CN203173684U - Component for hoisting reinforcement cage - Google Patents

Component for hoisting reinforcement cage Download PDF

Info

Publication number
CN203173684U
CN203173684U CN 201220650585 CN201220650585U CN203173684U CN 203173684 U CN203173684 U CN 203173684U CN 201220650585 CN201220650585 CN 201220650585 CN 201220650585 U CN201220650585 U CN 201220650585U CN 203173684 U CN203173684 U CN 203173684U
Authority
CN
China
Prior art keywords
reinforcement cage
hook
steel reinforcement
crane
fixed pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220650585
Other languages
Chinese (zh)
Inventor
任利民
吴文明
邹中波
于新山
张军政
党智军
董金国
刘晶
武峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, Bridge and Tunnel Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN 201220650585 priority Critical patent/CN203173684U/en
Application granted granted Critical
Publication of CN203173684U publication Critical patent/CN203173684U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

A component for hoisting a reinforcement cage belongs to the field of hoisting construction, includes a carrying pole beam, steel wire ropes, a lifting hook and fixed pulleys, and is characterized in that a crane main hook hoisting hole used for being connected with a main hook of a crane is formed in the center of the carrying pole beam; pulley mounting holes are formed in two sides of the crane main hook hoisting hole; fixed pulleys are mounted in the pulley mounting holes; the steel wire ropes bypass the fixed pulleys and are connected with a to-be-hoisted reinforcement cage; the fixed pulleys are mounted in the pulley mounting holes by virtue of hangers; ferrules are arranged between the fixed pulleys and the hangers/the lifting hook/the fixed pulleys; the lifting hook mounted in the crane main hook hoisting hole and the hangers can rotate freely; and the steel wire ropes can slide freely in the fixed pulleys. According to the utility model, the fixed pulleys and the steel wire ropes are adopted for controlling the reinforcement cage, the reinforcement cage can be hoisted only through one crane, consumption of machinery, labor and time under the previous construction condition can be saved to a certain extent, the cost is greatly saved and the structure is simple.

Description

A kind of member that lifts steel reinforcement cage
Technical field
The present invention relates to a kind ofly for the bridge pile foundation construction member for longer reinforcing bar cage hoisting, belong to the lifting construction field.
Background technology
In pile foundation construction, in order to lift steel reinforcement cage, steel reinforcement cage is installed in the boring, use the method for crane lifting usually, according to conventional approach, the steel reinforcement cage for long generally uses two cranes.A crane (main crane) is used in front middle part position at steel reinforcement cage in the construction, the afterbody of steel reinforcement cage uses another crane (secondary crane) to lift, two cranes cooperatively interact, main crane is sling steel reinforcement cage top, secondary crane cooperates makes the steel reinforcement cage built on stilts, secondary crane is adjusted steel reinforcement cage by adjusting the lifting rope height, and is vertical until steel reinforcement cage.Thereby adopt this method, and bigger to mechanical use amount, need with two cranes, the time spent is longer, to the technical requirements height of machinery operator.
And
The utility model content
In order to overcome the problems referred to above, the present invention proposes to use a kind of new type of component, can improve and save under original execution conditions the use for machinery, personnel, time to the full extent, and construct fairly simple, objective condition is required low, suitable being extensive use of.
Its concrete technical scheme is as follows:
A kind of member that lifts steel reinforcement cage, it comprises shoulder pole girder, steel rope, suspension hook and fixed pulley 1, have for the crane main hook hole for hoist 2 that is connected with the main hook of crane in described shoulder pole girder center, both sides at crane main hook hole for hoist 2 have pulley mounting hole 3, fixed pulley 1 is installed on the pulley mounting hole 3, and steel rope is walked around fixed pulley 1 and is connected with steel reinforcement cage to be sling; Fixed pulley 1 is installed in the pulley mounting hole 3 by hook; Reaching between the fixed pulley 1 between described fixed pulley 1 and the hook is the collar, and the suspension hooks that are installed in the crane main hook hole for hoist 2 can rotate freely with hook, and steel rope can be free to slide in fixed pulley 1.
Used wirerope diameter is 16mm.
The material of fixed pulley 1 is not less than the A3 steel, and the selected steel plate thickness of shoulder pole girder is 10mm.
Ultimate range between the pulley mounting hole 3 of described shoulder pole girder both sides is slightly larger than the diameter of steel reinforcement cage to be lifted.
Method for making of the present utility model is as follows:
At first be the steel plate of 10mm with thickness, make the used shoulder pole girder of member according to operating needs, the fixed pulley member is installed at the two ends of shoulder pole girder, and checked its degree of safety to meet the requirements.At fixed pulley steel rope is installed, is utilized the sabre button to be fixed on top and the middle part of steel reinforcement cage two ends of steel rope, then the steel rope of the little suspension hook of crane is installed in the afterbody of steel reinforcement cage.
Use of the present utility model is as follows:
During lifting, at first use little suspension hook with the lifting of steel reinforcement cage bottom, make it be about to built on stilts, promote big suspension hook afterwards, make steel reinforcement cage top become 60 ° with ground.And then promote little hook, and make the whole disengaging of steel reinforcement cage ground unsettled, the rotation crane is long-armed, adjusts the steel reinforcement cage squareness at bore position, and the little hook that descends makes steel reinforcement cage vertical substantially with boring.Utilize the fixed pulley of this device to make steel reinforcement cage in vertical process, adjust angle at last, treat and the vertically little hook of back dismounting of holing thoroughly that steel reinforcement cage is sling by big suspension hook fully like this, finishes the lifting before steel reinforcement cage enters the hole.
The utility model can obtain following beneficial effect:
The utility model uses " shoulder pole girder " to cooperate the method for fixed pulley can only use a crane, has reduced construction area in construction, has saved engineering time and machine cost, has improved work efficiency.
Description of drawings
Fig. 1 uses the utility model lifting component procedure chart;
The structural representation of the shoulder pole girder of Fig. 2 the utility model member;
Fig. 3 is the detail view of hook with pulley.
Among the figure: 1, fixed pulley, 2, crane main hook hole for hoist, 3, pulley mounting hole.
The specific embodiment
Below in conjunction with accompanying drawing to the utility model to specifying:
A kind of member that lifts steel reinforcement cage as shown in Figure 1 to Figure 3, it comprises shoulder pole girder, steel rope, suspension hook and fixed pulley 1, it is characterized in that: have in described shoulder pole girder center for the crane main hook hole for hoist 2 that is connected with the main hook of crane, both sides at crane main hook hole for hoist 2 have pulley mounting hole 3, on the pulley mounting hole 3 fixed pulley is installed, steel rope is walked around fixed pulley 1 and is connected with steel reinforcement cage to be sling; Fixed pulley 1 is installed in the pulley mounting hole 3 by hook; Be the collar between described fixed pulley 1 and hook suspension hook and the fixed pulley 1, the suspension hook that is installed in the crane main hook hole for hoist 2 can rotate freely with hook, and steel rope can be free to slide in fixed pulley 1.
Used wirerope diameter is 16mm.
The material of fixed pulley 1 is not less than the A3 steel, and the selected steel plate thickness of shoulder pole girder is 10mm.
Ultimate range between the pulley mounting hole 3 of described shoulder pole girder both sides is slightly larger than the diameter of steel reinforcement cage to be lifted.
The application in practice of the member of lifting steel reinforcement cage of the present invention:
After steel reinforcement cage completes, be transported to the scene, at first " shoulder pole girder " is installed on the crane hook, and is installed on the suitable pulley mounting hole site according to big young pathbreaker's member of lifting steel reinforcement cage.The steel rope of lifting usefulness is tied up top and middle part at steel reinforcement cage respectively by fixed pulley.Then little suspension hook steel rope is installed in the steel reinforcement cage afterbody.
In hoisting process, promote little suspension hook earlier and make the bottom of steel reinforcement cage be about to built on stilts, afterwards hoisting hook, make the top lifting, the regulating action by fixed pulley guarantees that steel reinforcement cage is stable, treats that big suspension hook is promoted to certain altitude when becoming 60 ° with ground, promote little suspension hook, make steel reinforcement cage break away from ground.Treat steel reinforcement cage rise to the hole that becomes basic vertically after, slowly put down little hook steel reinforcement cage kept vertically, this moment, shoulder pole girder got final product apart from steel reinforcement cage top 40cm-60cm, unloaded little suspension hook steel rope and got final product.
Can effectively shorten the time by such method allocation and transportation steel reinforcement cage, only use a crane, promote economic benefit greatly, actv. has been finished the lifting of steel reinforcement cage.And operate fairly simple.
In sum, adopt the construction method of this new type of component lifting steel reinforcement cage, not only saved the engineering time, and had characteristics such as better operability and economy, have higher popularization and application values.

Claims (4)

1. member that lifts steel reinforcement cage, it comprises shoulder pole girder, steel rope, suspension hook and fixed pulley (1), it is characterized in that: have in described shoulder pole girder center for the crane main hook hole for hoist (2) that is connected with the main hook of crane, have pulley mounting hole (3) in the both sides of crane main hook hole for hoist (2), fixed pulley (1) is installed on the pulley mounting hole (3), and steel rope is walked around fixed pulley (1) and is connected with steel reinforcement cage to be sling; Fixed pulley (1) is installed in the pulley mounting hole (3) by hook; Reaching between the fixed pulley (1) between described fixed pulley (1) and the hook is the collar, and the suspension hook that is installed in the crane main hook hole for hoist (2) can rotate freely with hook, and steel rope can be free to slide in fixed pulley (1).
2. a kind of member that lifts steel reinforcement cage according to claim 1, it is characterized in that: used wirerope diameter is 16mm.
3. a kind of member that lifts steel reinforcement cage according to claim 1, it is characterized in that: the material of fixed pulley (1) is not less than the A3 steel, and the selected steel plate thickness of shoulder pole girder is 10mm.
4. a kind of member that lifts steel reinforcement cage according to claim 1, it is characterized in that: the ultimate range between the pulley mounting hole (3) of described shoulder pole girder both sides is slightly larger than the diameter of steel reinforcement cage to be lifted.
CN 201220650585 2012-11-29 2012-11-29 Component for hoisting reinforcement cage Expired - Fee Related CN203173684U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220650585 CN203173684U (en) 2012-11-29 2012-11-29 Component for hoisting reinforcement cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220650585 CN203173684U (en) 2012-11-29 2012-11-29 Component for hoisting reinforcement cage

Publications (1)

Publication Number Publication Date
CN203173684U true CN203173684U (en) 2013-09-04

Family

ID=49070418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220650585 Expired - Fee Related CN203173684U (en) 2012-11-29 2012-11-29 Component for hoisting reinforcement cage

Country Status (1)

Country Link
CN (1) CN203173684U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103693547A (en) * 2013-12-16 2014-04-02 上海市机械施工集团有限公司 Self-balance hoisting tool and hoisting method for specially-shaped component
CN103741719A (en) * 2013-11-29 2014-04-23 中交第二航务工程局有限公司 Reinforcing cage guiding moving system and method
CN105645248A (en) * 2016-03-24 2016-06-08 中交第四公路工程局有限公司 Reinforcement cage lifting device and method
CN108086309A (en) * 2017-12-14 2018-05-29 中交第四航务工程局有限公司 A kind of mini pile cages installation method
CN110217686A (en) * 2019-05-18 2019-09-10 陕西建工第五建设集团有限公司 A kind of put down based on the flat steel reinforcement cage for hanging equipment of steel reinforcement cage hangs method
CN110745683A (en) * 2019-10-17 2020-02-04 中铁科工集团装备工程有限公司 Hoisting device and method for reinforcement cage of underground continuous wall

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741719A (en) * 2013-11-29 2014-04-23 中交第二航务工程局有限公司 Reinforcing cage guiding moving system and method
CN103693547A (en) * 2013-12-16 2014-04-02 上海市机械施工集团有限公司 Self-balance hoisting tool and hoisting method for specially-shaped component
CN103693547B (en) * 2013-12-16 2016-08-17 上海市机械施工集团有限公司 The hanging method of special-shaped component
CN105645248A (en) * 2016-03-24 2016-06-08 中交第四公路工程局有限公司 Reinforcement cage lifting device and method
CN105645248B (en) * 2016-03-24 2017-08-08 中交第四公路工程局有限公司 A kind of steel reinforcement cage lifting device and method
CN108086309A (en) * 2017-12-14 2018-05-29 中交第四航务工程局有限公司 A kind of mini pile cages installation method
CN108086309B (en) * 2017-12-14 2023-11-21 中交第四航务工程局有限公司 Mini pile reinforcement cage installation method
CN110217686A (en) * 2019-05-18 2019-09-10 陕西建工第五建设集团有限公司 A kind of put down based on the flat steel reinforcement cage for hanging equipment of steel reinforcement cage hangs method
CN110217686B (en) * 2019-05-18 2020-08-11 陕西建工第五建设集团有限公司 Steel reinforcement cage horizontal hoisting method based on steel reinforcement cage horizontal hoisting equipment
CN110745683A (en) * 2019-10-17 2020-02-04 中铁科工集团装备工程有限公司 Hoisting device and method for reinforcement cage of underground continuous wall

Similar Documents

Publication Publication Date Title
CN203173684U (en) Component for hoisting reinforcement cage
CN205045698U (en) Reinforcement cage hoisting utensil
CN106744257B (en) A kind of kiloton adjustable combined sling, assemble method and the method for lifting caisson
CN201809036U (en) Hanging hopper with detachable chassis
CN102070071A (en) Steel reinforcement cage hoisting method
CN207513158U (en) Concrete stack shell constructing device
CN106006425B (en) A kind of high-rise building ground machine room lower large scale equipment hoisting transportation method
CN101597960A (en) Large-tonnage jack tension construction technology for non-bonded prestressed silo
CN107795122A (en) Concrete stack shell constructing device and construction method
CN109095343A (en) Assembled hanger
CN206767425U (en) A kind of integral hoisting device for rapid for ground-connecting-wall steel reinforcement cage
CN204342297U (en) A kind of transfer crane with jib structure
CN106315426A (en) Block form tower crane mounting and jacking method for assembled building
CN107881926B (en) Combined hanging basket with full-rotation crane and construction method thereof
CN203638979U (en) Device for mounting tank floor in low-temperature storage tank
CN205170161U (en) Precast beam board framework of steel reinforcement hoist
CN201762053U (en) Simple automatic hoisting rod
CN104355238A (en) Portal crane with jib structure
CN109339399A (en) A kind of section construction method of steel construction in elevator shaft
CN210635599U (en) Prevent cracked steel bar truss concrete superimposed sheet hoist
CN108516454A (en) A kind of hanging apparatus of prefabricated components
CN211769762U (en) Concrete box girder steel reinforcement cage integral hoisting device
CN209179426U (en) A kind of elevator shaft steel construction section construction device
CN210505201U (en) Equipment for hoisting reinforcing steel bars in batches
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CU01 Correction of utility model

Correction item: Patentee

Correct: BRIDGE & TUNNEL ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

False: BRIDGE & TUNNEL ENGINEERING CO LTD OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Number: 36

Page: The title page

Volume: 29

CU03 Publication of corrected utility model

Correction item: Patentee

Correct: BRIDGE & TUNNEL ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

False: BRIDGE & TUNNEL ENGINEERING CO LTD OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Number: 36

Volume: 29

ERR Gazette correction

Free format text: CORRECT: PATENTEE; FROM: BRIDGE + TUNNEL ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING CO., LTD. TO: CCCC FIRST HIGHWAY BRIDGE AND TUNNEL ENGINEERING CO., LTD.

RECT Rectification
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 074000, 98 North Main Street, Baoding, Hebei, Gaobeidian

Co-patentee after: BRIDGE & TUNNEL ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Patentee after: CHINA FIRST HIGHWAY ENGINEERING Co.,Ltd.

Address before: 074000, 98 North Main Street, Baoding, Hebei, Gaobeidian

Co-patentee before: BRIDGE & TUNNEL ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Patentee before: CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904

Termination date: 20211129