CN202484438U - Pipelaying vessel pipe conveying device - Google Patents

Pipelaying vessel pipe conveying device Download PDF

Info

Publication number
CN202484438U
CN202484438U CN 201220054806 CN201220054806U CN202484438U CN 202484438 U CN202484438 U CN 202484438U CN 201220054806 CN201220054806 CN 201220054806 CN 201220054806 U CN201220054806 U CN 201220054806U CN 202484438 U CN202484438 U CN 202484438U
Authority
CN
China
Prior art keywords
pipe
oil cylinder
tooth bar
roll
piston rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220054806
Other languages
Chinese (zh)
Inventor
吴建民
王定亚
徐晓鹏
孟祥丽
蔡娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoji Oilfield Machinery Co Ltd
Original Assignee
Baoji Oilfield Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoji Oilfield Machinery Co Ltd filed Critical Baoji Oilfield Machinery Co Ltd
Priority to CN 201220054806 priority Critical patent/CN202484438U/en
Application granted granted Critical
Publication of CN202484438U publication Critical patent/CN202484438U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)
  • Pipeline Systems (AREA)

Abstract

The utility model discloses a pipelaying vessel pipe conveying device. Two racks are arranged on a deck along the radial direction of a pipe; one end of the rack is provided with a position sensor and a locking block; two sets of gear wheels are arranged on each rack; one set of gears on each rack is in transmission connection with a travel motor; an oil cylinder is connected with each gear wheel respectively; the upper end of the piston rod of one oil cylinder is provided with a back-up roll; the upper end of the piston rod of the other oil cylinder is provided with a power roll, and the lower end of the piston rod is provided with a weight sensor; the power roll is in transmission connection with a driving motor; and an adjusting rod is connected between the two oil cylinders on each rack. The device provided by the utility model adopts the method of orbit conveying and roller moving, thereby efficiently solving the problems of conveying the pipe to an operating line and abutting joint on the operating line and realizing the automation of pipeline; and the pipelaying vessel pipe conveying device has high efficiency, simpleness in operation, high safety and stable pipe conveying state, thereby saving resources.

Description

Pipe laying barge pipe conveying means
Technical field
The utility model belongs to offshore oil engineering equipment manufacturing technology field, relates to a kind of pipe laying barge pipe conveying means.
Background technique
Current; The offshore oil natural-gas transfer pipeline adopts pipe laying barge to lay mostly; Submarine pipeline engineering is the important component part in the middle of the oil and gas development, and is along with offshore oil exploration and exploitation constantly develops to darker waters, more and more high to the requirement of pipe laying barge and pipe laying barge pipe-laying equipment; The main effect of this device is after being sent on the pipelaying work line welding on the pipe laying barge deck as requested, to transfer to the seabed to oil and gas pipes; Not only to satisfy the needs of ability, and will satisfy the needs of efficient, so require the automaticity of pipe laying barge operation more and more high.
Present pipe laying barge pipeline transmits and leans on equipment manual operations such as cantilever hangs, slide rail to realize basically, not only to operator's requirement height, and inefficiency, labor intensity is big.
Summary of the invention
The purpose of the utility model provides a kind of pipe laying barge pipe conveying means, has solved the available technology adopting manual operation, has the requirement height to operator, and inefficiency, the problem that labor intensity is big.
The technological scheme that the utility model adopted is; A kind of pipe laying barge pipe conveying means; Radially be provided with the twice tooth bar along pipe above deck; One termination of tooth bar is provided with position transducer and latch, and two groups of gears are installed on the per pass tooth bar, and one group of gear and running motor on the per pass tooth bar are in transmission connection; Each gear upwards is connected with an oil cylinder separately; The piston rod upper end of one of them oil cylinder is provided with back-up roll; The piston rod upper end of another oil cylinder is provided with live roll, and this piston-rod lower end is provided with weighing transducer, and live roll and drive motor are in transmission connection; Be connected with an adjustable lever between two oil cylinders on the per pass tooth bar.
The beneficial effect of the utility model is; Lay operation with Yu Haiyang submarine oil and natural gas line; Adopt " track travel and roller roll " structural type and PLC technology, can not only realize the automated job requirement, and have the characteristics of highly effective and safe; Realize the automated job that pipe transmits, had application foundation widely.
Description of drawings
Fig. 1 is pipe laying barge pipe conveying means (a moving radially) structural representation;
Fig. 2 is pipe laying barge pipe conveying means (a moving axially) structural representation.
Among the figure, 1. back-up roll; 2. live roll; 3. drive motor; 4. adjustable lever; 5. oil cylinder; 6. gear; 7. tooth bar; 8. position transducer; 9. latch; 10. weighing transducer; 11. running motor; 12. hydraulic station; 13.PLC system.
Embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is elaborated.
With reference to Fig. 1, Fig. 2; The pipe laying barge pipe conveying means structure of the utility model is; Radially be provided with twice tooth bar 7 along pipe above deck; One termination of tooth bar 7 is provided with position transducer 8 and latch 9, and two groups of gears 6 are installed on the per pass tooth bar 7, and the one group of gear 6 on the per pass tooth bar 7 is in transmission connection with running motor 11; Each gear 6 upwards is connected with an oil cylinder 5 separately; The piston rod upper end of one of them oil cylinder 5 is provided with back-up roll 1; The piston rod upper end of another oil cylinder 5 is provided with live roll 2, and this piston-rod lower end is provided with weighing transducer 10, and live roll 2 is in transmission connection with drive motor 3; Be connected with an adjustable lever 4 between two oil cylinders 5 on the per pass tooth bar 7, all oil cylinders 5 all are connected with hydraulic station 12; Position transducer 8 all is connected with PLC system 13 with weighing transducer 10, drive motor 3, running motor 11, hydraulic station 12, accepts unified control.
Back-up roll 1 also can be provided with the transmission device of oneself, promptly changes live roll 2 structures into, and this moment, two live rolls, 2 composition " V " types supported.Back-up roll 1 moves axially pipe with live roll 2 frictionallies, and the surface of two groups of rollers is wear-resisting nonmetallic composite manufacturings, and can exchange and change.
Adjustable lever 4 is in order to the distance between adjustable support roller 1 and the live roll 2, and to adapt to the conveying of different-diameter pipe, adjustable lever 4 can be the threads of lead screw nut structure, also can be the telescopic oil cylinder structure; Oil cylinder 5 makes the pipe autobalance on a plurality of conveying meanss in the middle of transporting pipe, motion steadily when pipe misalignment production line, can align pipe by human intervention adjusting oil cylinder 5; Latch 9 can be installed any position on tooth bar 7, is used for regulating the distance that moves radially, and when position transducer 8 inefficacies or fault, forces gear 6 to shut down, and avoids having an accident.
Move radially and rely on gear 6 engagement rolling on tooth bar 7 to realize, also can be by roller scrolling realization on slide rail, or realize by their combination.Two group oil cylinders 5 on the per pass tooth bar 7 are supported roller 1 and live roll 2 respectively, need not adjust height when the pipe laying production line and reach correct time, and oil cylinder 5 can remove the employing support and replace to reduce cost.
Position transducer 8 and weighing transducer 10, two sensors can also be replaced realizing the control of PLC by position limit switch.
Moving by drive motor 3 and running motor 11 of the different direction of pipe conveying means accomplished, and two groups of motors can be replaced by motor, and motor or motor are slowed down by epicyclic gearbox, also can be zero motor or motor direct-drive.
Pipe laying barge pipe conveying means needs at least two covers could accomplish the conveying of pipe; Site operation will be arranged the pipe conveying means according to the length of pipelaying work line and the quantity of welding station; By many covers even the common transportation of accomplishing single pipe and welding rear line of tens of cover; Be the digital control realization automation mechanized operation of PLC, have the highly effective and safe characteristic of low energy consumption.
The pipe laying barge pipe conveying means of the utility model; Its working principle is: this device is arranged on the boat deck, and on pipe was hung oneself " V " type that the back-up roll 1 that is placed down in this device and live roll 2 form by the pipe loop wheel machine from cargo ship, pipe gravity made weighing transducer 10 picked up signal and controls the hydraulic station valve opening solenoid motor 11 of setting out away through the PLC system handles; Running motor 11 actuation gears 6 move on tooth bar 7; Thereby realize moving radially of pipe, when moving to the position of setting, position transducer 8 receives signal; PLC handles the closed electromagnetic valve running motor 11 of back instruction hydraulic station, and pipe moves radially and stops; The PLC electromagnetic valve of instruction is opened drive motor 3 then, and live roll 2 entrys into service axially move pipe under frictional force action, and after pipe shifted out conveying means, weighing transducer 10 sends closed drive motor 3 signals, and live roll 2 shuts down; The PLC electromagnetic valve of instruction starts running motor 11 actuation gears 6 and on tooth bar 7, moves then; When this device turns back to initial, set position; The position transducer 8 instruction running motors 11 of tooth bar 7 the other ends shut down, and accomplish the transport of a pipe this moment, when next root pipe is put; Repeat above-mentioned action, the transmission work of next pipe is accomplished in circulation successively.
The pipe laying barge pipe conveying means of the utility model utilizes this device hydraulic transmission advantage stably, can realize that the horizontal and vertical above deck orientation of pipeline moves; This model utility is taked the method for " track send; roller moves "; I.e. " track travel mechanism is responsible for moving radially, and powered rollers friction realizes moving axially " form efficiently solves carrying and the problem of docking on production line to production line of pipe; And, have efficient height, simple to operate, safe, characteristics such as the pipe shipping situation is steady through sensor and PLC realization line transportation automatically working.The utility model adopts the digital control hydraulic electromagnetic valve technology of PLC, has automation, intelligentized characteristics, and when this device was gone up no pipe, this device did not start and is in holding state, has reduced consumption, has practiced thrift the energy.

Claims (3)

1. pipe laying barge pipe conveying means; Its characteristics are: radially be provided with twice tooth bar (7) along pipe above deck; One termination of tooth bar (7) is provided with position transducer (8) and latch (9); Two groups of gears (6) are installed on the per pass tooth bar (7), and the one group of gear (6) on the per pass tooth bar (7) is in transmission connection with running motor (11); Each gear (6) upwards is connected with an oil cylinder (5) separately; The piston rod upper end of one of them oil cylinder (5) is provided with back-up roll (1); The piston rod upper end of another oil cylinder (5) is provided with live roll (2); This piston-rod lower end is provided with weighing transducer (10), and live roll (2) is in transmission connection with drive motor (3); Be connected with an adjustable lever (4) between two oil cylinders (5) on the per pass tooth bar (7).
2. pipe laying barge pipe conveying means according to claim 1, its characteristics are: described all oil cylinders (5) all are connected with hydraulic station (12); Position transducer (8) all is connected with PLC system (13) with weighing transducer (10), drive motor (3), running motor (11), hydraulic station (12).
3. pipe laying barge pipe conveying means according to claim 1, its characteristics are: described back-up roll (1) is provided with the transmission device of oneself in addition.
CN 201220054806 2012-02-20 2012-02-20 Pipelaying vessel pipe conveying device Expired - Fee Related CN202484438U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220054806 CN202484438U (en) 2012-02-20 2012-02-20 Pipelaying vessel pipe conveying device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220054806 CN202484438U (en) 2012-02-20 2012-02-20 Pipelaying vessel pipe conveying device

Publications (1)

Publication Number Publication Date
CN202484438U true CN202484438U (en) 2012-10-10

Family

ID=46958859

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220054806 Expired - Fee Related CN202484438U (en) 2012-02-20 2012-02-20 Pipelaying vessel pipe conveying device

Country Status (1)

Country Link
CN (1) CN202484438U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943924A (en) * 2012-10-29 2013-02-27 中国海洋石油总公司 Pipe conveying device with automatic correcting function
CN108621317A (en) * 2017-03-22 2018-10-09 中天科技精密材料有限公司 Pipe cutting equipment and cutting method
CN109703622A (en) * 2019-01-31 2019-05-03 山东能源重装集团泰装工程装备制造有限公司 Two-way self-tipping type pipe carrying truck in a kind of tunnel
CN110091102A (en) * 2019-05-24 2019-08-06 薛溪健 A kind of auxiliary docking facilities for chemical pipeline welding
CN110509100A (en) * 2019-08-31 2019-11-29 云南联塑科技发展有限公司 A kind of tubing mobile unit and the tubing mobile device with tubing mobile unit
CN110700214A (en) * 2019-11-11 2020-01-17 武汉理工大学 Oil spill treatment emergency ship based on bubble curtain technology
CN110789426A (en) * 2018-08-02 2020-02-14 中国石油天然气集团有限公司 Pipe conveying and distributing vehicle for pipeline construction
CN110886903A (en) * 2019-11-11 2020-03-17 武汉理工大学 Rubber hose laying device
CN112360554A (en) * 2020-09-18 2021-02-12 燕山大学 Automatic installation operation vehicle for hanging pipeline of coal mine tunnel
CN114215963A (en) * 2021-12-04 2022-03-22 广东盈辉建设工程有限公司 Construction method for water supply and drainage engineering of building
CN117722533A (en) * 2024-02-07 2024-03-19 临汾淼森能源工程有限公司 Auxiliary equipment for laying thermal pipeline

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943924A (en) * 2012-10-29 2013-02-27 中国海洋石油总公司 Pipe conveying device with automatic correcting function
CN108621317A (en) * 2017-03-22 2018-10-09 中天科技精密材料有限公司 Pipe cutting equipment and cutting method
CN110789426A (en) * 2018-08-02 2020-02-14 中国石油天然气集团有限公司 Pipe conveying and distributing vehicle for pipeline construction
CN109703622A (en) * 2019-01-31 2019-05-03 山东能源重装集团泰装工程装备制造有限公司 Two-way self-tipping type pipe carrying truck in a kind of tunnel
CN110091102A (en) * 2019-05-24 2019-08-06 薛溪健 A kind of auxiliary docking facilities for chemical pipeline welding
CN110509100A (en) * 2019-08-31 2019-11-29 云南联塑科技发展有限公司 A kind of tubing mobile unit and the tubing mobile device with tubing mobile unit
CN110509100B (en) * 2019-08-31 2024-06-11 云南联塑科技发展有限公司 Pipe moving unit and pipe moving device with same
CN110700214A (en) * 2019-11-11 2020-01-17 武汉理工大学 Oil spill treatment emergency ship based on bubble curtain technology
CN110886903A (en) * 2019-11-11 2020-03-17 武汉理工大学 Rubber hose laying device
CN112360554A (en) * 2020-09-18 2021-02-12 燕山大学 Automatic installation operation vehicle for hanging pipeline of coal mine tunnel
CN112360554B (en) * 2020-09-18 2022-03-11 燕山大学 Automatic installation operation vehicle for hanging pipeline of coal mine tunnel
CN114215963A (en) * 2021-12-04 2022-03-22 广东盈辉建设工程有限公司 Construction method for water supply and drainage engineering of building
CN114215963B (en) * 2021-12-04 2022-09-02 广东盈辉建设工程有限公司 Construction method for water supply and drainage engineering of building
CN117722533A (en) * 2024-02-07 2024-03-19 临汾淼森能源工程有限公司 Auxiliary equipment for laying thermal pipeline
CN117722533B (en) * 2024-02-07 2024-04-19 临汾淼森能源工程有限公司 Auxiliary equipment for laying thermal pipeline

Similar Documents

Publication Publication Date Title
CN202484438U (en) Pipelaying vessel pipe conveying device
CN104555769B (en) A kind of electric drive active compensation ocean winch
CN105173881A (en) Automatic cable conveying system
CN101715408B (en) Pipelaying vessel
CN204400501U (en) A kind of electric drive active compensation ocean winch
CN105417381A (en) Direct pump control type electro-hydraulic heaving compensation device
CN100569626C (en) Hydraulic pressure turn-over device of large-scale component
CN201410953Y (en) Carriage in-tunnel tube conveying installation car
CN105398965A (en) Video-ranging offshore platform crane heave compensation control system and method
CN201982799U (en) Cross traveling trolley for pipe laying ship
CN203270460U (en) Walking type continuous pushing system
CN102943924A (en) Pipe conveying device with automatic correcting function
CN204823445U (en) Cable automatic conveying system
CN102582803A (en) Hydraulic lifting roller shipping process for ultra-large marine structure
CN203877758U (en) Pushing system of rail clamping device
CN204000817U (en) The large-scale counterweight block privileged sites of vertical ship lift move assembling device
CN100528495C (en) Robot electric cable propeller based on water-dressing method for cable operation
CN103241683B (en) Under a kind of ocean pipeline balance weight production line, the rail mounted of pipe lifts pipe device
CN102530521A (en) Stepping type pipeline arranging device
CN105587275A (en) Full automatic rod transmission mechanism
CN103851135A (en) High-power double-speed-ratio gearbox
CN203296708U (en) Drilling machine moving system with hydraulic friction disk used for braking
CN203461721U (en) Tail lifting equipment
CN203682928U (en) Electric hydraulic lifting device
CN201857220U (en) Dual-portal hoisting equipment with high hoisting capacity and capable of advancing horizontally and jacking vertically and automatically

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Beijing gem Offshore Petroleum Engineering Technology Co Ltd

Assignor: Baoji Petroleum Machinery Co., Ltd.

Contract record no.: 2014990000541

Denomination of utility model: Pipelaying vessel pipe conveying device

Granted publication date: 20121010

License type: Exclusive License

Record date: 20140714

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20150220

EXPY Termination of patent right or utility model