the air guide channel in pipeline is carried out rapid hole sealing.
The using method of rapid hole packer described in the utility model is:
1. prepare the wireway 6 of each parts of hole packer and enough joint numbers, check in fast joint, whether O type circle has breakage, as found disappearance or can not normally using, should change in time;
2. after drilling construction completes, connect successively measurement chamber pipe 10, capsule hole sealing tube 9, gas tube 3, and by fast joint, connect the wireway 6 of enough joint numbers;
3. use inflator 5 or other compressed air source unit to the interior inflation of expanded capsule 2 on capsule hole sealing tube 9, until pressure meter 4 shows that numerical value are to precalculated position (assurance can not outwards be stirred with hand);
4. by snap joint 7 by the rear port connecting test device of tail end wireway 6 or extraction pipeline, test or extraction;
5. after measuring, pull out connecting line in snap joint 7, discharge the gas in expanded capsule 2 simultaneously, hole packer is extracted, coal dust installing in order to using next time on cleaning hole packer.
Claims (6)
1. a rapid hole packer, it is characterized in that: the measurement chamber pipe, capsule hole sealing tube and the wireway that comprise docking successively, pipe outer ring around capsule hole sealing tube is wound with expanded capsule, and the two-port of expanded capsule is sealingly fastened in respectively the both sides of capsule hole sealing tube, and expanded capsule is connected with gas tube.
2. rapid hole packer as claimed in claim 1, is characterized in that: described gas tube is provided with pressure meter, and the end of gas tube connects source of the gas.
3. rapid hole packer as claimed in claim 2, is characterized in that: described source of the gas is inflator.
4. rapid hole packer as claimed in claim 2, is characterized in that: described source of the gas is down-hole air line.
5. rapid hole packer as claimed in claim 1, is characterized in that: the shutoff of measurement chamber pipe one end, the other end connect described capsule hole sealing tube, and the pipe shaft of measurement chamber pipe is provided with several air vents.
6. rapid hole packer as claimed in claim 1, is characterized in that: described wireway arranges several, and several wireways are for docking by snap joint between docking and adjacent two wireways successively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320612394.7U CN203515454U (en) | 2013-09-30 | 2013-09-30 | Quick hole packer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320612394.7U CN203515454U (en) | 2013-09-30 | 2013-09-30 | Quick hole packer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203515454U true CN203515454U (en) | 2014-04-02 |
Family
ID=50374401
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320612394.7U Expired - Fee Related CN203515454U (en) | 2013-09-30 | 2013-09-30 | Quick hole packer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203515454U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104847303A (en) * | 2015-05-19 | 2015-08-19 | 安徽佳泰矿业科技有限公司 | Quick injection type hole sealing device and method for applying same |
-
2013
- 2013-09-30 CN CN201320612394.7U patent/CN203515454U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104847303A (en) * | 2015-05-19 | 2015-08-19 | 安徽佳泰矿业科技有限公司 | Quick injection type hole sealing device and method for applying same |
CN104847303B (en) * | 2015-05-19 | 2018-01-09 | 安徽佳泰矿业科技有限公司 | Fast injection formula hole packer and its application method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107605461B (en) | Observation method of mine rock mass drilling gas plugging and extraction integrated system | |
CN107829723B (en) | Mine rock mass mining damage range integrated detection equipment and detection method | |
CN107191165A (en) | Both-end blocks water filling device in hole | |
CN111022030A (en) | Device and method for measuring coal seam gas content based on flow method | |
CN103510943A (en) | Instrument for measuring initial velocity of gas discharged from deep drill hole for coal mine outburst prediction | |
CN104179491A (en) | Ultrasonic detecting device and system for downhole rock fracture drilling | |
CN104764625A (en) | Low-temperature coal seam sampling device and method | |
CN203515454U (en) | Quick hole packer | |
CN203655265U (en) | Gun drilling gas emission initial speed tester for outburst forecast of coal mine | |
CN107642354B (en) | Method for measuring length of drill hole after drill rod exits from drill hole | |
CN103398733B (en) | Anti-blocking pressure-leading probe of wind speed and wind direction detection device | |
CN109162703B (en) | Super-long soft coal seam drilling multi-stage pressure sealing pressure measuring device and method | |
CN104100293B (en) | Gas extraction drilling leak detection and leakage stoppage integrated device and method | |
CN204200238U (en) | A kind of Novel down-hole height of water flowing fractured zone observation probe of real-time probing | |
CN204082135U (en) | Extraction borehole sealing quality detector | |
CN108693069B (en) | Drilling coal dust gas desorption characteristic parameter measurement while drilling device | |
CN204314282U (en) | Detect the experimental provision of gas discharge drilling sealing material sealing property | |
CN110778308A (en) | Device and method for testing gas flow while drilling | |
CN107859500B (en) | Mine rock drilling anti-reflection type gas plugging unit and measuring system | |
CN113984627B (en) | Rock stratum permeability testing device | |
CN211573597U (en) | Gas emission initial velocity measuring device with fixed hole sealing length | |
CN104278983A (en) | Coupling device for sound-wave all-around testing dry hole probe | |
CN204495593U (en) | A kind of coal seam low temperature sampler | |
CN211851811U (en) | Device based on flow method survey coal seam gas content | |
CN208224248U (en) | Firedamp testing device with quick coupling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140402 |