CN203188369U - Bolt cylinder placing type high-rise block structure assembly combined type unit complex - Google Patents

Bolt cylinder placing type high-rise block structure assembly combined type unit complex Download PDF

Info

Publication number
CN203188369U
CN203188369U CN2013200200494U CN201320020049U CN203188369U CN 203188369 U CN203188369 U CN 203188369U CN 2013200200494 U CN2013200200494 U CN 2013200200494U CN 201320020049 U CN201320020049 U CN 201320020049U CN 203188369 U CN203188369 U CN 203188369U
Authority
CN
China
Prior art keywords
unit combination
floor plates
floor
combination body
block structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2013200200494U
Other languages
Chinese (zh)
Inventor
孙善骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2013200200494U priority Critical patent/CN203188369U/en
Application granted granted Critical
Publication of CN203188369U publication Critical patent/CN203188369U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model discloses a bolt cylinder placing type high-rise block structure assembly combined type unit complex. The bolt cylinder placing type high-rise block structure assembly combined type unit complex mainly comprises unit complex passage floor plates, unit complex throat floor plates, ordinary floor plates, steel structural members, reinforcing bars and concrete or cast steel or other placing materials. The ordinary floor plates or/and a floor structure unit complex or/and the unit complex passage floor plates or/and the unit complex throat floor plates or/and unit complex throat passage floor plates and matched pipelines are adopted, structural bodies of some forms are arranged among the components in a supporting mode, matching installation of socket plugs or butt-welding plugs or bolting plugs arranged on the components is carried out, or installation of other matched structural members is carried out, a body part of a bolt cylinder placing type high-rise block structure assembly combined type unit complex building system is formed, supports can be added to the body part, and pipelines such as accessory pipelines, water and electricity pipelines, ventilation pipelines, air conditioner pipelines, communication pipelines, gas pipelines and television pipelines can be added in the components. The bolt cylinder placing type high-rise block structure assembly combined type unit complex is applicable to matching application in steel structure buildings, reinforced concrete buildings and the like, and the steel structure buildings, the reinforced concrete buildings and ordinary buildings can be rapidly built.

Description

The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula
Technical field
The utility model relates to a kind of building component, it is the packaging combined unit combination body of the how high-rise block structure of a kind of bolt tube placing formula, be mainly used on the various buildings as the critical piece of building, be applicable at the steel work that builds up fast, steel reinforced concrete building and use.
Background technology
The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present invention has been filled up domestic and international building blank, adapted to building newly-built, remove frequent and with the diversified requirement in room, building up steel work, steel reinforced concrete building more quickly more and more becomes the demand in market, along with popularizing of steel construction, steel reinforced concrete building etc., adopts packaging combined form of structure, utilize the unit block Rapid Combination to install, the body plan building more and more becomes the building problem that needs crucial solution scientifically and rationally.In order to address this problem the opening structure unit combination body of inventing with the supporting inventor, floor structure unit combination body, unit combination body passage floor plates, unit combination body throat passage floor plates, the packaging combined building of opening structure, the packaging combined steel construction of modularization, relevant Patent projects such as concrete combination corrosion protection steel construction piece and other combined member, save building materials to greatest extent, the various steel constructions of exploitation and buildings in general are necessary to invent a kind of being suitable for fast, advanced butt welding or tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint.
Summary of the invention
The utility model is to provide the how high-rise block structure of a kind of bolt tube placing formula packaging combined unit combination body, is applicable to supporting application on buildings such as steel work, steel reinforced concrete, can build up steel construction, steel reinforced concrete building and buildings in general more quickly.
The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present utility model is mainly by unit combination body passage floor plates 1, unit combination body throat floor plates 2, common floor plates 3, steel construction piece 4, arrangement of reinforcement 5, concrete or cast steel or other are built material 6, insulation layer 7, unit corner post bolt tube 8, socket joint or butt welding or tie plug 9, floor structure body letter beam 10, floor structure body beam 11, floor structure body secondary beam 12, stair 13, bolt tube 14 is built in the part, supporting keratotic plug tube 15, supporting bolt tube 16, earthworm plate or floor or build ground 17, combination keratotic plug tube group 18 is formed, it mainly contains the employing butt welding of full steel structure or ties or the butt welding of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula that socket joint connects and concrete combination corrosion protection or armored concrete or tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula that socket joint is connected, be mainly the common floor plates 3 of employing or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and the packaging combined unit combination body of the unit combination body throat passage floor plates dispensing unit corner post bolt tube 8 formation how high-rise block structures of bolt tube placing formula; The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula can be installed in supporting keratotic plug tube 15, supporting bolt tube 16, on the combination keratotic plug tube group 18 or and various building structural members or and opening structure unit combination body on, can butt welding or tie or socket joint to the packaging combined unit combination body of another group how high-rise block structure of bolt tube placing formula, the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula can be directly and ground is basic docks or adopt supporting keratotic plug tube 15, supporting bolt tube 16, combination keratotic plug tube group 18 or and various building structural members or and opening structure unit combination body and the butt joint of basis, ground; Unit combination body passage floor plates 1 or and unit combination body throat floor plates 2 or and the inside of unit combination body throat passage floor plates generally be furnished with and transform bascule, inlet channel, pneumatic channel and supporting pipeline etc.; Common floor plates 3 or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and unit combination body throat passage floor plates is permutated and combined as the floor structure body, the structure that adopts some forms be supported in common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and be equipped with in the unit combination body throat passage floor plates with socket joint or butt welding or tie in the supporting pore of plug 9, constitute butt welding of the present invention or tie or the block structure collection of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula that socket joint connects is adorned the main part of assembly, the main part splicing of several block structure collection dress assemblys can be formed combination keratotic plug tube group 18 automatically at the place, diagonal angle, the combination keratotic plug tube group 18 of single-piece can adopt several supporting keratotic plug tubes 15 to constitute, combination keratotic plug tube group 18 is similar with supporting bolt tube 16 main parts, in the part that combination keratotic plug tube is organized 18 supporting bolt tube 16 supporting keratotic plug tubes 15 part can be set and build bolt tube 14, combination keratotic plug tube group 18 and supporting bolt tube 16 supporting keratotic plug tube 15 concretings or cast steel or other are built material 6 and are constituted the structural column main body, be other material that whole concretings maybe can solidify generally speaking, before building, can adopt welding at combination keratotic plug tube group 18 some positions, clip or tie 15 in supporting keratotic plug tube or the assembling slit of 8 formation of unit corner post bolt tube, can organize configuration arrangement of reinforcement 5 in the 18 supporting bolt tube 16 supporting keratotic plug tubes 15 at combination keratotic plug tube as required, ground on the floor structure body can concreting or and adopt earthworm plate or floor or build ground 17 on block structure collection dress assembly, supporting bolt tube 16 can adopt 1/4th pipes, can 2 semicanals, can homogeneous tube and with the 18 corresponding designs of combination keratotic plug tube group, can also accommodation design its inner accessory and interfacing part; Up and down two common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and constitute floor space between the unit combination body throat passage floor plates, and can add upper support betwixt, can also in each parts, add pipelines such as annex, water power, ventilation, air-conditioning, communication, coal gas, TV, arrange and reserve auxiliary equipment as required, all do not do special restriction.
Unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and the passage floor plates of unit combination body throat passage floor plates part mainly by draught fan impeller, arc plate, wind-driven generator, cable, inlet channel, pneumatic channel, air port passage frame door frame, transverse reinforcement truss, truss connector, longitudinal reinforcement truss, insulation layer 7, drainage installing hole, pneumatic channel guide pad, building ventilation system air port, wind power generation plant mounting base etc. are formed up and down.
Unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and the throat floor plates part of unit combination body throat passage floor plates mainly by throat, the arc plate, the longitudinal reinforcement truss, wind-force negative pressure discharger installing hole, air-condition heat exchanger, the drainage installing hole, insulation layer 7, transform bascule, throat's baffle, air port passage frame door frame, access door, heat-conducting plate, the transverse reinforcement truss, truss connector up and down, regenerator, wind-force negative pressure discharger 12 compositions such as grade.
Unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and throat's passage floor plates of unit combination body throat passage floor plates partly is above-mentioned throat floor plates part and passage floor plates synthesis partly.
The arc plate is generally with metal or and steel-wire-net reinforced concrete is made and and transverse reinforcement truss, truss connector, being integral of longitudinal reinforcement truss-like up and down.
To sum up, the principal character of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present utility model is: block structure collect dress assembly or common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and be furnished with unit corner post bolt tube 8 on the unit combination body throat passage floor plates; Block structure collect dress assembly or common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and socket joint or the butt welding on be combined keratotic plug tube 18 or supporting bolt tube 16 or the supporting keratotic plug tube 15 arranged on the unit combination body throat passage floor plates or ties the pore that plug 9 butt joints tie, the pore assembling is gone up combination keratotic plug tube 18 or supporting bolt tube 16 concretings or cast steel or other and is built material 6 and be combined into the floor structure body; Combination keratotic plug tube 18 or supporting bolt tube 16 or supporting keratotic plug tube 15 or other structure are supported in up and down socket joint or the butt welding that is equipped with in two floor structure bodies or tie in the plug 9 supporting pores, and the block structure collection that constitutes the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula is adorned assembly; Block structure collect dress assembly or common floor plates 3 or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and the internal placement of unit combination body throat passage floor plates has supporting annex, pipeline.
When unit corner post bolt tube 8 or combination keratotic plug tube 18 or supporting bolt tube 16 or supporting keratotic plug tube 15 or other structure adopt socket joint or butt welding or tie plug 9 connections, if make socket joint head connection request joint a wedge degree, slitless connection to be arranged; If making butt welding connection request joint will have a wedge degree, the seam butt joint is arranged, there is seam to be the soldered of reservation; If do tying the connection request joint wedge degree, slitless connection will be arranged, require to be reserved with bolt hole at suitable position on it, tie the hold-doun nut that can dispose connecting bolt in addition, can not need prepared screw-bolt hole if adopt self-drilling screw to connect; The butt welding of concrete combination corrosion protection or armored concrete or tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint is that usefulness steel construction piece 4 is or/and arrangement of reinforcement 5, concrete or cast steel or other are built material 6, beam body junction plate, part steel construction piece in the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula in assemblys such as the Liang Tixin pipe replacement full steel structure, if require the main part of floor structure body beam 11 hollow, also can install Liang Tixin pipe fluid concrete or cast steel additional or other builds material 6, floor structure body secondary beam 12 also can be made the main part of the floor structure body secondary beam 12 of concrete combination corrosion protection steel construction piece or armored concrete spare with reference to the main part of floor structure body beam 11, mainly adopts the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula that has just constituted concrete combination corrosion protection or armored concrete after the assembly manufacturing of above-mentioned making; Steel construction piece 4 in the floor structure body beam 11 is or/and arrangement of reinforcement 5 can adopt various shaped steel, channel-section steel, C steel, weld assembly, combination steel construction piece etc., and the multiple patent steel member of inventor's invention, combination steel member also can be made into floor structure body beam column and other parts; Generally in the packaging combined unit combination body of the how high-rise block structure of each bolt tube placing formula, be equipped with unit corner post bolt tube 8 with socket joint or butt welding or tie plug 9 and dock, socket joint or butt welding or tie and have a wedge degree can make things convenient for location and installation on the plug 9, also can or tie the hold-doun nut that disposes connecting bolt on the plug 9 in addition in socket joint or butt welding, and can also do the auxiliary hand hole of installation check in its side, installation hole count, pore size on it are not done restriction; Adopt concrete combination corrosion protection steel construction piece patented method to make the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula, mainly being at steel construction piece 4 builds material 6 or/and arrangement of reinforcement 5 outsides or inner face adopt the method for spray, being coated with, smearing, irritating, watering etc. to do concrete or cast steel or other, as required the layout arrangement of reinforcement of putting more energy in position.Concrete and/or corrosion protection concrete all refer to require energy and steel construction piece 4 or/and arrangement of reinforcement 5 has the mechanical characteristic of strong adhesion, durability and steel member better to mate, and the concrete of suitable performances such as intensity is arranged.The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula etc. all is called the unit combination body with a lifting elements body, select to adopt various butt welding or tie or the methods permutation and combination of the packaging combined unit combination body and function selection of the how high-rise block structure of bolt tube placing formula of socket joint becomes some floors, if butt welding up and down or tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint between opening structure unit combination body is installed, under the support of opening structure unit combination body, just constituted one deck floor again, butt welding or tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint on accessory can dispose configuration quantity as required, the shape size, do not do restriction with material etc.; The composition mode of each ingredient of the packaging combined unit combination body of the composition how high-rise block structure of bolt tube placing formula, shape, quantity, annex etc. are not done restriction.Pei Zhi stair 13, the draught fan impeller of wind-driven generator assembly, wind-driven generator, cable as required, special restriction is not done in configurations as required such as building heat collecting tank, constructure ventilation system, wind-force negative pressure discharger, generating air conditioner controller, access door.Each parts of forming the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present invention are the parts that can select, the parts accessory that has is selected to determine whether adopt, the usage quantity of composition each parts of the present invention of selecting for use, shape etc. are not done restriction as required.
The packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present utility model has the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of full steel structure and the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of concrete combination corrosion protection or armored concrete, the common floor plates 3 that adopts or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and unit combination body throat passage floor plates and supporting pipeline etc., with some forms the structure support wherein, and adopt socket joint or the butt welding that is equipped with in the structure support or tie that plug 9 is installed or and other supporting structural member install, constituted the main part in the packaging combined unit combination body of the how high-rise block structure of the bolt tube placing formula of the present invention building system, and can add support thereon and in each parts, add annex, water power, ventilate, air-conditioning, communication, coal gas, pipelines such as TV, arrange and reserve auxiliary equipment as required, so just provide the how high-rise block structure of a kind of bolt tube placing formula packaging combined unit combination body, be applicable at steel work, supporting application on the buildings such as steel reinforced concrete can be built up steel construction more quickly, steel reinforced concrete building and buildings in general.
Description of drawings: accompanying drawing 1 Fig. 2 Fig. 3 Fig. 4 of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present utility model is some principle schematic of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of four kinds of forms, Fig. 5 Fig. 6 Fig. 7 is respectively common floor plates 3, unit combination body passage floor plates 1, a kind of principle schematic of unit combination body throat floor plates 2, Fig. 8 adopts combination keratotic plug tube 18 or supporting bolt tube 16 or supporting keratotic plug tube 15 or other structure to be supported in up and down socket joint or the butt welding that is equipped with in two floor structure bodies or ties a kind of schematic diagram that constitutes the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula in the plug 9 supporting pores, Fig. 9 Figure 10 Figure 11 is respectively that combination keratotic plug tube group 18 adopts the socket joint head to be connected with supporting bolt tube 16, butt welding connects, tie three kinds of principle schematic of connection, Figure 12 is 16 1 kinds of principle schematic of supporting bolt tube, Figure 13 is a kind of principle schematic of supporting keratotic plug tube 15, Figure 14 is a kind of principle schematic of the supporting bolt tube 16 of opening structure, Figure 15 Figure 16 is respectively two kinds of principle schematic of two kinds of combination keratotic plug tube groups 18, Figure 17 Figure 18 Figure 19 Figure 20 Figure 21 Figure 22 Figure 23 Figure 24 Figure 25 Figure 26 is respectively the main part splicing of several block structure collection dress assemblys or combination keratotic plug tube group 18 is formed in the splicing of several floor plates at the place, diagonal angle several principle schematic, each accompanying drawing shows only be a special case all, is not special restriction.
The specific embodiment: with reference to above-mentioned each accompanying drawing, the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula is mainly by unit combination body passage floor plates 1, unit combination body throat floor plates 2, common floor plates 3, steel construction piece 4, arrangement of reinforcement 5, concrete or cast steel or other are built material 6, insulation layer 7, unit corner post bolt tube 8, socket joint or butt welding or tie plug 9, floor structure body letter beam 10, floor structure body beam 11, floor structure body secondary beam 12, stair 13, bolt tube 14 is built in the part, supporting keratotic plug tube 15, supporting bolt tube 16, earthworm plate or floor or build ground 17, combination keratotic plug tube is organized 18 compositions such as grade, the butt welding that batch production is prefabricated tie or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint supporting be installed on unit corner post bolt tube 8 or combination keratotic plug tube 18 or supporting bolt tube 16 or supporting keratotic plug tube 15 or opening structure unit combination body or other structure supporter and another group butt welding or tie or the packaging combined unit combination body butt joint of the how high-rise block structure of bolt tube placing formula of socket joint or and common floor plates 3 or/and the butt joint of floor structure unit combination body or and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and unit combination body throat passage floor plates or and ground is basic docks.Unit combination body passage floor plates 1 is or/and unit combination body throat floor plates 2 transforms bascule, inlet channel, pneumatic channel and supporting pipeline etc. or/and the internal placement of unit combination body throat passage floor plates has; Common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and unit combination body throat passage floor plates is permutated and combined as the floor structure body, adopt the structure of some forms, as unit corner post bolt tube 8 or combination keratotic plug tube 18 or supporting bolt tube 16 or supporting keratotic plug tube 15 or opening structure unit combination body or other structure supporter be supported in common floor plates 3 or/and floor structure unit combination body or/and unit combination body passage floor plates 1 or/and unit combination body throat floor plates 2 or/and be equipped with in the unit combination body throat passage floor plates and can or tie in the pore of plug 9 butt joints by socket joint or butt welding, constitute the main part of the block structure collection dress assembly of the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of the present invention, and can add support thereon and in each parts, add annex, water power, ventilate, air-conditioning, communication, coal gas, pipelines such as TV, arrange and reserve auxiliary equipment as required, all do not do special restriction.The modularization making that adopts is installed butt welding or is tied or the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula of socket joint, preferentially adopts the connection of socket joint or socket joint bolt.Configuration such as other annex that need dispose, auxilliary material etc. are not as required done restriction.Restriction is not all done in the supporting use of being used of other structural member, other form of structure and building.

Claims (4)

1. packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula, mainly by unit combination body passage floor plates (1), unit combination body throat floor plates (2), common floor plates (3), steel construction piece (4), arrangement of reinforcement (5), concrete or cast steel or other are built material (6), insulation layer (7), unit corner post bolt tube (8), socket joint or butt welding or tie plug (9), floor structure body letter beam (10), floor structure body beam (11), floor structure body secondary beam (12), stair (13), bolt tube (14) is built in the part, supporting keratotic plug tube (15), supporting bolt tube (16), earthworm plate or floor or build ground (17), combination keratotic plug tube group (18) is formed, and it is characterized in that: block structure collect dress assembly or common floor plates (3) or/and floor structure unit combination body or/and unit combination body passage floor plates (1) or/and unit combination body throat floor plates (2) or/and be furnished with unit corner post bolt tube (8) on the unit combination body throat passage floor plates.
(2) according to claim 1, wherein the bolt barrel pouring multi-level block structure assembled modular unit assembly; wherein: block structure of the manifold assembly or general floor plate (3) and / or combinations of structural units of floors body and / or unit combination channel floor plate (1) and / or unit combination throat floor plate (2) and / or unit combination throat passageway floor panel has been combined angle plug cylinder (18) or the supporting bolt cylinder (16) or matching angle plug cylinder (15) on the socket or butt weld or bolt connecting plug (9) butt plug connected pores, pore assembly on the combination angle plug cylinder (18) or the supporting bolt cylinder (16 ) pouring pouring concrete or steel, or other materials (6) combination of a floor structure.
3. the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula according to claim 1, it is characterized in that: combination keratotic plug tube (18) or supporting bolt tube (16) or supporting keratotic plug tube (15) or other structure are supported in up and down socket joint or the butt welding that is equipped with in two floor structure bodies or tie in the supporting pore of plug (9), and the block structure collection that constitutes the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula is adorned assembly.
4. the packaging combined unit combination body of the how high-rise block structure of bolt tube placing formula according to claim 1 is characterized in that: block structure collect dress assembly or common floor plates (3) or/and unit combination body passage floor plates (1) or/and unit combination body throat floor plates (2) or/and the internal placement of unit combination body throat passage floor plates has supporting annex, pipeline.
CN2013200200494U 2013-01-15 2013-01-15 Bolt cylinder placing type high-rise block structure assembly combined type unit complex Expired - Fee Related CN203188369U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013200200494U CN203188369U (en) 2013-01-15 2013-01-15 Bolt cylinder placing type high-rise block structure assembly combined type unit complex

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013200200494U CN203188369U (en) 2013-01-15 2013-01-15 Bolt cylinder placing type high-rise block structure assembly combined type unit complex

Publications (1)

Publication Number Publication Date
CN203188369U true CN203188369U (en) 2013-09-11

Family

ID=49105237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013200200494U Expired - Fee Related CN203188369U (en) 2013-01-15 2013-01-15 Bolt cylinder placing type high-rise block structure assembly combined type unit complex

Country Status (1)

Country Link
CN (1) CN203188369U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306369A (en) * 2013-06-24 2013-09-18 孙善骏 Bolt cylinder or bolt cylinder section steel
CN104088366A (en) * 2013-09-22 2014-10-08 中集模块化建筑设计研发有限公司 Building module and middle/high-layered modularized building with building module

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306369A (en) * 2013-06-24 2013-09-18 孙善骏 Bolt cylinder or bolt cylinder section steel
CN104088366A (en) * 2013-09-22 2014-10-08 中集模块化建筑设计研发有限公司 Building module and middle/high-layered modularized building with building module

Similar Documents

Publication Publication Date Title
CN203230042U (en) Bolt-cylinder-poured and multi-high-rise-block-structured integrated combination type building
CN204901084U (en) Prefabricated integration assembled sectional shelf -unit based on BIM
CN205444458U (en) Integrated assembled steel construction building
CN103122667B (en) Light-weight steel structure plafond of large-span underground powerhouse of hydroelectric station
CN205502577U (en) A thimble assembly for buried sleeve one shot forming construction in piping shaft
CN102003082A (en) Combined box-type house and mounting method thereof
CN203188369U (en) Bolt cylinder placing type high-rise block structure assembly combined type unit complex
CN106760059B (en) Assembled building structure system
CN202194159U (en) Square pipe gallery bracket and square pipe gallery
CN203347203U (en) Multi-functional super-thick bulked concrete steel tube support system
CN105971328B (en) A kind of assembling type steel structure cooling tower being made of six bar tetrahedron elements
CN208063088U (en) Roofing is without support type roof photovoltaic power station
CN109469338A (en) A kind of tall and big workshop self-control grid platform and its construction method as electromechanical pipeline
CN207715928U (en) A kind of prefabricated direct-buried thermal insulation pipe with mounting bracket
CN107687541A (en) A kind of pipeline provided with people's row access path shares suspension bracket
CN207619866U (en) A kind of detachable sound barrier
CN207686133U (en) A kind of assembling truss purlin system
CN203188360U (en) Block structure integrated-installation combined-type unit combined body
CN103924671A (en) Bolt cylinder pouring type multi-story block structure packaging combined type unit assembly
CN206052963U (en) The top shock insulation building module structure of the self adaptation shock insulation number of plies
CN203594160U (en) Notch plate, folding angle plate and jointed plate coordinated with cylinder-shaped packaging assembling unit assembly
CN104088481A (en) Sandwich composite glass fiber reinforced plastic plenum chamber for auditorium and construction method thereof
CN203008233U (en) K-structure unit assembly
CN207130970U (en) A kind of Novel T-shaped building vertical column
CN207376813U (en) A kind of assembled steel tubing string-prefabricated band beam floor steel construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130911

Termination date: 20190115

CF01 Termination of patent right due to non-payment of annual fee