CN203464308U - Multi-tube accelerated flue gas desulfurization device - Google Patents

Multi-tube accelerated flue gas desulfurization device Download PDF

Info

Publication number
CN203464308U
CN203464308U CN201320505071.8U CN201320505071U CN203464308U CN 203464308 U CN203464308 U CN 203464308U CN 201320505071 U CN201320505071 U CN 201320505071U CN 203464308 U CN203464308 U CN 203464308U
Authority
CN
China
Prior art keywords
reaction tower
desulfurization reaction
flue gas
flue
desulfurization
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320505071.8U
Other languages
Chinese (zh)
Inventor
蓝庆辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Xinren Environmental Protection Technology Co ltd
Original Assignee
JIANGSU NEW ENVIRONMENTAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU NEW ENVIRONMENTAL CO Ltd filed Critical JIANGSU NEW ENVIRONMENTAL CO Ltd
Priority to CN201320505071.8U priority Critical patent/CN203464308U/en
Application granted granted Critical
Publication of CN203464308U publication Critical patent/CN203464308U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a multi-tube accelerated flue gas desulfurization device. The multi-tube accelerated flue gas desulfurization device comprises a coal-fired boiler, a desulfurization reaction tower, a dust remover and a chimney, wherein a flue gas outlet and a flue gas inlet are respectively formed in the upper and lower sidewalls of the desulfurization reaction tower; the coal-fired boiler is communicated with the desulfurization reaction tower through a flue which is communicated with the flue gas inlet in the lower side of the desulfurization reaction tower, the desulfurization reaction tower is communicated with the dust remover through a flue which is communicated with the flue gas outlet in the upper side of the desulfurization reaction tower, the dust remover is communicated with the chimney through a flue, a transverse bracket is transversely arranged in the desulfurization reaction tower between the flue gas outlet and the flue gas inlet, at least five Venturi tube groups are uniformly distributed on the transverse bracket, each Venturi tube group at least comprises five Venturi tubes, a spraying pipe is arranged in the desulfurization reaction tower above the Venturi tubes, one end of the spraying pipe is closed, the other end of the spraying pipe extends out of the desulfurization reaction tower and is communicated with a desulfurizer preparation tower, and a plurality of spraying mouths with downward spray openings are formed in the spraying pipe. The multi-tube accelerated flue gas desulfurization device has the advantage of high desulfurization efficiency.

Description

A kind of multitube accelerates flue gas desulfur device
Technical field
The utility model relates to waste gas purification field, is specifically related to a kind of multitube and accelerates flue gas desulfur device.
Background technology
Coal-burning boiler in use can continue to produce sulfur-containing smoke gas, therefore all sulfur-containing smoke gas will be carried out to desulfurization by flue gas desulfur device, the structure of the flue gas desulfur device using is at present: comprise coal-burning boiler, desulfurization reaction tower, deduster, chimney, coal-burning boiler is connected with desulfurization reaction tower downside by flue, desulfurization reaction tower is connected with deduster by flue, and deduster is connected with chimney by flue, and in desulfurization reaction tower, upper strata is provided with desulfurizing agent spray equipment.The shortcoming of this flue gas desulfur device is: the gas flow rate that enters desulfurization reaction tower due to sulfur-containing smoke gas is fast, and the easy like this sulfur-containing smoke gas that causes is short with the time of contact of the desulfurizing agent spraying from desulfurizing agent spray equipment, and desulfuration efficiency is low.
Utility model content
The purpose of this utility model is to provide a kind of multitube that a kind of desulfuration efficiency is high and accelerates flue gas desulfur device.
For achieving the above object, the utility model has adopted following technical scheme: described a kind of multitube accelerates flue gas desulfur device, comprising: coal-burning boiler, is respectively arranged with outlet flue and the desulfurization reaction tower that enters mouth, deduster and chimney on upper and lower two side, coal-burning boiler is by being connected with desulfurization reaction tower with the flue that mouth is connected that enters of desulfurization reaction tower downside, desulfurization reaction tower is connected with deduster by the flue being connected with the outlet flue of its upside, deduster is connected with chimney by flue, at outlet flue and enter in the desulfurization reaction tower between mouth to be horizontally arranged with horizontal support, on horizontal support, be evenly distributed with at least five group Venturi tube groups, every group of Venturi tube group at least comprises five Venturi tubes, in desulfurization reaction tower above Venturi tube, be provided with shower, one end sealing of shower, the other end stretches out desulfurization reaction tower to be prepared tower with desulfurizing agent and is connected, on shower, offer some spouts mouth spray down.
Further, aforesaid a kind of multitube accelerates flue gas desulfur device, wherein: described mouth spray flare opening arranges.
By the enforcement of technique scheme, the beneficial effects of the utility model are: the gas velocity of sulfur-containing smoke gas after Venturi tube can reduce, thereby increased the gas-liquid contact time of sulfur-containing smoke gas and desulfurizing agent, make fully haptoreaction of sulfur-containing smoke gas and desulfurizing agent, thereby improved desulfuration efficiency.
Accompanying drawing explanation
Fig. 1 is the operation principle schematic diagram that a kind of multitube described in the utility model accelerates flue gas desulfur device.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As shown in Figure 1, described a kind of multitube accelerates flue gas desulfur device, comprising: coal-burning boiler 1, is respectively arranged with outlet flue and the desulfurization reaction tower 2 that enters mouth, deduster 3 and chimney 4 on upper and lower two side, coal-burning boiler 1 is connected with desulfurization reaction tower 1 by the first flue 5 being connected with 2 times side smoke inlets of desulfurization reaction tower, desulfurization reaction tower 2 is connected with deduster 3 by the second flue 6 being connected with its upside outlet flue, deduster 3 is connected with chimney 4 by the 3rd flue 7, at outlet flue and enter in the desulfurization reaction tower 2 between mouth to be horizontally arranged with horizontal support 8, on horizontal support 8, be evenly distributed with at least five group Venturi tube groups, every group of Venturi tube group at least comprises five Venturi tubes 9, in desulfurization reaction tower 2 above Venturi tube 9, be provided with shower 10, one end sealing of shower 10, the other end stretches out desulfurization reaction tower 2 to be prepared tower 11 with desulfurizing agent and is connected, on shower 10, offer some spouts mouth spray 12 down, like this when sulfur-containing smoke gas is through being uniformly distributed in after a plurality of Venturi tubes 9 on horizontal support 8, the gas velocity of sulfur-containing smoke gas can reduce, and then increased the gas-liquid contact time of sulfur-containing smoke gas and desulfurizing agent, make fully haptoreaction of desulfurizing agent and sulfur-containing smoke gas, thereby improved desulfuration efficiency.In the present embodiment, described mouth spray 12 flare openings arrange, and can make like this desulfurizing agent can fully contact with sulfur-containing smoke gas, have improved desulfuration efficiency.In actual applications, the quantity of described Venturi tube group can arrange according to the concentration of sulfur-containing smoke gas and gas velocity.
Below be only concrete exemplary applications of the present utility model, protection domain of the present utility model is not constituted any limitation.In addition to the implementation, the utility model can also have other embodiment.All employings are equal to the technical scheme of replacement or equivalent transformation formation, within all dropping on the utility model scope required for protection.

Claims (2)

1. multitube accelerates a flue gas desulfur device, comprising: coal-burning boiler, is respectively arranged with outlet flue and the desulfurization reaction tower that enters mouth, deduster and chimney on upper and lower two side, coal-burning boiler is by being connected with desulfurization reaction tower with the flue that mouth is connected that enters of desulfurization reaction tower downside, desulfurization reaction tower is connected with deduster by the flue being connected with the outlet flue of its upside, deduster is connected with chimney by flue, it is characterized in that: at outlet flue and enter in the desulfurization reaction tower between mouth to be horizontally arranged with horizontal support, on horizontal support, be evenly distributed with at least five group Venturi tube groups, every group of Venturi tube group at least comprises five Venturi tubes, in desulfurization reaction tower above Venturi tube, be provided with shower, one end sealing of shower, the other end stretches out desulfurization reaction tower to be prepared tower with desulfurizing agent and is connected, on shower, offer some spouts mouth spray down.
2. a kind of multitube according to claim 1 accelerates flue gas desulfur device, it is characterized in that: described mouth spray flare opening arranges.
CN201320505071.8U 2013-08-19 2013-08-19 Multi-tube accelerated flue gas desulfurization device Expired - Fee Related CN203464308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320505071.8U CN203464308U (en) 2013-08-19 2013-08-19 Multi-tube accelerated flue gas desulfurization device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320505071.8U CN203464308U (en) 2013-08-19 2013-08-19 Multi-tube accelerated flue gas desulfurization device

Publications (1)

Publication Number Publication Date
CN203464308U true CN203464308U (en) 2014-03-05

Family

ID=50176672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320505071.8U Expired - Fee Related CN203464308U (en) 2013-08-19 2013-08-19 Multi-tube accelerated flue gas desulfurization device

Country Status (1)

Country Link
CN (1) CN203464308U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103423758A (en) * 2013-08-19 2013-12-04 江苏新中环保股份有限公司 Multitube acceleration smoke desulfurizer

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103423758A (en) * 2013-08-19 2013-12-04 江苏新中环保股份有限公司 Multitube acceleration smoke desulfurizer

Similar Documents

Publication Publication Date Title
CN203971653U (en) A kind of gas-liquid reallocation and subparticle capturing device that is applicable to single tower double circulation desulphurization tower
CN210645841U (en) Desulfurizing tower system in coal-fired boiler flue gas desulfurization system
CN204911221U (en) Unequal venturi in convergent flaring angle restraints and CFB absorption tower thereof
CN203464308U (en) Multi-tube accelerated flue gas desulfurization device
CN203836993U (en) Dedusting flue
CN204147762U (en) A kind of circulating fluid bed flue-gas desulfurizing device adopting special-shaped many venturi
CN203842496U (en) Semi-dry-process desulfurization tower of novel circulating fluidized bed
CN203803362U (en) Efficient transmission layer desulfurization device in desulfurization absorption tower
CN103423758A (en) Multitube acceleration smoke desulfurizer
CN106512705A (en) Biological desulfurization device for flue gas
CN205308135U (en) Can realize series connection, SOx/NOx control system that connects in parallel
CN204261557U (en) A kind of Multi-level deflector formula desulfurizer
CN204320095U (en) A kind of flue gas blender being applied to desulphurization denitration
CN204147707U (en) Drum type gas purifier
CN203002209U (en) Desulfurizing device
CN204121961U (en) A kind of desulfurizer
CN205182486U (en) Alkaline waste water desulfurization desalination device
CN204563921U (en) A kind of oxidation air pipe with non-isometrical qi-emitting hole
CN202778247U (en) Novel flue gas desulfurization device
CN204865488U (en) Ozone uniform distributor
CN203886403U (en) Smoke inlet guiding device of adsorption tower
CN204275740U (en) Combined desulfurizing dust remover
CN203507735U (en) Coal-water slurry boiler dust-removing tower with efficient dust-removing device
CN204294097U (en) A kind of Multistage desulfuration device with filtered fluid purifier
CN204718420U (en) Flue dust cooling-sedimentation system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190108

Address after: 215600 Donglai Jiangqiao, Yangshe Town, Zhangjiagang City, Jiangsu Province (in Zhangjiagang East China Marine Valve Manufacturing Co., Ltd.)

Patentee after: Jiangsu Xinren Environmental Protection Technology Co.,Ltd.

Address before: 215600 Jiangsu Xinzhong Environmental Protection Co., Ltd. Zhangjiagang Economic Development Zone, Suzhou City, Jiangsu Province

Patentee before: JIANGSU NEW ENVIRONMENTAL Corp.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140305