CN202745854U - Hard shut-in simulation experiment device for petroleum drilling - Google Patents
Hard shut-in simulation experiment device for petroleum drilling Download PDFInfo
- Publication number
- CN202745854U CN202745854U CN 201220300768 CN201220300768U CN202745854U CN 202745854 U CN202745854 U CN 202745854U CN 201220300768 CN201220300768 CN 201220300768 CN 201220300768 U CN201220300768 U CN 201220300768U CN 202745854 U CN202745854 U CN 202745854U
- Authority
- CN
- China
- Prior art keywords
- pressure sensor
- flow meter
- electromagnetic valve
- pvc pipe
- centrifugal pump
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a hard shut-in simulation experiment device for petroleum drilling, which is applied to the data acquisition of hard shut-in simulation experiments for petroleum drilling. The device is characterized in that a water outlet of a water tank is connected with an inlet of a centrifugal pump through a pipeline; an outlet of the centrifugal pump is sequentially connected with a check valve, a first pressure sensor and a first flowmeter through a PVC (polyvinyl chloride) pipe; the outlet end of the first flowmeter is sequentially connected with a second pressure sensor, a first electromagnetic valve, a third pressure sensor and a second electromagnetic valve through the PVC pipe; the outlet end of the second electromagnetic valve is connected with the inlet end of the second flowmeter through the PVC pipe, and the outlet end of the second flowmeter is connected with the PVC pipe. The device disclosed by the utility model has the effects that the simulation and determination of water-hammer pressure of drilling under the conditions of different flows and different shut-in times can be realized, the hard shut-in simulation on overflow and blowout working conditions can be realized by using conventional and normal pressure equipment without carrying out determination by using actual working conditions; and the device has the advantages of low cost, easy determination, and capability of reducing project risks, and the like.
Description
Technical field
The utility model relates to the petroleum drilling technology field, and particularly a kind of drilling well ground experiment device is a kind of oil drilling hard closing analogue experiment installation.
Background technology
At present, in the petroleum engineering well drilling process, when overflow or blowout occur, can produce the sudden change of pressure jump and flow during owing to closing well.And these two kinds of sudden changes all can produce the very large water hammer of harm.Because the water attack meeting makes superpressure in preventer inside and the well at the very large pressure of moment generation, and easy link (such as the casing shoe place) generation pressure leakage stratum accident the weakest in well, thereby normal wellbore construction affected.Therefore, water attack problem obtains paying attention to more and more widely.
The scene shows: if take " soft closing " mode, although the surge pressure during closing well is less to formation damage, but owing to can cause the further intrusion well of formation fluid, cause the generation of parasitic pressure drop, thereby increase stratum, casing shoe place by the danger of pressure break, be unfavorable for next step kill job; If take " hard closing ", surge pressure will impact preventer when then worrying closing well.Want reasonable selection closing well mode and just need to carry out ground experiment, the water attack problem when making closing well clear.Because a bite oil well is very high at cost, and hard closing might damage oil well, therefore, should not measure the surge pressure of closing well process in drilling process.
Method and the device of the Water Hammer that well head and casing shoe place produce when now, energy Accurate Determining hard closing being arranged not yet.
The utility model content
The purpose of this utility model is: a kind of oil drilling hard closing analogue experiment installation is provided, can carries out carrying out the test of hard closing surge pressure on ground when overflow and blowout.Use the simulation hard closing under the principle of similitude to avoid risk, save cost, and be used for instructing drilling well production.
The technical solution adopted in the utility model is: oil drilling hard closing analogue experiment installation, comprise water tank, centrifugal pump, flap valve, the first pressure sensor, first flow meter, the second pressure sensor, the first electromagnetic valve, the 3rd pressure sensor, the second electromagnetic valve and the second flow meter, it is characterized in that: the entrance that connects centrifugal pump at the delivery port of water tank by pipeline; Centrifugal delivery side of pump connects flap valve, the first pressure sensor and first flow meter successively by pvc pipe; The port of export of first flow meter connects the second pressure sensor, the first electromagnetic valve, the 3rd pressure sensor and the second electromagnetic valve successively by pvc pipe; The port of export of the second electromagnetic valve connects the arrival end of the second flow meter by pvc pipe, and the port of export of the second flow meter connects pvc pipe.
Described the first pressure sensor, first flow meter, the second pressure sensor, the 3rd pressure sensor and the flow meter of being connected connect the computer data acquiring card by holding wire.
The operating principle of summary oil drilling hard closing analogue experiment installation.Consult Fig. 1.Centrifugal pump 2 obtains fluid and it is pumped in the pvc pipe from water tank 1, flap valve 3, electromagnetic valve 7 and electromagnetic valve 9 are all opened at this moment, show value electromagnetic valve for adjusting 9 according to flow meter 10, make the flow in the pipeline meet the flow rate calculation value that draws according to the principle of similitude, the measured value of record pressure sensor 8.Then the simulation closed-in time that calculates according to the principle of similitude, shut electromagnetic valve 7 with the measured value of data collecting card record pressure sensor 6, pressure sensor 4 and flow meter 5, and carries out the water attack analog computation of hard closing according to the principle of similitude.When changing, water attack time and flow repeat above-mentioned steps.Use centrifugal pump, pressure sensor, flow meter and choke valve to realize the adjusting of flow, mensuration and the simulation of surge pressure.Use the common PVC pipe die to intend well casing, and install back pressure valve, pressure sensor, choke valve and flow meter at pipeline.But choke valve flexible modulation flow, flow and pressure in pressure sensor and the flow transmitter energy Accurate Determining pipeline, and can use capture card to carry out data acquisition.
The beneficial effects of the utility model: the utility model oil drilling hard closing analogue experiment installation, can realize different flow, the drilling well water attack pressure simulation of different closed-in times mensuration, can use routine, normal pressure equipment to realize the hard closing simulation is carried out in overflow and blowout operating mode, and measure (actual condition also be difficult to measure) without actual condition, have cheap, be easy to measure, reduce the advantages such as engineering risk.
Description of drawings
Fig. 1 is the utility model oil drilling hard closing analogue experiment installation structural representation.
Among the figure, 1-water tank, 2-centrifugal pump, 3-flap valve, 4-the first pressure sensor, 5-first flow meter, 6-the second pressure sensor, 7-the first electromagnetic valve, 8-the 3rd pressure sensor, 9-the second electromagnetic valve, 10-the second flow meter.
The specific embodiment
Embodiment 1: take an oil drilling hard closing analogue experiment installation as example, the utility model is described in further detail.
Consult Fig. 1.The utility model oil drilling hard closing analogue experiment installation comprises water tank 1, centrifugal pump 2, flap valve 3, the first pressure sensor 4, first flow meter 5, the second pressure sensor 6, the first electromagnetic valve 7, the 3rd pressure sensor 8, the second electromagnetic valve 9 and the second flow meter 10.The entrance that connects centrifugal pump 2 at the delivery port of water tank 1 by pipeline.The outlet of centrifugal pump 2 connects flap valve 3, the first pressure sensor 4 and first flow meter 5 successively by pvc pipe.The port of export of first flow meter 5 connects the second pressure sensor 6, the first electromagnetic valve 7, the 3rd pressure sensor 8 and the second electromagnetic valve 9 successively by pvc pipe.The port of export of the second electromagnetic valve 9 connects the arrival end of the second flow meter 10 by pvc pipe, and the port of export of the second flow meter 10 connects pvc pipe.The first pressure sensor 4, first flow meter 5, the second pressure sensor 6, the 3rd pressure sensor 8 and the flow meter 10 of being connected connect the computer data acquiring card by holding wire.
Claims (2)
1. oil drilling hard closing analogue experiment installation, comprise water tank (1), centrifugal pump (2), flap valve (3), the first pressure sensor (4), first flow meter (5), the second pressure sensor (6), the first electromagnetic valve (7), the 3rd pressure sensor (8), the second electromagnetic valve (9) and the second flow meter (10), it is characterized in that: the entrance that connects centrifugal pump (2) at the delivery port of water tank (1) by pipeline; The outlet of centrifugal pump (2) connects flap valve (3), the first pressure sensor (4) and first flow meter (5) successively by pvc pipe; The port of export of first flow meter (5) connects the second pressure sensor (6), the first electromagnetic valve (7), the 3rd pressure sensor (8) and the second electromagnetic valve (9) successively by pvc pipe; The port of export of the second electromagnetic valve (9) connects the arrival end of the second flow meter (10) by pvc pipe, and the port of export of the second flow meter (10) connects pvc pipe.
2. oil drilling hard closing analogue experiment installation according to claim 1 is characterized in that: described the first pressure sensor (4), first flow meter (5), the second pressure sensor (6), the 3rd pressure sensor (8) and the flow meter (10) of being connected connect the computer data acquiring card by holding wire.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220300768 CN202745854U (en) | 2012-06-21 | 2012-06-21 | Hard shut-in simulation experiment device for petroleum drilling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220300768 CN202745854U (en) | 2012-06-21 | 2012-06-21 | Hard shut-in simulation experiment device for petroleum drilling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202745854U true CN202745854U (en) | 2013-02-20 |
Family
ID=47705271
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220300768 Expired - Fee Related CN202745854U (en) | 2012-06-21 | 2012-06-21 | Hard shut-in simulation experiment device for petroleum drilling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202745854U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104851268A (en) * | 2015-04-30 | 2015-08-19 | 西南石油大学 | Blowout emergency drill simulation system and blowout emergency drill simulation method |
CN106468164A (en) * | 2015-08-21 | 2017-03-01 | 崔磊 | Shale gas pressure break sleeve pipe collapse resistance designs |
CN107035327A (en) * | 2017-05-09 | 2017-08-11 | 中国石油大学(北京) | The method and apparatus for determining transient surge pressure during start and stop pump |
CN110131588A (en) * | 2019-05-21 | 2019-08-16 | 珠江水利委员会珠江水利科学研究院 | Long range water supply line water hammer experimental rig |
CN110487475A (en) * | 2018-05-15 | 2019-11-22 | 中国石油化工股份有限公司 | Pressure monitoring device and method between a kind of foam slurry waiting-on-cement |
CN114566072A (en) * | 2022-02-25 | 2022-05-31 | 中国海洋石油集团有限公司 | Blowout emergency drilling simulation system |
-
2012
- 2012-06-21 CN CN 201220300768 patent/CN202745854U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104851268A (en) * | 2015-04-30 | 2015-08-19 | 西南石油大学 | Blowout emergency drill simulation system and blowout emergency drill simulation method |
CN106468164A (en) * | 2015-08-21 | 2017-03-01 | 崔磊 | Shale gas pressure break sleeve pipe collapse resistance designs |
CN107035327A (en) * | 2017-05-09 | 2017-08-11 | 中国石油大学(北京) | The method and apparatus for determining transient surge pressure during start and stop pump |
CN107035327B (en) * | 2017-05-09 | 2018-06-01 | 中国石油大学(北京) | Determine start and stop pump during transient surge pressure method and apparatus |
CN110487475A (en) * | 2018-05-15 | 2019-11-22 | 中国石油化工股份有限公司 | Pressure monitoring device and method between a kind of foam slurry waiting-on-cement |
CN110131588A (en) * | 2019-05-21 | 2019-08-16 | 珠江水利委员会珠江水利科学研究院 | Long range water supply line water hammer experimental rig |
CN114566072A (en) * | 2022-02-25 | 2022-05-31 | 中国海洋石油集团有限公司 | Blowout emergency drilling simulation system |
CN114566072B (en) * | 2022-02-25 | 2024-04-19 | 中国海洋石油集团有限公司 | Blowout emergency drilling simulation system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202745854U (en) | Hard shut-in simulation experiment device for petroleum drilling | |
CN105114043B (en) | A kind of system and method for improving deep water gas field gaslift water pumping gas production recovery ratio | |
CN205301140U (en) | Simulation oil pipe corrodes visual device of scale deposit | |
CN110325705A (en) | System and method for operating blowout preventer system | |
MX2009013401A (en) | Hydrocarbons. | |
CN103865500A (en) | Liquid rubber plug and method for pulling out coiled tubing velocity pipe column by using liquid rubber plug under pressure | |
CN204532297U (en) | A kind of oil-field water injection device | |
CN202194628U (en) | Integrated device of Christmas tree and gas well ground construction assembly skid | |
CN103335762B (en) | Performance test method and performance test device of high-power fracturing pump truck | |
CN202228038U (en) | Pipe string for plugging shallow-layer sleeve leakage water injection well | |
CN114383554B (en) | Submarine pipeline length calculation method for underwater HIPPS downstream high-pressure section | |
CN102706751B (en) | One is pipe laying multifunctional detecting device vertically | |
CN208294499U (en) | A kind of normal pressure shale gas water drainage gas production device | |
CN104405364B (en) | A kind of evaluation method and device for oil well production characteristics | |
CN204098872U (en) | Electric immersible pump well tubing string and electric immersible pump well | |
CN211785431U (en) | Drag reducer evaluation instrument for convenient slickwater fracturing | |
CN201835785U (en) | Oil-water well device capable of automatically controlling pressure relief and liquid discharge as well as pumping discharged liquid to production pipeline | |
CN203603834U (en) | Underground shooting-type plugging tool for coiled tubing | |
CN203925432U (en) | A kind of production tree device | |
CN202108480U (en) | Constant pressure gas discharge wellhead device of oil well sleeve | |
CN205135581U (en) | Tubular column is annotated to digital branch of flexible composite oil pipe in pit | |
CN202745840U (en) | High-efficiency injection pipe string for large-inclination well | |
CN203145892U (en) | Pressure-building prevention device for heavy oil well | |
CN207017985U (en) | Stope adopts the pre- gas-removing shallow bore hole hydraulic fracturing device of section in advance | |
CN204344067U (en) | A kind of vertical double hose submerged production tree device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130220 Termination date: 20210621 |
|
CF01 | Termination of patent right due to non-payment of annual fee |