CN203330185U CN2013202491687U CN201320249168U CN203330185U CN 203330185 U CN203330185 U CN 203330185U CN 2013202491687 U CN2013202491687 U CN 2013202491687U CN 201320249168 U CN201320249168 U CN 201320249168U CN 203330185 U CN203330185 U CN 203330185U
Authority
CN
China
Prior art keywords
jack
pipe
auxiliary device
plate
steel pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2013202491687U
Other languages
Chinese (zh)
Inventor
南足刚
方磊
赵保华
陈芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN2013202491687U priority Critical patent/CN203330185U/en
Application granted granted Critical
Publication of CN203330185U publication Critical patent/CN203330185U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model provides an auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing. The auxiliary device comprises an upper half-moon plate and a lower half-moon plate which are vertically arranged in pairs, wherein a lifting jack is installed in the middle of the lower half-moon plate, the lifting jack abuts against the upper half-moon plate through an auxiliary lifting jack circular tube, and the upper half-moon plate and the lower half-moon plate are spliced to be of an integral circular shape. The auxiliary device can resolve the problem of deformation of a large-aperture steel pipeline, and is affordable and convenient to install.

Description

The heavy caliber steel pipe is made ovality and is corrected servicing unit
Technical field
The utility model metallic conduit manufacture field, particularly relate to the heavy caliber steel pipe and make ovality rectification servicing unit.
Background technology
In the making of large-diameter pipeline, the major diameter steel pipe often is difficult to control the circular arc degree of pipeline.Because the steel plate thickness of rolling pipeline is generally sheet metal, after moulding, due to the effect of himself gravity, easily distortion, cause the pipeline circular arc degree of rolling inadequate, and on-the-spot pipeline installation exercise difficulty is strengthened.
Therefore, need to make the servicing unit that a kind of steel conduit is controlled its circular arc degree, for solving the problem on deformation of Large-diameter Steel pipeline, facilitate the workman to install.
Summary of the invention
Technical problem to be solved in the utility model is the technical deficiency over against above-mentioned existence, and a kind of problem on deformation that can solve the Large-diameter Steel pipeline is provided, and economic and practical, and heavy caliber steel pipe easy for installation is made ovality and corrected servicing unit.
The utility model solves the technical scheme that its technical problem adopts:
The heavy caliber steel pipe is made ovality and is corrected servicing unit, it is characterized in that: include two meniscus that arrange in pairs up and down, wherein the centre of lower meniscus is equipped with jack, and jack withstands the plate in first half of the month by auxiliary jack pipe, and upper lower meniscus pieces together complete circle.
In such scheme, be provided with pipe, the nested pipe inside that is arranged on of jack in the middle of described lower meniscus;
In such scheme, between described jack and jack pipe, also be provided with backing plate.
Operation principle of the present utility model is: the major diameter steel pipe is after rolling completes, be placed on smooth place, then load onto gusset along circumference one circle electric welding on inside pipe wall, then withstand plate and lower meniscus in first half of the month with jack, first half of the month, plate and lower meniscus withstood gusset simultaneously, respectively to the top of pipeline and below carry out the radian rectification, until pipeline reaches ideal effect, be dismountable this device, this device can be recycled.
The beneficial effect that the utility model can reach is:
This device can solve the problem on deformation of Large-diameter Steel pipeline, and economic and practical, easy for installation.
The accompanying drawing explanation
Fig. 1 is the utility model embodiment device structural representation;
Fig. 2 is the utility model embodiment plate structure in first half of the month schematic diagram;
Fig. 3 is the utility model embodiment lower meniscus structural representation;
In figure: 1. first half of the month plate; 2. lower meniscus; 3. jack; 4. gusset; 5. jack pipe; 6. pipe; 7. backing plate.
The specific embodiment
Below in conjunction with the specific embodiment, the utility model is further described:
Heavy caliber steel pipe is as shown in Figure 1 made ovality and is corrected servicing unit, include two meniscus that arrange in pairs up and down, wherein the centre of lower meniscus 2 is equipped with jack 3, and jack 3 withstands plate 1 in first half of the month by auxiliary jack pipe 5, and upper lower meniscus pieces together complete circle.
In the present embodiment, be provided with pipe 6, nested pipe 6 inside that are arranged on of jack 3 in the middle of lower meniscus as shown in Figure 32;
In the present embodiment, between described jack 3 and jack pipe 5, also be provided with backing plate 7.
Add man-hour, the major diameter steel pipe is after rolling completes, be placed on smooth place, then load onto gusset 4 along circumference one circle electric welding on inside pipe wall, then withstand plate 1 and lower meniscus 2 in first half of the month with jack 3, first half of the month, plate 1 and lower meniscus 2 withstood gusset 4 simultaneously, respectively to the top of pipeline and below carry out the radian rectification, until pipeline reaches ideal effect, be dismountable this device, this device can be recycled.
Protection domain of the present utility model is not limited to the above embodiments, and obviously, those skilled in the art can carry out various changes and distortion and not break away from scope and spirit of the present utility model the utility model.If these changes and distortion belong in the scope of the utility model claim and equivalent technologies thereof, intention of the present utility model also comprises these changes and is out of shape interior.

Claims (3)

1. the heavy caliber steel pipe is made ovality and is corrected servicing unit, it is characterized in that: include two meniscus that arrange in pairs up and down, wherein the centre of lower meniscus is equipped with jack, and jack withstands the plate in first half of the month by auxiliary jack pipe, and upper lower meniscus pieces together complete circle.
2. heavy caliber steel pipe as claimed in claim 1 is made ovality and is corrected servicing unit, it is characterized in that: be provided with pipe, the nested pipe inside that is arranged on of jack in the middle of described lower meniscus.
3. heavy caliber steel pipe as claimed in claim 1 is made ovality and is corrected servicing unit, it is characterized in that: between described jack and jack pipe, also be provided with backing plate.
CN2013202491687U 2013-05-10 2013-05-10 Auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing Expired - Lifetime CN203330185U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013202491687U CN203330185U (en) 2013-05-10 2013-05-10 Auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013202491687U CN203330185U (en) 2013-05-10 2013-05-10 Auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing

Publications (1)

Publication Number Publication Date
CN203330185U true CN203330185U (en) 2013-12-11

Family

ID=49698886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013202491687U Expired - Lifetime CN203330185U (en) 2013-05-10 2013-05-10 Auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing

Country Status (1)

Country Link
CN (1) CN203330185U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108772440A (en) * 2018-05-28 2018-11-09 台嘉玻璃纤维有限公司 A kind of fabric drum maintenance unit
CN109807201A (en) * 2019-03-21 2019-05-28 洛阳双瑞达特铜有限公司 A kind of irregular set round method of pipe internal diameter circularity
CN111589904A (en) * 2019-12-18 2020-08-28 中国一冶集团有限公司 Large-diameter steel pipe correction butt joint method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108772440A (en) * 2018-05-28 2018-11-09 台嘉玻璃纤维有限公司 A kind of fabric drum maintenance unit
CN109807201A (en) * 2019-03-21 2019-05-28 洛阳双瑞达特铜有限公司 A kind of irregular set round method of pipe internal diameter circularity
CN111589904A (en) * 2019-12-18 2020-08-28 中国一冶集团有限公司 Large-diameter steel pipe correction butt joint method
CN111589904B (en) * 2019-12-18 2022-03-22 中国一冶集团有限公司 Large-diameter steel pipe correction butt joint method

Similar Documents

Publication Publication Date Title
CN203330185U (en) Auxiliary device for ellipticity correcting in large-aperture steel pipeline manufacturing
CN203044588U (en) Fitting-up welding correction device of heavy caliber steel pipes
CN103243905B (en) A kind of reducing arc formwork
CN204800232U (en) A organize frock for tapered head of split
CN204544466U (en) Electrostatic precipitator positive plate auxiliary lifting appliance
CN206966363U (en) A kind of mouth of pipe apparatus for correcting
CN201964063U (en) Reinforced bell-spigot joint steel pipe
CN202441416U (en) Gas drainage pipeline for coal mine
CN102172679A (en) Roundness correcting device for U-shaped stainless steel pipe
CN202763328U (en) Welding deformation control device
CN204242752U (en) For the air chamber that converter transformer vacuumizes
CN202100826U (en) Reinforcing rib supporting device used for large-diameter drain pipes
CN204300567U (en) A kind of Novel ring flange
CN102489968A (en) Flanging welded cylinder manufacturing method
CN204122538U (en) A kind of bearing bending machine
CN203163942U (en) Pressure test tank
CN203764690U (en) Two-wheel flange correcting tooling
CN203079646U (en) Prestressed concrete cylinder pipe (PCCP) heavy-caliber steel cylinder turnover machine
CN204346172U (en) A kind of mineral hot furnace blanking column assembly structure
CN204346173U (en) A kind of welding stock column cap
CN103506435A (en) Method and auxiliary tool for reshaping of cover plate used for transformer transportation
CN202203571U (en) Flange tee
CN203549233U (en) Novel elbow
CN204035270U (en) A kind of stewing device of snakelike companion's hot coil
CN202045214U (en) Device for rounding U-shaped stainless steel tube

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20131211