CN202323880U - Reverse osmosis drainage system of concrete face rockfill dam in construction period - Google Patents

Reverse osmosis drainage system of concrete face rockfill dam in construction period Download PDF

Info

Publication number
CN202323880U
CN202323880U CN 201120474725 CN201120474725U CN202323880U CN 202323880 U CN202323880 U CN 202323880U CN 201120474725 CN201120474725 CN 201120474725 CN 201120474725 U CN201120474725 U CN 201120474725U CN 202323880 U CN202323880 U CN 202323880U
Authority
CN
China
Prior art keywords
drainage
pipe
reverse osmosis
construction period
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201120474725
Other languages
Chinese (zh)
Inventor
湛正刚
蔡大咏
田业军
慕洪友
陈娟
刘雯
童文辉
史鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
Hydrochina Guiyang Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina Guiyang Engineering Corp filed Critical Hydrochina Guiyang Engineering Corp
Priority to CN 201120474725 priority Critical patent/CN202323880U/en
Application granted granted Critical
Publication of CN202323880U publication Critical patent/CN202323880U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a reverse osmosis drainage system of a concrete face rockfill dam in a construction period. Drainage blind materials are paved in a horizontal juncture face of a transition area and an upstream enrockment area, the upstream side of the drainage blind materials is connected with a sleeve, the other side of the sleeve is connected with a horizontal drainage pipe with a one-way water sealing valve, joint threads are arranged on the outsides of both the two ends of the horizontal drainage steel pipe, the other side of the sleeve is connected with a drainage flexible pipe, the other end of the drainage flexible pipe is arranged in a water collection well, and a vertical drainage pipe is further arranged. The reverse osmosis drainage system particularly suitable to reverse osmosis drainage of the concrete face rockfill dam in a construction period which has depth toe board foundation excavation and long upstream paving filling period and in a river bed section and the reverse osmosis drainage of a dam body needing flood passing drainage.

Description

A kind of rock construction period reverse osmosis drainage system
Technical field
The utility model relates to the rock technical field, particularly relates to rock construction period reverse osmosis drainage system.
Background technology
In Hydraulic and Hydro-Power Engineering, because of irrigation draught or generating etc. need, the formation reservoir of will building a dam usually, numerous dam Selection Floater loose rock dam of founding a capital and planning to build.Rock upstream side plinth foundation generally all is seated on complete, the hard basement rock; Because of toe board and toe board inner slope excavation darker; Cause dam foundation upstream side to be lower than the downstream, construction period dam district's construction water and rainwater etc. can not freedom be discharged downstream, are pooled to the dam body upstream side; Form reverse head, dam body upstream side bedding material, panel and panel water-stopping system can be owing to water pressure is destroyed.Therefore, timely and effectively the reverse water in the dam body is drained most importantly, generally need construction period reverse drainage system is set at the dam body upstream side.Conventional counter drainage system complex process, cost height are built interference greatly to dam embankment and panel, influence the duration, and later stage operation and shutoff are inconvenient.
Summary of the invention
The utility model technical problem to be solved is to overcome the defective that existing reverse drainage system process is complicated, cost is high; A kind of rock construction period reverse osmosis drainage system is provided; This system can the reverse water of convenient effective discharge, and simple in structure, the arrangement convenience of system, and cost is low.
In order to solve the problems of the technologies described above, the utility model adopts following technical scheme:
The utility model rock construction period reverse osmosis drainage system: in the horizontal interface in transition region 10 and enrockment district, the upper reaches 11, lay the blind material 1 of draining; The blind material 1 upstream side splicing sleeve 2 of draining; The opposite side of sleeve pipe 2 connects horizontal drain pipe 3, and the opposite side of horizontal drain pipe 3 connects scupper hose 5, and the other end of scupper hose 5 places in the collecting well 6; Other establishes vertical drainage pipe 7, and vertical drainage pipe 7 lower ends connect 13 and are connected with horizontal drain pipe 3 through curved.
Above-mentioned rock construction period reverse osmosis drainage system is provided with unidirectional sealing valve 4 on horizontal drain pipe 3.Unidirectional sealing valve 4 permission dams Nei Shui discharges, and does not allow dam Wai Shui to pour in the dam.
Aforementioned reverse osmosis drainage system is all established joint screw thread in the outside, two ends of horizontal drainage steel pipe 3, the installation after dismounting when making things convenient for the panel construction and panel have been built.
Aforementioned reverse osmosis drainage system, vertical drainage pipe 7 upper ends link to each other with lengthening vertical drainage pipe 7 with another section steel pipe through direct 14.
Compared with prior art, the utility model is established the blind material of draining as dam internal drainage passage in the water in dam tiling, makes things convenient for the dam body construction, reduces construction and disturbs, and the reduction of erection time, reduces investment outlay; Members such as the blind material of draining, gutter, unidirectional sealing valve are less relatively, transportation and easy for installation flexible, and it is little that counter plate weakens scope; Adopt nipple that horizontal drain pipe and sleeve pipe are joined, conveniently dismounting had made things convenient for slding form operation when panel was built; The installation of unidirectional sealing valve not only can under normal circumstances move; Also can normally move during the dam body temporary water dash in flood season; Can prevent to catchment outside the dam, the upper reaches pours in the dam, prevents that mud and rubbish stop up drainage system outside the dam, external water pressure in the balance dam body voluntarily behind the flood.The present invention is specially adapted to that section plinth foundation excavation in riverbed is dark, upstream apron fills long, dam body of duration and need cross the reverse drainage of the rock construction period of flood dash.
Description of drawings
Fig. 1 is the structural representation of the utility model.
The specific embodiment
Rock construction period reverse osmosis drainage system is as shown in Figure 1, in the horizontal interface in transition region 10 and enrockment district, the upper reaches 1, lays the blind material 1 of draining, the blind material 1 upstream side splicing sleeve 2 of draining; The opposite side of sleeve pipe 2 connects the horizontal drain pipe 3 that has unidirectional sealing valve 4; Joint screw thread is all established in the outside, two ends of horizontal drainage steel pipe 3, and its opposite side connects scupper hose 5, and the other end of scupper hose 5 places in the collecting well 6; Other establishes vertical drainage pipe 7; Other establishes vertical drainage pipe 7, and vertical drainage pipe 7 lower ends connect 13 and are connected with horizontal drain pipe 3 through curved, and vertical drainage pipe 7 upper ends are passed through direct 14 and linked to each other with the vertical drainage pipe 7 that extends with another section steel pipe.
Rock construction period reverse osmosis water processing method is following:
After rock upstream side horizontal segment transition region 10 placement grindings are accomplished; The blind material 1 of the circular draining of the horizontal laying high-strength degree of the medium position of each piece panel 8 of section in the riverbed; The upstream side of the blind material 1 of draining is laid the upstream edge in the enrockment district 11 to the upper reaches; Connect steel sleeve 2 at blind material 1 upstream side of draining; The upstream side of steel sleeve 2 aligns with the panel that will build 8 surface line; The upstream side that is connected on steel sleeve 2 in the horizontal drainage steel pipe 3 of unidirectional sealing valve 4 will be installed then, an end of scupper hose 5 be external in adopt steel wire to tighten and 9 lay to collecting well 6 on the horizontal drainage steel pipe 3, and adopt the pump drainage facility that the water in the collecting well 6 are evacuated to outside the upstream cofferdam with toe board 12 along the bed course district; Sheetpile masonry dam construction face to face is when building panel 8; For ease of slding form operation, pull down the horizontal drainage steel pipe 3 that is about to build the panel place temporarily, when panel is built steel sleeve 2 ends are protected; Prevent to stop up; And leave aperture herein, again horizontal drainage steel pipe 3 is connected with steel sleeve 2 after panel 8 constructions are accomplished, and this place's aperture periphery is repaired.
When flood season, dam body needed temporary water dash, pull down external scupper hose 5, drain upper reaches foundation ditch water behind the flood after, more external scupper hose is connected, guarantee that panel, toe board and water-stopping system are in dry state, repair and sealing construction in the crack of being convenient to toe board, panel.
When upstream apron fills to horizontal drainage steel pipe 3 elevations; Remove external scupper hose 5 earlier, more external vertical drainage steel pipe 7 is connected in horizontal drainage steel pipe 3 upstream sides through the curved joint 13 of steel pipe, external vertical drainage steel pipe 7 is established direct joint 14; Fill intensity one section one section lengthening gradually according to bedding; External water pressure in being convenient in the balance dam is when the bedding height fills when being higher than the free draining elevation 1m in downstream~2m, with the method shutoff of vertical drainage steel pipe 7 employing gravity flow cement groutings.

Claims (4)

1. rock construction period reverse osmosis drainage system; It is characterized in that: in the horizontal interface in transition region (10) and upper reaches enrockment district (11), lay the blind material of draining (1); The blind material of draining (1) upstream side splicing sleeve (2); The opposite side of sleeve pipe (2) connects horizontal drain pipe (3), and the opposite side of horizontal drain pipe (3) connects scupper hose (5), and the other end of scupper hose (5) places in the collecting well (6); Other establishes vertical drainage pipe (7), and vertical drainage pipe (7) lower end connects (13) and is connected with horizontal drain pipe (3) through curved.
2. according to the said rock of claim 1 construction period reverse osmosis drainage system, it is characterized in that: on horizontal drain pipe (3), be provided with unidirectional sealing valve (4).
3. according to the said rock of claim 1 construction period reverse osmosis drainage system, it is characterized in that: joint screw thread is all established in the outside, two ends of said horizontal drainage steel pipe (3).
4. according to the said rock of claim 1 construction period reverse osmosis drainage system, it is characterized in that: said vertical drainage pipe (7) upper end links to each other with another section steel pipe with lengthening vertical drainage pipe (7) through direct (14).
CN 201120474725 2011-11-25 2011-11-25 Reverse osmosis drainage system of concrete face rockfill dam in construction period Expired - Lifetime CN202323880U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120474725 CN202323880U (en) 2011-11-25 2011-11-25 Reverse osmosis drainage system of concrete face rockfill dam in construction period

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120474725 CN202323880U (en) 2011-11-25 2011-11-25 Reverse osmosis drainage system of concrete face rockfill dam in construction period

Publications (1)

Publication Number Publication Date
CN202323880U true CN202323880U (en) 2012-07-11

Family

ID=46435864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120474725 Expired - Lifetime CN202323880U (en) 2011-11-25 2011-11-25 Reverse osmosis drainage system of concrete face rockfill dam in construction period

Country Status (1)

Country Link
CN (1) CN202323880U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132488A (en) * 2011-11-25 2013-06-05 中国水电顾问集团贵阳勘测设计研究院 Reverse osmosis water processing method and reverse osmosis drainage system in construction period of concrete faced rockfill dam
CN105464124A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Treatment method and structure for water gushing of dam body foundation of rock-fill dam
CN108035318A (en) * 2017-12-28 2018-05-15 中国葛洲坝集团第二工程有限公司 The construction method of the dam body water draining structure of homogeneous earth dam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132488A (en) * 2011-11-25 2013-06-05 中国水电顾问集团贵阳勘测设计研究院 Reverse osmosis water processing method and reverse osmosis drainage system in construction period of concrete faced rockfill dam
CN103132488B (en) * 2011-11-25 2015-04-15 中国电建集团贵阳勘测设计研究院有限公司 Reverse osmosis water treatment method and reverse osmosis drainage system for face rockfill dam in construction period
CN105464124A (en) * 2015-12-31 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 Treatment method and structure for water gushing of dam body foundation of rock-fill dam
CN105464124B (en) * 2015-12-31 2017-10-13 中国电建集团贵阳勘测设计研究院有限公司 Treatment method and structure for water gushing of dam body foundation of rock-fill dam
CN108035318A (en) * 2017-12-28 2018-05-15 中国葛洲坝集团第二工程有限公司 The construction method of the dam body water draining structure of homogeneous earth dam
CN108035318B (en) * 2017-12-28 2019-12-13 中国葛洲坝集团第二工程有限公司 Construction method of dam body drainage structure of homogeneous earth dam

Similar Documents

Publication Publication Date Title
CN103132488B (en) Reverse osmosis water treatment method and reverse osmosis drainage system for face rockfill dam in construction period
CN105201002B (en) A kind of underground structure oozes drainage system and its construction method
CN104005419B (en) The box culvert structure of sinking method construction and construction method
CN202323880U (en) Reverse osmosis drainage system of concrete face rockfill dam in construction period
CN205259214U (en) Pin -connected panel rainwater regulation pond of method of sinking construction
CN204266170U (en) A kind of dam foundation gallery syndeton
CN1297713C (en) Back ward water draining system of face plate rock-fill dam dam body and its construction method
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN211228363U (en) Face river barricade
CN104404919A (en) Dam foundation corridor and bank slope bedrock connecting structure
CN116733021A (en) Basement leakage treatment structure construction method
CN110725717A (en) Water plugging structure for ore body roadway
CN205907658U (en) Be used for anti - structure that seeps water of concrete -faced rockfill dam construction time dam body
CN212983913U (en) Pressure-bearing downcomer well back cover is from waterproof one-way water outlet layer board piece of burying
CN205205831U (en) Ground even wall defect seepage ends drainage structures
CN112982319A (en) Structure and method for conducting diversion, emptying and water taking through dam foundation culvert
CN114045880A (en) Basement post-cast strip treatment process
CN204000742U (en) Self adaptation distortion inverted-siphon
CN204875703U (en) A cross adfluxion sediment weir for hydraulic and hydroelectric engineering
CN208594095U (en) A kind of wetland structure combined using wetland technology and rainwater storage
CN203080480U (en) Upstream blanket structure of concrete face rockfill dam
CN107059948B (en) Reset processing method and system for floating open cut tunnel structure
CN207619951U (en) Structure for improving external pressure resistance stability of pressure steel pipe
CN206599762U (en) Dam reverse drainage plugging device
CN203878600U (en) Box culvert structure constructed by adopting sinking method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: HYDROCHINA GUIYANG ENGINEERING CORPORATION, LTD.

Free format text: FORMER NAME: GUIYANG PROSPECTION + DESIGN INST, CHINA HYDRAULIC POWER CONSULTARY GROUP

Owner name: CHINA POWER GROUP GUIYANG INVESTIGATION DESIGN + R

Free format text: FORMER NAME: HYDROCHINA GUIYANG ENGINEERING CORPORATION, LTD.

CP01 Change in the name or title of a patent holder

Address after: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee after: POWERCHINA GUIYANG ENGINEERING Corp.,Ltd.

Address before: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee before: HydroChina Guiyang Engineering Corp.

Address after: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee after: POWERCHINA GUIYANG ENGINEERING CORPORATION LIMITED

Address before: 550081 No. 16 Xing Qian Road, Jinyang New District, Guizhou, Guiyang

Patentee before: POWERCHINA GUIYANG ENGINEERING Corp.,Ltd.

AV01 Patent right actively abandoned

Granted publication date: 20120711

Effective date of abandoning: 20150415

AV01 Patent right actively abandoned

Granted publication date: 20120711

Effective date of abandoning: 20150415

RGAV Abandon patent right to avoid regrant