CN202429894U - Holder for mounting and assembling of bridge crane - Google Patents

Holder for mounting and assembling of bridge crane Download PDF

Info

Publication number
CN202429894U
CN202429894U CN2012200229233U CN201220022923U CN202429894U CN 202429894 U CN202429894 U CN 202429894U CN 2012200229233 U CN2012200229233 U CN 2012200229233U CN 201220022923 U CN201220022923 U CN 201220022923U CN 202429894 U CN202429894 U CN 202429894U
Authority
CN
China
Prior art keywords
crane
support
bridge type
carriage
right support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012200229233U
Other languages
Chinese (zh)
Inventor
倪淑梅
何兆芳
魏发利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN2012200229233U priority Critical patent/CN202429894U/en
Application granted granted Critical
Publication of CN202429894U publication Critical patent/CN202429894U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a holder for mounting and assembling of a bridge crane and belongs to a mounting auxiliary device for bridge cranes. The holder is characterized by comprising a left support, a right support and an upper supporting beam. The left support and the right support are identical in structure and disposed symmetrically. The left support and the right support are inverted V-shaped steel leg weldments. A tie bar is welded on the lower portion between the inverted V-shaped steel legs of each support. A base plate is welded on the bottom of the inverted V-shaped steel legs of each support. The channeled upper supporting beam with a downward channel opening is welded on the tops of the left support and the right support. The upper supporting beam, the left support and the right support can be made of No. 24 channel steels. When the holder is used, two sets of the holders are used to support two crossbeams of the bridge crane, and precise assembling of end beams on two sides of the bridge crane is achieved. The holder for mounting and assembling of the bridge crane is safe and reliable, mounting and assembling precision of the bridge crane is enhanced, and construction cost is lowered.

Description

Crane in bridge type installation group is to using carriage
Technical field
The utility model belongs to the crane in bridge type installation auxiliary device, especially relates to a kind of crane in bridge type installation group to carriage.
Background technology
In the metallurgical construction industry, each workshop all can dispose all kinds of crane in bridge type, and usually crane in bridge type is assembled at originating firm earlier in advance, splits into assembly then so that transportation, and the scene that is transported to is assembled into integral body again, lifts after again.But ground relief often between the work car in building, gravel is more, and installation unit is suited measures to local conditions usually; Adopt the bracing frame of sleeper as two crossbeams of crane in bridge type, the on-the-spot interim group of carrying out crane in bridge type is right, because ground relief between work car; Gravel is more; The sleeper that banks out is just firm inadequately as bracing frame, has potential safety hazard, and displacement, the levelling of crossbeam are also wasted time and energy.
Summary of the invention
The purpose of the utility model is to propose a kind of crane in bridge type installation group to using carriage; Safe and reliable; Solve effectively crane in bridge type installation group to the time sleeper piled up is firm inadequately and displacement, levelling are wasted time and energy problem; And this overhead traveling crane unit reduces construction cost to can improve the right precision of installation group of crane in bridge type with carriage.
The purpose of the utility model is achieved in that a kind of crane in bridge type installation group is to using carriage; It is characterized in that this crane in bridge type installation group is to mainly being made up of left socle, right support and last joist with carriage; This left socle is identical with the right support structure and be symmetrical set; Be and be splay steel leg weldment, and the welding lacing wire of the bottom between this splay steel leg and weld base plate in the bottom of this splay steel leg respectively, joist on the top of left socle and right support fixedly is welded the downward flute profile of notch; Should go up joist and can be channel-section steel No. 24, splay steel leg can be processed with No. 24 channel-section steels.
During use, to play two crossbeams of crane in bridge type with the carriage support, accurate group of accomplishing crane in bridge type both sides end carriage is right through two groups of four this installation groups; Safe and reliable; The right precision of installation group is high, and this crane in bridge type installation group is to can repeated usage with carriage, and construction cost is low.
The crane in bridge type installation group that the utility model proposed is to using carriage, and is simple in structure, safe and reliable, and the right precision of installation group is high, and this crane in bridge type installation group has reduced construction cost to can repeated usage with carriage.
Combine at present accompanying drawing and embodiment to crane in bridge type installation group that the utility model proposed to being described further with carriage.
Description of drawings
Fig. 1 is that the crane in bridge type installation group that the utility model proposes is looked scheme drawing to the master with carriage.
Fig. 2 is that the crane in bridge type installation group that the utility model proposes is looked scheme drawing to the left side with carriage.
Fig. 3 is that the crane in bridge type installation group that proposes of the utility model is to the use scheme drawing with carriage.
Fig. 4 is that the crane in bridge type installation group that proposes of the utility model is to the use schematic top plan view with carriage.
Among Fig. 1-Fig. 4: 1, left socle 2, right support 3, last joist 4, crossbeam 5, end carriage.
The specific embodiment
From Fig. 1-Fig. 4, can find out: a kind of crane in bridge type installation group is to using carriage; It is characterized in that this crane in bridge type installation group is to mainly being made up of left socle 1, right support 2 and last joist 3 with carriage; This left socle 1 is identical with right support 2 structures and be symmetrical set; Be and be splay steel leg weldment, and the welding lacing wire of the bottom between this splay steel leg and weld base plate in the bottom of this splay steel leg respectively, joist 3 on the top of left socle 1 and right support 2 fixedly is welded the downward flute profile of notch; Should go up joist 3 and can be channel-section steel No. 24, splay steel leg can be processed with No. 24 channel-section steels.
During use; Through two groups of four this installation groups to play two crossbeams 4 of crane in bridge type with the carriage support; Accurate group of accomplishing crane in bridge type both sides end carriage 5 is right, safe and reliable, and the precision that the installation group is right is high; And this crane in bridge type installation group has reduced construction cost to can repeated usage with carriage.

Claims (3)

1. a crane in bridge type installation group is to using carriage; It is characterized in that this crane in bridge type installation group is to mainly being made up of left socle (1), right support (2) and last joist (3) with carriage; This left socle (1) is identical with right support (2) structure and be symmetrical set; Be and be splay steel leg weldment; And the bottom between this splay steel leg welding lacing wire and weld base plate in the bottom of this splay steel leg respectively, joist (3) on the top of left socle (1) and right support (2) fixedly is welded the downward flute profile of notch.
2. crane in bridge type installation group according to claim 1 is characterized in that to using carriage joist on this (3) is No. 24 channel-section steels.
3. crane in bridge type installation group according to claim 1 is to using carriage, it is characterized in that this splay steel leg processes with No. 24 channel-section steels.
CN2012200229233U 2012-01-18 2012-01-18 Holder for mounting and assembling of bridge crane Expired - Lifetime CN202429894U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200229233U CN202429894U (en) 2012-01-18 2012-01-18 Holder for mounting and assembling of bridge crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200229233U CN202429894U (en) 2012-01-18 2012-01-18 Holder for mounting and assembling of bridge crane

Publications (1)

Publication Number Publication Date
CN202429894U true CN202429894U (en) 2012-09-12

Family

ID=46779360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200229233U Expired - Lifetime CN202429894U (en) 2012-01-18 2012-01-18 Holder for mounting and assembling of bridge crane

Country Status (1)

Country Link
CN (1) CN202429894U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105152032A (en) * 2015-09-08 2015-12-16 中国十七冶集团有限公司 Installing method for bridge crane in enclosed environment workshop
CN105565175A (en) * 2016-03-08 2016-05-11 中冶建工集团有限公司 Installation method for large bridge crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105152032A (en) * 2015-09-08 2015-12-16 中国十七冶集团有限公司 Installing method for bridge crane in enclosed environment workshop
CN105565175A (en) * 2016-03-08 2016-05-11 中冶建工集团有限公司 Installation method for large bridge crane

Similar Documents

Publication Publication Date Title
CN107879248A (en) A kind of big beam orbit manufacture craft
CN102049647A (en) Welding fixture for girder of truss
CN202429894U (en) Holder for mounting and assembling of bridge crane
CN105014363B (en) The general dismounting stand of gun turret
CN202290893U (en) Straightening machine for H section steel flange slab
CN202482772U (en) Collapse-proof stop block mounting system for railway bridge
CN203127978U (en) Combined type automatic escalator truss
CN202220400U (en) Lap-joint type formwork support beam
CN204913165U (en) Artifical assemblage bed -jig of welding H shaped steel
CN204000620U (en) A kind of Bridge Erector is packed device
CN204644878U (en) A kind of transom pier steel truss girder lifting construction device
CN106996195A (en) The support and its application method lifted for steel structural overhead
CN206956534U (en) A kind of railway and track traffic suspended beam type Frame Pier
CN201933423U (en) Movable type protecting canopy frame
JP3182485U (en) Welding base
CN203568689U (en) Steel structure for wall-sleeving cantilever crane
CN202317830U (en) Turnover machine
CN205602900U (en) Buffer base reinforcing apparatus
CN204847830U (en) Bridge crane girder
CN210912488U (en) Vehicle frame transportation tool
CN203541898U (en) Thick T-shaped section welding tool for automatic submerged-arc welding machine
CN203568643U (en) Elevator traction machine installation structure
CN203863275U (en) Die frame for welding embedded bolts of railway box girder
CN202053039U (en) Welding clamp for truss girder
CN208329151U (en) A kind of assemble welding formula steel construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120912

CX01 Expiry of patent term