CN202975272U CN 201220644293 CN201220644293U CN202975272U CN 202975272 U CN202975272 U CN 202975272U CN 201220644293 CN201220644293 CN 201220644293 CN 201220644293 U CN201220644293 U CN 201220644293U CN 202975272 U CN202975272 U CN 202975272U
Authority
CN
China
Prior art keywords
monitoring device
breaker
time
isolating switch
processing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220644293
Other languages
Chinese (zh)
Inventor
张秉俊
牛立群
张胜
张治新
李大卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuyang Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
Fuyang Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuyang Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical Fuyang Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority to CN 201220644293 priority Critical patent/CN202975272U/en
Application granted granted Critical
Publication of CN202975272U publication Critical patent/CN202975272U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Arc-Extinguishing Devices That Are Switches (AREA)

Abstract

An on-line monitoring device for connecting and disconnecting time of a high voltage breaker comprises a monitoring device, a main control panel, a communication front-end processor and a host computer. The on-line monitoring device is characterized in that the monitoring device is divided into two parts, a monitoring device I is provided with the main control panel, a high speed data processing unit, a DSP 2812 and a logic signal processing unit CPLD, an output interface of the main control panel is respectively connected with a main computer, waveform output, a network communication interface and a watchdog, a current measuring port and a stroke measuring port of the monitoring device are respectively connected with the breaker, a current measuring port and a stroke measuring port of a monitoring device II are respectively connected with a breaker II, and the monitoring device I and the monitoring device II are connected with the communication front-end processor and the host computer through a CAN bus. According to the on-line monitoring device, a photoelectric current sensor is employed to measure various current signals in a real-time manner, the signals are transmitted to a digital processing unit module through optical fiber communication under an IEC 61850 protocol, and the international general object-oriented language C++ is employed for programming, thereby measuring connecting and disconnecting time of the breaker on line and diagnosing faults of the breaker.

Description

Primary cut-out cut-offs and the time on-Line Monitor Device is closed in the pass
Technical field:
The utility model relates to the on-Line Monitor Device of transformer station's primary cut-out, particularly the on-Line Monitor Device of cut-offfing, closing the time of closing and fault diagnosis of primary cut-out under the IEC61850 of International Electrotechnical Commission communication protocol.
Background technology:
In substation equipment, primary cut-out quantity is maximum, maintenance workload is huge, and current primary cut-out is carried out Maintenance Mode, has basically replaced traditional scheduled overhaul pattern fully.For improving the specific aim of maintenance, need to grasp in real time the performance quality of isolating switch self, in time find the defective of primary cut-out in service, in recent years, under the IEC61850 communication protocol, on-line monitoring technique requires more and more higher to the monitoring of mechanical characteristic of high-voltage circuit breaker and electrical specification.Particularly primary cut-out cut-off and time module is closed in the pass, it not only can obtain the status information of high-voltage circuit-breaker switching on-off electromagnet performance, operating mechanism and kinematic train, and can be convenient to analyze the variation tendency of sentencing primary cut-out key property parameter, enable the health status of accurate evaluation equipment, for the repair based on condition of component strategy provides basis of compilation.Therefore measure primary cut-out and close and close and switch off time, very necessary.
Define according to People's Republic of China's power industry standard " ac hv breaker parameters selection guide rule " DL/T615-1997: concerning isolating switch, operation in every not charged situation is called separating brake and combined floodgate, and the operation in every charged situation calls off disconnected and close the pass.Difference between them is there is no arc time and pre arcing time when not charged, and should notice that arc extinguishing moment and prebreakdown moment is different in the three-phase situation in three-phase, cut-off the monitoring of closing the time with the pass for contact of breaker, present existing technology has:
1, adopt outside current transformer, get moment that last phase current of isolating switch major loop has or not as the contact of breaker deciliter complete moment.The defective that this method exists is: (1) must have the existence of load current, in case operating process is not loaded, just can not monitor the existence of electric current, causes and can't locate; (2) precision in the affects isolating switch deciliter complete moment of the threshold value of judgement electric current existence.
2, add vibration transducer, adopt and judge the isolating switch deciliter complete moment based on mechanical oscillation signal.
Acceleration transducer is generally used in the collection of vibration signal, and acceleration transducer converts the contact vibration signal to charge signal, converts voltage signal to by charge amplifier, then obtains desired signal by the resonance and demodulation device.But the analysis to the contact of breaker vibration signal is the difficult point of mechanical property monitoring, disperse, reflection and refraction due to primary cut-out operation vibrations and various neighbourhood noise, signal, make the vibration signal that sensor obtains have interference component, the more difficult identification of small-signal.When the instantaneous amplitude of undesired signal and frequency reach can compare with vibration signal the time, use conventional methods and be difficult to effectively distinguish noise and useful signal.Shortcoming is to need a plurality of acceleration sensors to be placed on different positions.The analysis breaker operation mechanism vibration signal shortcomings such as employing frequency domain analysis, zoom spectrum analysis method are that the time signal of reflection is inadequate.
3. having document to propose monitoring prebreakdown this problem constantly, is to utilize the high voltage display device that is arranged on together with primary cut-out on switch cubicle to measure the contact of breaker divide-shut brake constantly.When power circuit was charged, capacitive transducer induced voltage by field coupled, and showed having or not of voltage signal by electrification display.Shortcoming is that to measure pre arcing time and the arc time error of isolating switch larger.
In a word, recommend to comprise at present the isolating switch on-Line Monitor Device of having used, exist shortcoming separately, especially isolating switch is cut-off the arc time of main circuit and close the monitoring of the pre arcing time close main circuit inadequate, majority can only carry out divide-shut brake monitoring actuation time of isolating switch when not charged.
Summary of the invention:
Technical problem to be solved in the utility model is to overcome the deficiencies in the prior art, provide a kind of fast, the Measurement accuracy primary cut-out cut-offs the on-Line Monitor Device of closing the time with the pass, effectively carry out isolating switch and cut-off the on-line monitoring that closes the time with the pass.
The technical scheme that the utility model technical solution problem adopts is as follows:
a kind of primary cut-out cut-offs the on-Line Monitor Device of closing the time with the pass, by monitoring device, master control borad, prepositive communication computer and host computer consist of, it is characterized in that: monitoring device divides two parts, be provided with master control borad on monitoring device I, the high-speed data processing unit, DSP2812, logical signal processing unit CPLD, the master control borad output interface respectively with host computer, waveform output, network communication interface, house dog is connected, the current measurement of monitoring device, the stroke measurment port is connected with isolating switch respectively, the current measurement of monitoring device II, the stroke measurment port is connected with isolating switch II respectively, monitoring device I, II is connected with host computer with prepositive communication computer by the CAN bus.
The utility model adopts optical current transformer to measure in real time various current signals, under the IEC61850 stipulations by fiber-optic communications traffic to the digital processing element module; Utilize wavelet analysis technology, extract the various signal waveforms in the loop current waveform, recycle quick Fu Li industry conversion FFT deal with data, carrying out isolating switch cut-offs and the analyzing and processing of closing the various current waveforms in the closing operation process, high-speed data processing unit DSP2812 and logical signal processing unit CPLD are the hardware components of digital processing element, adopt international object oriented language C++ to write, the time is closed in cut-offfing with the pass of on-line measurement isolating switch, carries out the circuit breaker failure diagnosis.
Implementation result of the present utility model is as follows:
1, utilize the remote signalling sampling of current signal, obtain that isolating switch cut-offs and conducting constantly, comprise expectation in the primary cut-out making process that is incorporated into the power networks and wear arc time in time and separating brake process, make the isolating switch dynamic perfromance monitor that science is accurate more.
2, adopt wavelet analysis technology, carrying out main circuit current signal clocking value sets, and carry out the calibration of personal monitoring's analyzing and diagnosing according to signal record ripple, and solving the time zero problem to the current signal sampling, the isolating switch of having realized being incorporated into the power networks cut-offs the time measurement of closing time point with the pass and determines.
3, arc time and the pre arcing time in on-line monitoring primary cut-out course of action, provide foundation to Fault Diagnosis for HV Circuit Breakers and judgement.
Description of drawings:
Accompanying drawing is structural representation of the present utility model.
In the accompanying drawings, the 1st, monitoring device I, the 2nd, master control borad, the 3rd, prepositive communication computer, the 4th, host computer, the 5th, monitoring device II, the 6th, DSP2812, the 7th, CPLD, the 8th, current measurement A, the 9th, current measurement B, the 10th, current measurement C, the 11st is flow measurement D, the 12nd, isolating switch I, the 13rd, current measurement E, the 14th, current measurement F, the 15th, isolating switch II, the 16th, CAN bus.
Embodiment:
The utility model is described in further detail below in conjunction with accompanying drawing.
as shown in the figure, a kind of primary cut-out cut-offs the on-Line Monitor Device of closing the time with the pass, by monitoring device, master control borad 2, prepositive communication computer 3 and host computer 4 consist of, it is characterized in that: monitoring device divides two parts, be provided with master control borad 2 on monitoring device I, the high-speed data processing unit, DSP2812, logical signal processing unit CPLD7, master control borad 2 output interfaces respectively with host computer, waveform output, network communication interface, house dog is connected, the current measurement of monitoring device, the stroke measurment port is connected with isolating switch respectively, the current measurement of monitoring device II, the stroke measurment port is connected with isolating switch II respectively, monitoring device I, II is connected with host computer with prepositive communication computer by the CAN bus.
Its operation steps is as follows:
(1) to isolating switch minute, closing coil carries out the remote signalling sampling of voltage signal, when isolating switch is received minute, rise during the closing operation instruction, begin to record respectively the displacement moment that remote signals is grown out of nothing, the moment Tf that when being separating brake, voltage signal is set up in switching winding,, moment Th that when closing a floodgate, voltage signal is set up in closing coil, and with Tf, Th as breaker open operation coil, the charged initial time of closing coil:
(2) utilize photoelectric sensor to gather each phase current waveform of major loop, utilize wavelet analysis method to record the main circuit current waveform and have or not constantly.When closing closing operation, main circuit current waveform three-phase grows out of nothing and is designated as Ta1h, Tb1h, Tc1h constantly, with Ta1h, Tb1h, Tc1h as closing each phase major loop pre arcing time initial time in the closing operation process; Cut-off when operation main circuit current waveform from having to without constantly being designated as Ta1f, Tb1f, Tc1f, with Ta1f, Tb1f, Tc1f as cut-offfing in operating process each phase major loop finish time arc time; Last phase current signal is set up constantly as circuit turn-on constantly, and last phase current signal is disappeared to be disconnected constantly as circuit constantly;
(3) displacement transducer is measured connecting lever actuation time, displacement two-end-point when setting the connecting lever regular event according to breaker apparatus explanation and device field condition, and isolating switch is in when closing a floodgate, connecting lever position A point, when isolating switch is in separating brake, connecting lever position B point.When closing closing operation, connecting lever moves to the A point and is designated as Tsah, Tsbh, Tsch constantly, with Tsah, Tsbh, Tsch as isolating switch three-phase contact closure constantly; When cut-offfing operation, connecting lever moves to the B point and is designated as Tsaf, Tsbf, Tscf constantly, and Tsaf, Tsbf, Tscf are disconnected constantly as isolating switch three-phase contact;
(4) calculate the mistiming that the charged initial time Tf of brake division loop of circuit breaker and connecting lever move to B point moment Tsaf, Tsbf, Tscf, be breaker open operation time T 02; Calculate isolating switch and cut-off initial time Tf and main circuit current blackout mistiming constantly, be isolating switch switch off time T0; Calculate isolating switch and close and close loop band electrical initiation Th and main circuit current conducting constantly mistiming of Ta1h, Tb1h, Tc1h constantly, be the isolating switch pass and close time T 1; Calculate isolating switch close close the loop band electrical initiation constantly Th and connecting lever move to mistiming of A point moment Tsah, Tsbh, Tsch, be breaker closing time T 12.
(5) calculating isolating switch switch off time and the mistiming of breaker open operation time are isolating switch arc time T01; Calculating breaker closing time and isolating switch pass closes the mistiming of time and is isolating switch pre arcing time T11; Calculating in the isolating switch interrupting process major loop three-phase current signal mistiming constantly that disappears is isolating switch and cut-offs not the time T tq0 same period; Calculating isolating switch closes and closes in process the major loop three-phase current signal conducting mistiming constantly and be isolating switch and close and close not the time T tq1 same period.
DSP2812 master control borad software is the core that system controls, and the software of CPLD plate depends on the data of DSP2812 master control borad.The program of DSP2812 master control borad can be divided into watchdog routine, communication program, sampling routine and four main functional modules of calculation procedure.Watchdog routine is major cycle, adopts the Task Scheduling Mechanism of imitative embedded real-time multi-task operating system, and to self-check of device.Sampling routine is completed input quantity high-speed sampling, record ripple, the tasks such as generated clock.Seizure and the calculating of all kinds of on-line monitoring indexs when calculation procedure is completed breaker operator.Communication program encapsulates communication data by stipulations, and transmission or receive data.

Claims (1)

1. a primary cut-out cut-offs and the time on-Line Monitor Device is closed in the pass, by monitoring device, master control borad, prepositive communication computer and host computer consist of, it is characterized in that: monitoring device divides two parts, be provided with master control borad on monitoring device I, the high-speed data processing unit, DSP2812, logical signal processing unit CPLD, the master control borad output interface respectively with host computer, waveform output, network communication interface, house dog is connected, the current measurement of monitoring device, the stroke measurment port is connected with isolating switch respectively, the current measurement of monitoring device II, the stroke measurment port is connected with isolating switch II respectively, monitoring device I, II is connected with host computer with prepositive communication computer by the CAN bus.
CN 201220644293 2012-11-23 2012-11-23 On-line monitoring device for connecting and disconnecting time of high voltage breaker Expired - Fee Related CN202975272U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220644293 CN202975272U (en) 2012-11-23 2012-11-23 On-line monitoring device for connecting and disconnecting time of high voltage breaker

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220644293 CN202975272U (en) 2012-11-23 2012-11-23 On-line monitoring device for connecting and disconnecting time of high voltage breaker

Publications (1)

Publication Number Publication Date
CN202975272U true CN202975272U (en) 2013-06-05

Family

ID=48516330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220644293 Expired - Fee Related CN202975272U (en) 2012-11-23 2012-11-23 On-line monitoring device for connecting and disconnecting time of high voltage breaker

Country Status (1)

Country Link
CN (1) CN202975272U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103018664A (en) * 2012-11-23 2013-04-03 安徽省电力公司阜阳供电公司 Equipment for monitoring switching-off and on time of high-voltage circuit breaker on line
CN106601534A (en) * 2016-11-22 2017-04-26 平高集团有限公司 High-voltage isolating switch and high-voltage isolating switch transmission mechanism fault monitoring method
CN107861058A (en) * 2017-11-07 2018-03-30 山东泰开高压开关有限公司 A kind of measurement apparatus and measuring method of vacuum circuit breaker divide-shut brake speed
RU2748784C1 (en) * 2018-03-28 2021-05-31 Абб Швайц Аг Device and method for fault diagnosis for circuit breaker

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103018664A (en) * 2012-11-23 2013-04-03 安徽省电力公司阜阳供电公司 Equipment for monitoring switching-off and on time of high-voltage circuit breaker on line
CN106601534A (en) * 2016-11-22 2017-04-26 平高集团有限公司 High-voltage isolating switch and high-voltage isolating switch transmission mechanism fault monitoring method
CN106601534B (en) * 2016-11-22 2019-01-11 平高集团有限公司 High voltage isolator and high-voltage isolating switch transmission mechanism fault monitoring method
CN107861058A (en) * 2017-11-07 2018-03-30 山东泰开高压开关有限公司 A kind of measurement apparatus and measuring method of vacuum circuit breaker divide-shut brake speed
RU2748784C1 (en) * 2018-03-28 2021-05-31 Абб Швайц Аг Device and method for fault diagnosis for circuit breaker

Similar Documents

Publication Publication Date Title
CN103018664A (en) Equipment for monitoring switching-off and on time of high-voltage circuit breaker on line
CN102710014B (en) Mechanical characteristic condition monitoring device for circuit breaker based on IEC61850
CN105548874A (en) Intelligent switch state integrated online monitoring and fault diagnosis apparatus
CN202230150U (en) On-line monitoring intelligent terminal for electric power lightning arrester with fiber for power supply
CN102288907A (en) Comprehensive condition testing method of circuit breaker
CN102290865A (en) Integrated intelligent unit of intelligent substation
CN104007384A (en) Circuit breaker mechanical property test platform and test method
CN202975272U (en) On-line monitoring device for connecting and disconnecting time of high voltage breaker
CN102437650A (en) Intelligent electric power distribution system
CN205809245U (en) A kind of mechanical characteristic of high-voltage circuit breaker state on_line monitoring system
CN105823981A (en) On-line monitoring system of high-voltage circuit breaker and data processing method thereof
CN202210139U (en) Device capable of automatically testing service lifetime of low voltage breaker
CN110187193B (en) Dielectric loss monitoring system and method based on total-station voltage transformer stability judgment
CN105207361A (en) Intelligent medium-voltage switch equipment
CN201256292Y (en) GIS digital interval observing and controlling device
CN202837499U (en) Testing device for mechanical characteristics in grid circuit breakers
CN201535814U (en) On-line circuit breaker monitoring system based on IEC61850 standard
CN105070334A (en) Method for judging action of control rod drive mechanism based on current change
CN104578430A (en) Online monitoring device for circuit breaker operating mechanism
CN202475013U (en) Intelligent power distribution device
CN212008850U (en) Intelligent primary and secondary fused on-column circuit breaker
CN112540292B (en) Circuit breaker action frequency counting device and method
CN103954829A (en) Transformer core grounding current online monitoring system
CN203054193U (en) On-line monitoring system for mechanical characteristic of vacuum circuit breaker
CN104464253A (en) Intelligent diagnosis method for field electricity information acquisition equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130605

Termination date: 20131123