CN202812511U - Pipeline provided with built-in metal bellows and used for engineering - Google Patents

Pipeline provided with built-in metal bellows and used for engineering Download PDF

Info

Publication number
CN202812511U
CN202812511U CN 201220500026 CN201220500026U CN202812511U CN 202812511 U CN202812511 U CN 202812511U CN 201220500026 CN201220500026 CN 201220500026 CN 201220500026 U CN201220500026 U CN 201220500026U CN 202812511 U CN202812511 U CN 202812511U
Authority
CN
China
Prior art keywords
section
pipeline
hole
height
metal bellows
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220500026
Other languages
Chinese (zh)
Inventor
詹春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhan Kejun
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201220500026 priority Critical patent/CN202812511U/en
Application granted granted Critical
Publication of CN202812511U publication Critical patent/CN202812511U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The utility model discloses a pipeline provided with a built-in metal bellows and used for engineering. The pipeline comprises a pipeline body which is made of concrete or cement or cement mortar or resin cement mixture, and the metal bellows having the same coaxial line with the pipeline body is installed inside the pipeline body. The bellows is composed of a wave crest section, a first height section, a wave trough section and a second height section, wherein the wave crest section, the first height section, the wave trough and the second height section are successively connected in a circulated mode along the axial direction. A wave trough section through hole is formed in the wave trough section, a wave crest section through hole is formed in the wave crest section, and wave crest section through holes are formed in the first height section and the second height section. By means of the technical scheme, the metal bellows having the same axial line with the pipeline body is installed inside the pipeline body which is made of the concrete or the cement or the cement mortar or the resin cement mixture, so that intensity and ring stiffiness of the pipeline body are enhanced fully.

Description

A kind of engineering pipeline of built-in metal bellows
Technical field
The utility model relates to a kind of pipeline, relates in particular to the pipeline that a kind of engineering is used the built-in metal bellows.
Background technique
Engineering adopts concrete or cement or slush or resin cement mixture to make with pipeline mostly, and the pipeline strength of this structure is inadequate, is easy to fragmentation.The reinforcing bar that reinforing function has been set is also arranged, but intensity does not still meet in special engineering the requirement to pipe ring rigidity in pipeline body.
The model utility content
The utility model provides the pipeline of the strong engineering of a kind of ring stiffness with the built-in metal bellows in order to solve deficiency of the prior art.
For solving the problems of the technologies described above, the utility model adopts following technological scheme: a kind of engineering pipeline of built-in metal bellows, comprise the pipeline body of being made by concrete or cement or slush or resin cement mixture, be provided with the metal bellows with the pipeline body coaxial line in the described pipeline body.
Described bellows by vertically in turn and circulation the crest section, the first height section, trough section and the second height section that connect consist of, described trough section offers trough section through hole.
Described crest section offers crest section through hole.
Described the first height section and the second height Duan Jun offer height section through hole.
The total surface area of the crest section through hole on the described crest section is less than the total surface area of the trough section through hole on the trough section.
The total surface area of the height section through hole on described one first height section or the second height section is less than the total surface area of the crest section through hole on the crest section.
Be arranged with at least one pair of in the pipeline body along the steel band of pipeline body axial direction.
Adopt technique scheme, the metal bellows of setting and pipeline body coaxial line in the pipeline body that concrete or cement or slush or resin cement mixture are made, the intensity of so abundant enhancing pipeline body and ring stiffness.Offer some trough section through holes in the trough section, offer crest section through hole in the crest section, offer height section through hole in the first height section or the second height section; Can fully reduce metallic material like this, alleviate the weight of whole bellows and reduce the cost of production of bellows.The total surface area of the crest section through hole on crest section is less than the total surface area of the height section through hole on the total surface area of the trough section through hole on the trough section, first height section or the second height section total surface area less than the trough section through hole on the trough section; Be according to the in use stressed further restriction that varies in size and carry out of different sections like this, thereby the intensity of guaranteeing whole bellows is not subjected to large impact.Better reinforing function is played in the setting of steel band.
Description of drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is that the utility model is axially cut off the structural representation after trailing.
Embodiment
As depicted in figs. 1 and 2, a kind of engineering of the present utility model pipeline of built-in metal bellows, comprise the pipeline body 8 of being made by concrete or cement or slush or resin cement mixture, be provided with the metal bellows with pipeline body 8 coaxial lines in the pipeline body 8.
Bellows by vertically in turn and circulation the crest section 1, the first height section 2, trough section 3 and the second height section 4 that connect consist of, trough section 3 offers trough section through hole 5.
Crest section 1 offers the total surface area of the crest section through hole 6 on 6, one crest sections 1 of crest section through hole less than the total surface area of the trough section through hole 5 on the trough section 3.Be that the density of crest section through hole 6 is less than the density of trough section through hole 5.
The first height section the 2 and second height section 4 all offers the total surface area of the height section through hole 7 on 7, one first height sections of height section through hole the 2 or second height section 4 less than the total surface area of the crest section through hole 6 on the crest section 1.Namely the density of height section through hole 7 is less than the density of crest section through hole 6.
The shape of trough section through hole 5, crest section through hole 6 and height section through hole 7 can be circular, oval or other shape.
Be arranged with at least one pair of in the pipeline body 8 along the steel band 9 of pipeline body 8 axial directions, wherein steel band 9 is positioned at the inboard of metal bellows, and another root steel band 9 is positioned at the outside of metal bellows, steel band 9 and bellows-welding.
The pipeline body 8 interior settings that concrete or cement or slush or resin cement mixture are made and the metal bellows of pipeline body 1 coaxial line, the intensity of so abundant enhancing pipeline body 8 and ring stiffness.Offer trough section through hole 5 in trough section 3, offer crest section through hole 6 in crest section 1, offer height section through hole 7 in the first height section the 2 or second height section 4; Can fully reduce metallic material like this, alleviate the weight of whole bellows and reduce the cost of production of bellows.The total surface area of the crest section through hole 6 on crest section 1 is less than the total surface area of the height section through hole 7 on the total surface area of the trough section through hole 5 on the trough section 3, the first height section 2 or second height section 4 total surface area less than the crest section through hole 6 on the crest section 1; Be according to the in use stressed further restriction that varies in size and carry out of different sections like this, thereby the intensity of guaranteeing whole bellows is not subjected to large impact.

Claims (7)

1. an engineering is with the pipeline of built-in metal bellows, comprises the pipeline body of being made by concrete or cement or slush or resin cement mixture, it is characterized in that: be provided with the metal bellows with the pipeline body coaxial line in the described pipeline body.
2. a kind of engineering according to claim 1 is with the pipeline of built-in metal bellows, it is characterized in that: described bellows by vertically in turn and circulation the crest section, the first height section, trough section and the second height section that connect consist of, described trough section offers trough section through hole.
3. a kind of engineering according to claim 2 is with the pipeline of built-in metal bellows, and it is characterized in that: described crest section offers crest section through hole.
4. a kind of engineering according to claim 3 is with the pipeline of built-in metal bellows, and it is characterized in that: described the first height section and the second height Duan Jun offer height section through hole.
According to claim 3 or 4 described a kind of engineerings with the pipeline of built-in metal bellowss, it is characterized in that: the total surface area of the crest section through hole on the described crest section is less than the total surface area of the trough section through hole on the trough section.
6. a kind of engineering according to claim 4 is with the pipeline of built-in metal bellows, and it is characterized in that: the total surface area of the height section through hole on described one first height section or the second height section is less than the total surface area of the crest section through hole on the crest section.
7. a kind of engineering according to claim 1 is characterized in that: be arranged with at least one pair of in the pipeline body along the steel band of pipeline body axial direction with the pipeline of built-in metal bellows.
CN 201220500026 2012-09-28 2012-09-28 Pipeline provided with built-in metal bellows and used for engineering Expired - Fee Related CN202812511U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220500026 CN202812511U (en) 2012-09-28 2012-09-28 Pipeline provided with built-in metal bellows and used for engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220500026 CN202812511U (en) 2012-09-28 2012-09-28 Pipeline provided with built-in metal bellows and used for engineering

Publications (1)

Publication Number Publication Date
CN202812511U true CN202812511U (en) 2013-03-20

Family

ID=47871381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220500026 Expired - Fee Related CN202812511U (en) 2012-09-28 2012-09-28 Pipeline provided with built-in metal bellows and used for engineering

Country Status (1)

Country Link
CN (1) CN202812511U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016058275A1 (en) * 2014-10-14 2016-04-21 南京联众建设工程技术有限公司 Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall thereof and manufacturing method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016058275A1 (en) * 2014-10-14 2016-04-21 南京联众建设工程技术有限公司 Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall thereof and manufacturing method thereof
US10030792B2 (en) 2014-10-14 2018-07-24 Nanjing Lianzhong Construction Engineering Technology Co., Ltd. Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN103410247B (en) A kind of both sides connection side not contourly opens vertical seam steel plate shear force wall to putting more energy into
CN202812511U (en) Pipeline provided with built-in metal bellows and used for engineering
CN204780883U (en) Prefab with hollow structure
CN203479036U (en) Ring drilling machine of rotary kiln
CN104420464A (en) Preparation method of prestressed concrete square pile
CN204609313U (en) The auxiliaring bucket of a kind of well room body of wall concreting
CN202644788U (en) A constructional hollow wall
CN203432331U (en) Upper ripping fence of trolley of sintering machine
CN207122659U (en) Wire harness fixture block
CN202733215U (en) Metal pipe arranged in plastic double-wall corrugated pipeline
CN204724846U (en) Spindle-type caput stopper
CN205225305U (en) Cover tube swelling formula lets pressure stock
CN204384122U (en) A kind of iron and steel production hopper
CN204186984U (en) A kind of pressure water storage barrel exterior bowl
CN204921625U (en) Take nut of back taper body
CN204396498U (en) Produce seamless steel pipe cold drawing die
CN201954134U (en) Metal pipe billet
CN202484036U (en) Bolt member structure
CN203770792U (en) Ball valve cast piece
CN203907050U (en) Wear-resisting plastic water pipe
CN204355671U (en) Screw conveyer of shield machine structure
CN104096803A (en) Turbine mould shell structure
CN202284695U (en) High-strength hoop iron
CN202521113U (en) High-strength and wear-resistant concrete mixer composite pipe
CN202091306U (en) Embedded-type connecting part

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZHAN KEJUN

Free format text: FORMER OWNER: ZHAN CHUNSHENG

Effective date: 20140828

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 450000 ZHENGZHOU, HENAN PROVINCE TO: 215101 SUZHOU, JIANGSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20140828

Address after: Wuzhong District Mudu town of Suzhou city in Jiangsu province 215101 Suxiang garden building 4-7 room 604

Patentee after: Zhan Kejun

Address before: 450000, No. five, building fifteen, No.1 Hospital, No. four, No. 1 road, Zhengzhou, Henan

Patentee before: Zhan Chunsheng

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130320

Termination date: 20170928