CN202433000U - Underwater concrete pouring lifting height tester - Google Patents

Underwater concrete pouring lifting height tester Download PDF

Info

Publication number
CN202433000U
CN202433000U CN 201120551656 CN201120551656U CN202433000U CN 202433000 U CN202433000 U CN 202433000U CN 201120551656 CN201120551656 CN 201120551656 CN 201120551656 U CN201120551656 U CN 201120551656U CN 202433000 U CN202433000 U CN 202433000U
Authority
CN
China
Prior art keywords
underwater concrete
lifting height
plummet
concrete pouring
height tester
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120551656
Other languages
Chinese (zh)
Inventor
刘兴春
金宗朝
史少博
丁文杰
朱鹏
朱超
彭飞
曹战峰
于华珍
唐涛
李静
尚恺喆
杨喜朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Priority to CN 201120551656 priority Critical patent/CN202433000U/en
Application granted granted Critical
Publication of CN202433000U publication Critical patent/CN202433000U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to an underwater concrete tester, in particular to an underwater concrete pouring lifting height tester for solving the problem how to rapidly, accurately, economically and practically measure the position of an underwater concrete pouring surface. The underwater concrete pouring lifting height tester comprises a measuring rope, a measuring meter and a cone plummet. One end of the measuring rope is connected with the measuring meter and the other end of the measuring rope is connected with the cone plummet; a cavity is formed in the cone plummet; and a filling block is arranged in the cavity. The underwater concrete pouring lifting height tester has the advantages that the control effect is good; on the premise of ensuring the pouring quality, the pouring quantity of the concrete of a pile foundation is saved; and the underwater concrete pouring lifting height tester has good economic benefits.

Description

Concrete is built the lifting height analyzer under water
Technical field
The utility model relates to a kind of underwater concrete analyzer, and the concrete under water that in particular, how fast to relate to, mensuration underwater concrete accurate, economic and practical pours into the face position is built the lifting height analyzer.
Background technology
When pile foundation was carried out the underwater concrete perfusion, every certain interval of time should infer whether build height coincide with the concrete perfusion amount according to theory amount of building and actual relation between the amount of building.For guaranteeing the density and the intensity of pile foundation top concrete, the stake top mark height of perfusion should exceed certain altitude than design, is generally 0.5~1.0m on the other hand.This all needs the accurate fast measuring of underwater concreting height.Because of underwater concrete top is slurry coat method; The mensuration of building height generally is to decide with operator's feel with lining rope and plummet; The numerical value that different people draws has certain deviation, and this patent has provided the method that can accurately measure the concreting height according to law of buoyancy.
At present; Assay method all is to adopt traditional method; The plummet of promptly measuring the concreting height generally adopts the steel cone-shaped body; Inconsistent during mensuration because of its buoyancy suffered in slurry coat method and fresh concrete, the two at the interface penetration resistance obvious variation is arranged, operating personnel infer the concrete surface position in view of the above.But plummet and mud and fresh concrete buoyancy are inconsistent and form error at measurment, cause the mensuration out of true easily, thereby cause waste material, even build the underwater concrete height and can not satisfy Pile Foundations Design and code requirement.
The utility model content
Whether the purpose of the utility model just provides a kind of concrete under water and builds the lifting height analyzer and build height with accurate measurement and coincide with the concrete perfusion amount.
The utility model comprises lining rope, meter and taper plummet, one section connection meter of lining rope, and the other end connects the taper plummet, and taper is measured hammer and is contained cavity, is provided with filling block in the cavity.
Taper plummet in the utility model comprises upper hammer and the lower hammer through being threaded together.
It is fine that the advantage of the utility model is to control effect, under the prerequisite that guarantees pouring quality, practiced thrift the concrete amount of building of pile foundation, and good economic benefits is arranged.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is done further explanation:
Fig. 1 is the synoptic diagram of the utility model installment state;
Fig. 2 is the cut-open view of taper plummet in the present embodiment 2.
Embodiment
Embodiment 1
The utility model comprises lining rope 1, meter 2 and taper plummet 3, one section connection meter 2 of lining rope 1, and the other end connects taper plummet 3, and taper is measured hammer and is contained cavity 4, is provided with filling block 5 in the cavity 4.
The existence of filling block 5 causes the proportion of taper plummet and fresh concrete very approaching; When plummet just floods to pile foundation fresh concrete fully; Can stop to sink, and situation in time is reflected on the meter 2, thereby can determine the height of casting concrete more exactly.Among Fig. 1 10 is conduit, 8 by the slurry of survey height, 9 is slime water, 11 is ground.
Application in several pile foundation engineerings, its measuring error is generally in 10cm.The stake top mark height of regulation perfusion in the bridge standard should exceed certain altitude than design, and for guaranteeing the pile crown concrete quality, relatively conservative in the construction, general value is 0.5~1.0m.Less because of this method measuring error, in the practice of construction it highly is defined as 0.5m.
Embodiment 2
Mounting structure is with embodiment 1, and the taper plummet 3 in changing embodiment in the utility model comprises the upper hammer 6 and lower hammer 7 through being threaded together.Because this structure is a demountable structure, so filling block 5 is the fritter shown in the figure, this structure, when running into the measured material of different densities again, can be through changing filling block 5, the density of change filling block 5 adapts to different working environments.

Claims (2)

1. concrete is built the lifting height analyzer under water; It is characterized in that: said analyzer comprises lining rope (1), meter (2) and taper plummet (3); One section connection meter (2) of lining rope (1); The other end connects taper plummet (3), and taper is measured hammer and contained cavity (4), is provided with filling block (5) in the cavity (4).
2. concrete under water as claimed in claim 1 is built the lifting height analyzer, it is characterized in that: said taper plummet (3) comprises upper hammer (6) and the lower hammer (7) through being threaded together.
CN 201120551656 2011-12-27 2011-12-27 Underwater concrete pouring lifting height tester Expired - Fee Related CN202433000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120551656 CN202433000U (en) 2011-12-27 2011-12-27 Underwater concrete pouring lifting height tester

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120551656 CN202433000U (en) 2011-12-27 2011-12-27 Underwater concrete pouring lifting height tester

Publications (1)

Publication Number Publication Date
CN202433000U true CN202433000U (en) 2012-09-12

Family

ID=46782440

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120551656 Expired - Fee Related CN202433000U (en) 2011-12-27 2011-12-27 Underwater concrete pouring lifting height tester

Country Status (1)

Country Link
CN (1) CN202433000U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195066A (en) * 2013-04-23 2013-07-10 中建八局第二建设有限公司 Excessive concrete pouring detector for underwater cast-in-place piles and method for using excessive concrete pouring detector
CN103267464A (en) * 2013-05-03 2013-08-28 中冶集团武汉勘察研究院有限公司 Tool for measuring concrete pouring height
CN104111105A (en) * 2014-07-17 2014-10-22 葛洲坝集团基础工程有限公司 Device and method for measuring lifting height of underwater concrete surface
CN115030202A (en) * 2022-07-20 2022-09-09 中建三局集团有限公司 Soft-consolidation construction method for cofferdam under thin-covering-layer hard riverbed condition

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195066A (en) * 2013-04-23 2013-07-10 中建八局第二建设有限公司 Excessive concrete pouring detector for underwater cast-in-place piles and method for using excessive concrete pouring detector
CN103195066B (en) * 2013-04-23 2014-12-10 中建八局第二建设有限公司 Excessive concrete pouring detector for underwater cast-in-place piles and method for using excessive concrete pouring detector
CN103267464A (en) * 2013-05-03 2013-08-28 中冶集团武汉勘察研究院有限公司 Tool for measuring concrete pouring height
CN104111105A (en) * 2014-07-17 2014-10-22 葛洲坝集团基础工程有限公司 Device and method for measuring lifting height of underwater concrete surface
CN115030202A (en) * 2022-07-20 2022-09-09 中建三局集团有限公司 Soft-consolidation construction method for cofferdam under thin-covering-layer hard riverbed condition

Similar Documents

Publication Publication Date Title
CN202433000U (en) Underwater concrete pouring lifting height tester
CN205369323U (en) Drilling bored concrete pile concrete interface monitoring devices
CN109989433B (en) Device for detecting over-filling height of bored pile in real time and detection method thereof
CN106522288B (en) A kind of control device and its application method of underwater concrete filling pile absolute altitude
CN102359111A (en) Underwater concrete pouring elevation control device and use method thereof
CN206056982U (en) A kind of assay device of high water head rich water tunnel
CN102912806A (en) Construction method of precipitation well
CN105625485B (en) A kind of method of Accurate Determining snag filling concrete absolute altitude
CN204919631U (en) Automatic monitoring underwater concrete fills device of elevation
CN201367588Y (en) Underwater concrete sampler
CN206034512U (en) Bored concrete pile of driling under water construction monitoring devices
CN103267464A (en) Tool for measuring concrete pouring height
CN205720226U (en) A kind of obturator slip bleeding rate and the test device of the rate that shrinks
CN208668481U (en) A kind of simple machine of the underwater concrete absolute altitude of precise measurement
CN108396734B (en) Device for controlling pile top concrete pouring elevation of punched bored pile
CN204385780U (en) A kind of ultra-deep slurry drilled pile pile head elevation control device
CN202194161U (en) Detecting device for concrete at top of drilled pile
CN206352316U (en) A kind of control device of underwater concrete filling pile absolute altitude
CN109372036A (en) Cast-in-place concrete pile pile head elevation control device and its application method
CN208346808U (en) A kind of device controlling Punching Borehole Cast-in-place Concrete Pile stake top concrete casting elevation
CN210439337U (en) Device for detecting height of cast-in-situ bored pile in excess irrigation in real time
CN205975708U (en) First detector of bored concrete pile
CN202925579U (en) Cast-in-place pile top concrete surface measuring component
CN204780928U (en) Major diameter bored concrete pile concrete first set groundwater increment controlling means
CN207515676U (en) Plate thickness monitoring instrument when concrete floor pours

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120912

Termination date: 20141227

EXPY Termination of patent right or utility model