CN202484438U - Pipelaying vessel pipe conveying device - Google Patents
Pipelaying vessel pipe conveying device Download PDFInfo
- Publication number
- CN202484438U CN202484438U CN 201220054806 CN201220054806U CN202484438U CN 202484438 U CN202484438 U CN 202484438U CN 201220054806 CN201220054806 CN 201220054806 CN 201220054806 U CN201220054806 U CN 201220054806U CN 202484438 U CN202484438 U CN 202484438U
- Authority
- CN
- China
- Prior art keywords
- pipe
- oil cylinder
- tooth bar
- roll
- piston rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Earth Drilling (AREA)
- Pipeline Systems (AREA)
Abstract
The utility model discloses a pipelaying vessel pipe conveying device. Two racks are arranged on a deck along the radial direction of a pipe; one end of the rack is provided with a position sensor and a locking block; two sets of gear wheels are arranged on each rack; one set of gears on each rack is in transmission connection with a travel motor; an oil cylinder is connected with each gear wheel respectively; the upper end of the piston rod of one oil cylinder is provided with a back-up roll; the upper end of the piston rod of the other oil cylinder is provided with a power roll, and the lower end of the piston rod is provided with a weight sensor; the power roll is in transmission connection with a driving motor; and an adjusting rod is connected between the two oil cylinders on each rack. The device provided by the utility model adopts the method of orbit conveying and roller moving, thereby efficiently solving the problems of conveying the pipe to an operating line and abutting joint on the operating line and realizing the automation of pipeline; and the pipelaying vessel pipe conveying device has high efficiency, simpleness in operation, high safety and stable pipe conveying state, thereby saving resources.
Description
Technical field
The utility model belongs to offshore oil engineering equipment manufacturing technology field, relates to a kind of pipe laying barge pipe conveying means.
Background technique
Current; The offshore oil natural-gas transfer pipeline adopts pipe laying barge to lay mostly; Submarine pipeline engineering is the important component part in the middle of the oil and gas development, and is along with offshore oil exploration and exploitation constantly develops to darker waters, more and more high to the requirement of pipe laying barge and pipe laying barge pipe-laying equipment; The main effect of this device is after being sent on the pipelaying work line welding on the pipe laying barge deck as requested, to transfer to the seabed to oil and gas pipes; Not only to satisfy the needs of ability, and will satisfy the needs of efficient, so require the automaticity of pipe laying barge operation more and more high.
Present pipe laying barge pipeline transmits and leans on equipment manual operations such as cantilever hangs, slide rail to realize basically, not only to operator's requirement height, and inefficiency, labor intensity is big.
Summary of the invention
The purpose of the utility model provides a kind of pipe laying barge pipe conveying means, has solved the available technology adopting manual operation, has the requirement height to operator, and inefficiency, the problem that labor intensity is big.
The technological scheme that the utility model adopted is; A kind of pipe laying barge pipe conveying means; Radially be provided with the twice tooth bar along pipe above deck; One termination of tooth bar is provided with position transducer and latch, and two groups of gears are installed on the per pass tooth bar, and one group of gear and running motor on the per pass tooth bar are in transmission connection; Each gear upwards is connected with an oil cylinder separately; The piston rod upper end of one of them oil cylinder is provided with back-up roll; The piston rod upper end of another oil cylinder is provided with live roll, and this piston-rod lower end is provided with weighing transducer, and live roll and drive motor are in transmission connection; Be connected with an adjustable lever between two oil cylinders on the per pass tooth bar.
The beneficial effect of the utility model is; Lay operation with Yu Haiyang submarine oil and natural gas line; Adopt " track travel and roller roll " structural type and PLC technology, can not only realize the automated job requirement, and have the characteristics of highly effective and safe; Realize the automated job that pipe transmits, had application foundation widely.
Description of drawings
Fig. 1 is pipe laying barge pipe conveying means (a moving radially) structural representation;
Fig. 2 is pipe laying barge pipe conveying means (a moving axially) structural representation.
Among the figure, 1. back-up roll; 2. live roll; 3. drive motor; 4. adjustable lever; 5. oil cylinder; 6. gear; 7. tooth bar; 8. position transducer; 9. latch; 10. weighing transducer; 11. running motor; 12. hydraulic station; 13.PLC system.
Embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is elaborated.
With reference to Fig. 1, Fig. 2; The pipe laying barge pipe conveying means structure of the utility model is; Radially be provided with twice tooth bar 7 along pipe above deck; One termination of tooth bar 7 is provided with position transducer 8 and latch 9, and two groups of gears 6 are installed on the per pass tooth bar 7, and the one group of gear 6 on the per pass tooth bar 7 is in transmission connection with running motor 11; Each gear 6 upwards is connected with an oil cylinder 5 separately; The piston rod upper end of one of them oil cylinder 5 is provided with back-up roll 1; The piston rod upper end of another oil cylinder 5 is provided with live roll 2, and this piston-rod lower end is provided with weighing transducer 10, and live roll 2 is in transmission connection with drive motor 3; Be connected with an adjustable lever 4 between two oil cylinders 5 on the per pass tooth bar 7, all oil cylinders 5 all are connected with hydraulic station 12; Position transducer 8 all is connected with PLC system 13 with weighing transducer 10, drive motor 3, running motor 11, hydraulic station 12, accepts unified control.
Back-up roll 1 also can be provided with the transmission device of oneself, promptly changes live roll 2 structures into, and this moment, two live rolls, 2 composition " V " types supported.Back-up roll 1 moves axially pipe with live roll 2 frictionallies, and the surface of two groups of rollers is wear-resisting nonmetallic composite manufacturings, and can exchange and change.
Move radially and rely on gear 6 engagement rolling on tooth bar 7 to realize, also can be by roller scrolling realization on slide rail, or realize by their combination.Two group oil cylinders 5 on the per pass tooth bar 7 are supported roller 1 and live roll 2 respectively, need not adjust height when the pipe laying production line and reach correct time, and oil cylinder 5 can remove the employing support and replace to reduce cost.
Moving by drive motor 3 and running motor 11 of the different direction of pipe conveying means accomplished, and two groups of motors can be replaced by motor, and motor or motor are slowed down by epicyclic gearbox, also can be zero motor or motor direct-drive.
Pipe laying barge pipe conveying means needs at least two covers could accomplish the conveying of pipe; Site operation will be arranged the pipe conveying means according to the length of pipelaying work line and the quantity of welding station; By many covers even the common transportation of accomplishing single pipe and welding rear line of tens of cover; Be the digital control realization automation mechanized operation of PLC, have the highly effective and safe characteristic of low energy consumption.
The pipe laying barge pipe conveying means of the utility model; Its working principle is: this device is arranged on the boat deck, and on pipe was hung oneself " V " type that the back-up roll 1 that is placed down in this device and live roll 2 form by the pipe loop wheel machine from cargo ship, pipe gravity made weighing transducer 10 picked up signal and controls the hydraulic station valve opening solenoid motor 11 of setting out away through the PLC system handles; Running motor 11 actuation gears 6 move on tooth bar 7; Thereby realize moving radially of pipe, when moving to the position of setting, position transducer 8 receives signal; PLC handles the closed electromagnetic valve running motor 11 of back instruction hydraulic station, and pipe moves radially and stops; The PLC electromagnetic valve of instruction is opened drive motor 3 then, and live roll 2 entrys into service axially move pipe under frictional force action, and after pipe shifted out conveying means, weighing transducer 10 sends closed drive motor 3 signals, and live roll 2 shuts down; The PLC electromagnetic valve of instruction starts running motor 11 actuation gears 6 and on tooth bar 7, moves then; When this device turns back to initial, set position; The position transducer 8 instruction running motors 11 of tooth bar 7 the other ends shut down, and accomplish the transport of a pipe this moment, when next root pipe is put; Repeat above-mentioned action, the transmission work of next pipe is accomplished in circulation successively.
The pipe laying barge pipe conveying means of the utility model utilizes this device hydraulic transmission advantage stably, can realize that the horizontal and vertical above deck orientation of pipeline moves; This model utility is taked the method for " track send; roller moves "; I.e. " track travel mechanism is responsible for moving radially, and powered rollers friction realizes moving axially " form efficiently solves carrying and the problem of docking on production line to production line of pipe; And, have efficient height, simple to operate, safe, characteristics such as the pipe shipping situation is steady through sensor and PLC realization line transportation automatically working.The utility model adopts the digital control hydraulic electromagnetic valve technology of PLC, has automation, intelligentized characteristics, and when this device was gone up no pipe, this device did not start and is in holding state, has reduced consumption, has practiced thrift the energy.
Claims (3)
1. pipe laying barge pipe conveying means; Its characteristics are: radially be provided with twice tooth bar (7) along pipe above deck; One termination of tooth bar (7) is provided with position transducer (8) and latch (9); Two groups of gears (6) are installed on the per pass tooth bar (7), and the one group of gear (6) on the per pass tooth bar (7) is in transmission connection with running motor (11); Each gear (6) upwards is connected with an oil cylinder (5) separately; The piston rod upper end of one of them oil cylinder (5) is provided with back-up roll (1); The piston rod upper end of another oil cylinder (5) is provided with live roll (2); This piston-rod lower end is provided with weighing transducer (10), and live roll (2) is in transmission connection with drive motor (3); Be connected with an adjustable lever (4) between two oil cylinders (5) on the per pass tooth bar (7).
2. pipe laying barge pipe conveying means according to claim 1, its characteristics are: described all oil cylinders (5) all are connected with hydraulic station (12); Position transducer (8) all is connected with PLC system (13) with weighing transducer (10), drive motor (3), running motor (11), hydraulic station (12).
3. pipe laying barge pipe conveying means according to claim 1, its characteristics are: described back-up roll (1) is provided with the transmission device of oneself in addition.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220054806 CN202484438U (en) | 2012-02-20 | 2012-02-20 | Pipelaying vessel pipe conveying device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220054806 CN202484438U (en) | 2012-02-20 | 2012-02-20 | Pipelaying vessel pipe conveying device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202484438U true CN202484438U (en) | 2012-10-10 |
Family
ID=46958859
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220054806 Expired - Fee Related CN202484438U (en) | 2012-02-20 | 2012-02-20 | Pipelaying vessel pipe conveying device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202484438U (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102943924A (en) * | 2012-10-29 | 2013-02-27 | 中国海洋石油总公司 | Pipe conveying device with automatic correcting function |
CN108621317A (en) * | 2017-03-22 | 2018-10-09 | 中天科技精密材料有限公司 | Pipe cutting equipment and cutting method |
CN109703622A (en) * | 2019-01-31 | 2019-05-03 | 山东能源重装集团泰装工程装备制造有限公司 | Two-way self-tipping type pipe carrying truck in a kind of tunnel |
CN110091102A (en) * | 2019-05-24 | 2019-08-06 | 薛溪健 | A kind of auxiliary docking facilities for chemical pipeline welding |
CN110509100A (en) * | 2019-08-31 | 2019-11-29 | 云南联塑科技发展有限公司 | A kind of tubing mobile unit and the tubing mobile device with tubing mobile unit |
CN110700214A (en) * | 2019-11-11 | 2020-01-17 | 武汉理工大学 | Oil spill treatment emergency ship based on bubble curtain technology |
CN110789426A (en) * | 2018-08-02 | 2020-02-14 | 中国石油天然气集团有限公司 | Pipe conveying and distributing vehicle for pipeline construction |
CN110886903A (en) * | 2019-11-11 | 2020-03-17 | 武汉理工大学 | Rubber hose laying device |
CN112360554A (en) * | 2020-09-18 | 2021-02-12 | 燕山大学 | Automatic installation operation vehicle for hanging pipeline of coal mine tunnel |
CN114215963A (en) * | 2021-12-04 | 2022-03-22 | 广东盈辉建设工程有限公司 | Construction method for water supply and drainage engineering of building |
CN117722533A (en) * | 2024-02-07 | 2024-03-19 | 临汾淼森能源工程有限公司 | Auxiliary equipment for laying thermal pipeline |
-
2012
- 2012-02-20 CN CN 201220054806 patent/CN202484438U/en not_active Expired - Fee Related
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102943924A (en) * | 2012-10-29 | 2013-02-27 | 中国海洋石油总公司 | Pipe conveying device with automatic correcting function |
CN108621317A (en) * | 2017-03-22 | 2018-10-09 | 中天科技精密材料有限公司 | Pipe cutting equipment and cutting method |
CN110789426A (en) * | 2018-08-02 | 2020-02-14 | 中国石油天然气集团有限公司 | Pipe conveying and distributing vehicle for pipeline construction |
CN109703622A (en) * | 2019-01-31 | 2019-05-03 | 山东能源重装集团泰装工程装备制造有限公司 | Two-way self-tipping type pipe carrying truck in a kind of tunnel |
CN110091102A (en) * | 2019-05-24 | 2019-08-06 | 薛溪健 | A kind of auxiliary docking facilities for chemical pipeline welding |
CN110509100A (en) * | 2019-08-31 | 2019-11-29 | 云南联塑科技发展有限公司 | A kind of tubing mobile unit and the tubing mobile device with tubing mobile unit |
CN110509100B (en) * | 2019-08-31 | 2024-06-11 | 云南联塑科技发展有限公司 | Pipe moving unit and pipe moving device with same |
CN110700214A (en) * | 2019-11-11 | 2020-01-17 | 武汉理工大学 | Oil spill treatment emergency ship based on bubble curtain technology |
CN110886903A (en) * | 2019-11-11 | 2020-03-17 | 武汉理工大学 | Rubber hose laying device |
CN112360554A (en) * | 2020-09-18 | 2021-02-12 | 燕山大学 | Automatic installation operation vehicle for hanging pipeline of coal mine tunnel |
CN112360554B (en) * | 2020-09-18 | 2022-03-11 | 燕山大学 | Automatic installation operation vehicle for hanging pipeline of coal mine tunnel |
CN114215963A (en) * | 2021-12-04 | 2022-03-22 | 广东盈辉建设工程有限公司 | Construction method for water supply and drainage engineering of building |
CN114215963B (en) * | 2021-12-04 | 2022-09-02 | 广东盈辉建设工程有限公司 | Construction method for water supply and drainage engineering of building |
CN117722533A (en) * | 2024-02-07 | 2024-03-19 | 临汾淼森能源工程有限公司 | Auxiliary equipment for laying thermal pipeline |
CN117722533B (en) * | 2024-02-07 | 2024-04-19 | 临汾淼森能源工程有限公司 | Auxiliary equipment for laying thermal pipeline |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202484438U (en) | Pipelaying vessel pipe conveying device | |
CN104555769B (en) | A kind of electric drive active compensation ocean winch | |
CN105173881A (en) | Automatic cable conveying system | |
CN101715408B (en) | Pipelaying vessel | |
CN204400501U (en) | A kind of electric drive active compensation ocean winch | |
CN105417381A (en) | Direct pump control type electro-hydraulic heaving compensation device | |
CN100569626C (en) | Hydraulic pressure turn-over device of large-scale component | |
CN201410953Y (en) | Carriage in-tunnel tube conveying installation car | |
CN105398965A (en) | Video-ranging offshore platform crane heave compensation control system and method | |
CN201982799U (en) | Cross traveling trolley for pipe laying ship | |
CN203270460U (en) | Walking type continuous pushing system | |
CN102943924A (en) | Pipe conveying device with automatic correcting function | |
CN204823445U (en) | Cable automatic conveying system | |
CN102582803A (en) | Hydraulic lifting roller shipping process for ultra-large marine structure | |
CN203877758U (en) | Pushing system of rail clamping device | |
CN204000817U (en) | The large-scale counterweight block privileged sites of vertical ship lift move assembling device | |
CN100528495C (en) | Robot electric cable propeller based on water-dressing method for cable operation | |
CN103241683B (en) | Under a kind of ocean pipeline balance weight production line, the rail mounted of pipe lifts pipe device | |
CN102530521A (en) | Stepping type pipeline arranging device | |
CN105587275A (en) | Full automatic rod transmission mechanism | |
CN103851135A (en) | High-power double-speed-ratio gearbox | |
CN203296708U (en) | Drilling machine moving system with hydraulic friction disk used for braking | |
CN203461721U (en) | Tail lifting equipment | |
CN203682928U (en) | Electric hydraulic lifting device | |
CN201857220U (en) | Dual-portal hoisting equipment with high hoisting capacity and capable of advancing horizontally and jacking vertically and automatically |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Assignee: Beijing gem Offshore Petroleum Engineering Technology Co Ltd Assignor: Baoji Petroleum Machinery Co., Ltd. Contract record no.: 2014990000541 Denomination of utility model: Pipelaying vessel pipe conveying device Granted publication date: 20121010 License type: Exclusive License Record date: 20140714 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121010 Termination date: 20150220 |
|
EXPY | Termination of patent right or utility model |