CN202322715U - Novel stamp-charging coke oven - Google Patents

Novel stamp-charging coke oven Download PDF

Info

Publication number
CN202322715U
CN202322715U CN2011204495185U CN201120449518U CN202322715U CN 202322715 U CN202322715 U CN 202322715U CN 2011204495185 U CN2011204495185 U CN 2011204495185U CN 201120449518 U CN201120449518 U CN 201120449518U CN 202322715 U CN202322715 U CN 202322715U
Authority
CN
China
Prior art keywords
regenerator
chambers
chute
brick
tamping coke
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011204495185U
Other languages
Chinese (zh)
Inventor
丁世利
杨丽云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ENGINEERING TECHNOLOGY CO LTD University OF SCIENCE AND TECHNOLOGY LIAONING
Original Assignee
LIAONING METALLURGICAL COKING ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LIAONING METALLURGICAL COKING ENGINEERING TECHNOLOGY Co Ltd filed Critical LIAONING METALLURGICAL COKING ENGINEERING TECHNOLOGY Co Ltd
Priority to CN2011204495185U priority Critical patent/CN202322715U/en
Application granted granted Critical
Publication of CN202322715U publication Critical patent/CN202322715U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model relates to a novel stamp-charging coke oven, which is characterized in that the stamp-charging coke oven is a twinflue reheating coke oven with waste gas circulated, coke oven gas jetted downwards and lean gas and air fed sideways and comprises regenerative chambers, chutes, carbonization chambers, combustion chambers and an oven top, wherein the regenerative chambers are arranged on the lower portion of an oven body, the upper portions of the regenerative chambers are connected with the combustion chambers through the chutes, and the chutes are oblique channels which are connected with the regenerative chambers and the combustion chambers; the carbonization chambers are connected with the combustion chambers in sequence, each of the carbonization chambers is arranged on the lower portion between two combustion chambers and is connected with the regenerative chambers through the chutes; and the oven top is arranged on the upper portion of the carbonization chambers, three dedusting holes and an upward pipe hole, and ducts of the dedusting holes and the upward pipe hole are constructed with tongued and grooved bricks. Metallurgical coke produced in the novel stamp-charging coke oven completely meets national product quality requirements, and the novel stamp-charging coke oven has the advantages of being compact in structure, uniform in heating and high in thermal efficiency, so that times for delivery are reduced, intermittent pollution is reduced, coking production environment is improved and the service life of the oven is prolonged.

Description

A kind of novel tamping coke furnace
Technical field
The utility model relates to the Thermal Equipment of producing coke, chemical products in a kind of coking chemistry industry, particularly a kind of novel tamping coke furnace.
Background technology
At present; Tamping coke furnace day by day tends to maximize both at home and abroad; The height of coking chamber is increasingly high, and width and length are increasing, thereby causes that facility investment is big, coke over machinery is made complicacy and expense strengthens; Then the requirement of operational administrative and maintenance level is higher, makes it can not adapt to the demand that medium-sized and small enterprises are produced better.
Summary of the invention
The purpose of the utility model is for overcoming the defective of above-mentioned existence, a kind of novel tamping coke furnace being provided.
The utility model tamping coke furnace content Description:
The utility model tamping coke furnace; It is characterized in that: tamping coke furnace is the spray down of a kind of twinflue, waste gas circulation, coke-oven gas; The complex thermal coke of low-grade gas and air side entering type, by: regenerator, chute, coking chamber, combustion chamber and furnace roof five parts are formed; Regenerator is arranged on the bottom of body of heater, and top is connected with the combustion chamber through chute, and chute is the oblique passage that connects regenerator and combustion chamber; Coking chamber links to each other with the combustion chamber successively; Coking chamber is arranged between two combustion chambers, and the bottom is connected with regenerator through chute, is provided with furnace roof on the top of coking chamber; In furnace roof, be provided with three dedusting holes and a rising pore, the duct of dedusting hole and rising pore adopts brick the building of band ditch tongue to process.
The length of coking chamber is 14060mm, highly is 5500 mm, and width is 554 mm, and volume is 38.7m 3
Chute on the regenerator is oblique passage, and the height of oblique passage is 825mm, and the height of regenerator is 3600mm; Wide 290 mm of incorgruous air-flow main wall, employing has the structure of the shaped brick occlusal masonry of three ditch tongues, in the regenerator main wall, is provided with brick gas passage; There is not straight-through seam with the metope of regenerator; Wide 210 mm of air-flow list wall in the same way, air-flow list wall adopts the mutual occlusal masonry of " Z " shaped brick that has two ditch tongues to constitute in the same way, and the regenerator inwall adopts ultra-thin-wall 12 hole checker brick to build by laying bricks or stones and processes.
Below burner, be provided with regenerator sealing wall.
The bottom of the flue in the combustion chamber is provided with the chute mouth.
Coking chamber wall thickness 100 mm adopt brick the building of " pagoda " shape to process, and the metope between coking chamber and the combustion chamber does not have straight-through seam, and flue partition adopts brick the building of band ditch tongue to process.
The height of chute 15 is 825mm.
The height of furnace roof is 1454 mm.
The utility model tamping coke furnace; Solved that coke oven production adopts that metamorphic grade is low, high-volatile, weakly caking property coal or the high and low fugitive constituent of metamorphic grade, weakly caking property coal, the metallurgical coke of output reaches the national product specification of quality fully, has vertebration, homogeneous heating, characteristics that hot working efficiency is high; Under the situation of producing equal scale amount of coke, can reduce the number of times of coming out of the stove; Reduce paroxysmal and pollute, improved the coking production environment, improved converter life.
Description of drawings:
Fig. 1 is the tamping coke furnace structural representation.
Fig. 2 is a tamping coke furnace combustion chamber of furnace body sectional view
Fig. 3 is a tamping coke furnace body of heater coking chamber sectional view
Among the figure: the 1st, coking chamber, the 2nd, regenerator, the 3rd, incorgruous air-flow main wall, the 4th, brick gas passage, the 5th, the single wall, the 6th of one-way gas flow, burner, the 7th, regenerator sealing wall, the 8th, flue, the 9th, chute mouth, the 10th, combustion chamber, the 11st, flue partition, the 12nd, burner quirk, the 13rd, dedusting hole, the 14th, rising pore, the 15th, chute, the 16th, furnace roof.
Embodiment
The utility model tamping coke furnace is achieved in that to do below in conjunction with accompanying drawing and specifies.See Fig. 1, Fig. 2, Fig. 3, novel tamping coke furnace is the spray down of a kind of twinflue, waste gas circulation, coke-oven gas, the complex thermal coke of low-grade gas and air side entering type, by: regenerator 2, chute 15, coking chamber 1, combustion chamber 10 and furnace roof 16 5 parts are formed; Regenerator 2 is arranged on the bottom of body of heater, and top is connected with combustion chamber 10 through chute 15, and chute 15 is the oblique passages that connect regenerator 2 and combustion chamber 10; Coking chamber 1 links to each other with combustion chamber 10 successively, and coking chamber 1 is arranged between two combustion chambers 10, and the bottom is connected with regenerator 2 through chute 15; Be provided with furnace roof 16 on the top of coking chamber 1, in furnace roof 16, be provided with three dedusting holes 13 and a rising pore 14, the duct of dedusting hole 13 and rising pore 14 adopts brick the building of band ditch tongue to process; The globality and the exactness of masonry have been guaranteed; Furnace roof is firm, has reduced the blowby of raw gas, prevents the scaling loss of furnace roof horizontal brace.
For improving the stability of briquette, the height of coking chamber 1 is 5500 mm, and width is 554 mm, and briquette is wide to be 500 mm, and making into the briquette depth-width ratio firm by ramming is 10.6:1, and the volume of coking chamber 1 is 38.7m 3 , because the briquette of making firm by ramming is piled up Du Keda 1.0t/ m 3 More than, so the briquette good stability, coking chamber 1 can reduce the number of times of coming out of the stove under the situation of producing equal scale amount of coke, reduce paroxysmal and pollute, and has improved the coking production environment, has improved converter life.
Regenerator 2 links to each other with chute 15, and chute 15 is oblique passages, highly is 3600mm; Incorgruous air-flow main wall 3 wide 290 mm, employing has the structure of the shaped brick occlusal masonry of three ditch tongues, in incorgruous air-flow main wall 3, is provided with brick gas passage 4; Do not have straight-through seam with the metope of regenerator 2, guaranteed the exactness of brick gas passage 4, in the same way air-flow list wall 5 wide 210 mm; Air-flow list wall 5 adopts the mutual occlusal masonry of " Z " shaped brick that has two ditch tongues to constitute in the same way, has guaranteed the globality and the exactness of wall; Regenerator 2 inwalls adopt ultra-thin-wall 12 hole checker brick to build by laying bricks or stones, have increased heat-transfer surface, have reduced spent air temp, have improved thermo-efficiency.
Prevent to seal wall gas leakage in order to improve burner 6 heating, reduce thermosteresis, improve operating environment, below burner 6, be provided with regenerator sealing wall 7, improved sealing effectiveness and heat-insulating property.
The bottom of the flue 8 in the combustion chamber 10 is provided with chute mouth 9, and the air capacity of each quirk in the combustion chamber 10 and coal gas amount are distributed rationally, and the cross wall temperature distribution of combustion chamber 10 is even, has reduced the workman widely and has changed the labour intensity of regulating brick.
Coking chamber 1 wall thickness 100 mm; Adopt brick the building of " pagoda " shape to process, make the metope between coking chamber 1 and the combustion chamber 10 not have straight-through seam, make body of heater tight; Raw gas is difficult for blowby; Be convenient to wall and pick the stubble maintenance, flue partition 11 adopts brick the building of band ditch tongue to process, and has increased combustion chamber 10 greatly and has got structural strength and integrality of wall.
Burner quirk 12 adopts the ligulate loop structure, has solved burner quirk 12 temperature and has hanged down the ripe problem of giving birth to down on the charge of coke that reaches, and makes coking chamber charge of coke temperature even, and maturation has improved heat levels simultaneously.
Combustion chamber 10 is adopted waste gas circulation and is added the high coke oven gas holder structure; Guaranteed coking chamber 1 height to heating uniformity,, can reduce the oxynitrides content in the waste gas because of waste gas circulation is arranged; Minimizing is to atmospheric pollution; When coke oven prolongs the coking time operation, adopt coke-oven gas heating and high burner, therefore be difficult for short circuit.
The heat levels height of tamping coke furnace is decided to be 765mm, can makes charge of coke ripe simultaneously up and down, reduce furnace roof space feldspar China ink or green coke.
Chute 15 high 825mm.
The height of furnace roof 16 is 1454 mm, adopts intensity big, and heat-insulating efficiency highland floating bead brick and Sigur brick can be guaranteed the furnace roof surfacing, have reduced the furnace roof surface temperature, have improved operating environment.
The utility model tamping coke furnace, the metallurgical coke of producing reaches the national product specification of quality fully, and its structure is the spray down of twinflue, waste gas circulation, coke-oven gas; The complex thermal coke of low-grade gas and air side entering type, every hole coking chamber dress dry coal 35t produces per year and does complete burnt amount 8700-9100 t/a; 2 take advantage of the tamping coke furnace in one group in 60 holes to produce dried metallurgical coke amount 1,070,000 t/a, reach " coking industry entry criteria " standard-required, have vertebration, homogeneous heating, characteristics that hot working efficiency is high; Under the situation of producing equal scale amount of coke, can reduce the number of times of coming out of the stove; Reduce paroxysmal and pollute, improved the coking production environment, improved converter life.

Claims (8)

1. novel tamping coke furnace; It is characterized in that: tamping coke furnace is the spray down of a kind of twinflue, waste gas circulation, coke-oven gas; The complex thermal coke of low-grade gas and air side entering type, by: regenerator (2), chute (15), coking chamber (1), combustion chamber (10) and furnace roof (16) five parts are formed; Regenerator (2) is arranged on the bottom of body of heater, and top is connected with combustion chamber (10) through chute (15), and chute (15) is the oblique passage that connects regenerator (2) and combustion chamber (10); Coking chamber (1) links to each other with combustion chamber (10) successively; Coking chamber (1) is arranged between two combustion chambers (10); The bottom is connected with regenerator (2) through chute (15); Be provided with furnace roof (16) on the top of coking chamber (1), in furnace roof (16), be provided with three dedusting holes (13) and a rising pore (14), the duct of dedusting hole (13) and rising pore (14) adopts brick the building of band ditch tongue to process.
2. novel tamping coke furnace according to claim 1 is characterized in that: the height of coking chamber (1) is 5500 mm, and width is 554 mm, and volume is 38.7m 3
3. novel tamping coke furnace according to claim 1 is characterized in that: the chute (15) on the regenerator (2) is oblique passage, and the height of oblique passage is 825mm; Regenerator (2) highly is 3600mm; Wide 290 mm of incorgruous air-flow main wall (3), employing has the structure of the shaped brick occlusal masonry of three ditch tongues, in incorgruous air-flow main wall (3), is provided with brick gas passage (4); There is not straight-through seam with the metope of regenerator (2); Wide 210 mm of air-flow list wall (5) in the same way, air-flow list wall (5) adopts the mutual occlusal masonry of " Z " shaped brick that has two ditch tongues to constitute in the same way, and regenerator (2) inwall adopts ultra-thin-wall 12 hole checker brick to build by laying bricks or stones and processes.
4. novel tamping coke furnace according to claim 1 is characterized in that: below burner (6), be provided with regenerator sealing wall (7).
5. novel tamping coke furnace according to claim 1 is characterized in that: the bottom of the flue (8) in combustion chamber (10) is provided with chute mouth (9).
6. novel tamping coke furnace according to claim 1; It is characterized in that: coking chamber (1) wall thickness 100 mm; Adopt brick the building of " pagoda " shape to process, the metope between coking chamber (1) and combustion chamber (10) does not have straight-through seam, and flue partition (11) adopts brick the building of band ditch tongue to process.
7. novel tamping coke furnace according to claim 1 is characterized in that: the height of chute (15) is 825mm.
8. novel tamping coke furnace according to claim 1 is characterized in that: the height of furnace roof (16) is 1454 mm.
CN2011204495185U 2011-11-15 2011-11-15 Novel stamp-charging coke oven Expired - Lifetime CN202322715U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204495185U CN202322715U (en) 2011-11-15 2011-11-15 Novel stamp-charging coke oven

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204495185U CN202322715U (en) 2011-11-15 2011-11-15 Novel stamp-charging coke oven

Publications (1)

Publication Number Publication Date
CN202322715U true CN202322715U (en) 2012-07-11

Family

ID=46434702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204495185U Expired - Lifetime CN202322715U (en) 2011-11-15 2011-11-15 Novel stamp-charging coke oven

Country Status (1)

Country Link
CN (1) CN202322715U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103834417A (en) * 2014-04-02 2014-06-04 青岛伊诺威能源化工新技术有限公司 Transverse continuous heating and vertical coke discharging type tamping coke oven
CN103834416A (en) * 2014-03-18 2014-06-04 辽宁科技大学工程技术有限公司 Large-sized tamping coke oven
CN103834418A (en) * 2014-04-02 2014-06-04 青岛伊诺威能源化工新技术有限公司 Transverse alternate heating and vertical coke discharging type tamping coke furnace
CN106118690A (en) * 2016-08-23 2016-11-16 迁安市九江煤炭储运有限公司 A kind of poor gas heating coke oven improving chute

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103834416A (en) * 2014-03-18 2014-06-04 辽宁科技大学工程技术有限公司 Large-sized tamping coke oven
CN103834417A (en) * 2014-04-02 2014-06-04 青岛伊诺威能源化工新技术有限公司 Transverse continuous heating and vertical coke discharging type tamping coke oven
CN103834418A (en) * 2014-04-02 2014-06-04 青岛伊诺威能源化工新技术有限公司 Transverse alternate heating and vertical coke discharging type tamping coke furnace
CN103834418B (en) * 2014-04-02 2015-06-10 青岛伊诺威能源化工新技术有限公司 Transverse alternate heating and vertical coke discharging type tamping coke furnace
CN106118690A (en) * 2016-08-23 2016-11-16 迁安市九江煤炭储运有限公司 A kind of poor gas heating coke oven improving chute

Similar Documents

Publication Publication Date Title
CN201301298Y (en) Duplex exhaust gas reversed jet circulation stamp charging coke oven
CN203582805U (en) Outer-heating lignite dry distillation furnace
CN202322715U (en) Novel stamp-charging coke oven
CN202465585U (en) Tamping coke oven with combustors heated sectionally and regenerative chambers adjusted separately
CN202754941U (en) Stamp-charging coke oven with partition-adjustable regenerative chambers
CN202152278U (en) Novel integral activation furnace
CN204174158U (en) A kind of external-heat low-temperature pyrolysis stove
CN102627976B (en) Coking chamber for pulverized coal destructive distillation
CN204006647U (en) Semi-coal gas downward-burning type tubulation multistage heat exchange smoke-dust-free hot-air furnace
CN110938447A (en) Novel coke oven structure and sectional heating combustion method thereof
CN103834416A (en) Large-sized tamping coke oven
CN202322714U (en) Novel stamp-charging coke oven with wide coking chamber
CN102745671B (en) Pot-type carbon calciner
CN203923089U (en) A kind of large-scale tamping coke furnace
CN113149471A (en) Magnesite electric light-burning shaft kiln
CN111040782A (en) Coke oven and coking system
CN110922997A (en) Distributed combustion type heat recovery coke oven
CN203451226U (en) Carbon tank type calcining furnace
CN202501743U (en) Tank type calciner
CN211814263U (en) Distributed combustion type heat recovery coke oven
CN205784513U (en) External combustion vertical roasting stove
CN211946909U (en) Novel coke oven structure
CN108384913A (en) A kind of efficient reduction coal base shaft furnace
CN210463577U (en) High-temperature hot blast stove with heat exchange body for direct heat exchange
CN107903920B (en) Heat storage chamber of vertical furnace

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: ENGINEERING TECHNOLOGY CO., LTD., UNIVERSITY OF SCIENCE AND TECHNOLOGY LIAONING

Assignor: Liaoning Metallurgical Coking Engineering Technology Co., Ltd.

Contract record no.: 2013210000061

Denomination of utility model: Novel stamp-charging coke oven

Granted publication date: 20120711

License type: Exclusive License

Record date: 20130618

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
EC01 Cancellation of recordation of patent licensing contract

Assignee: ENGINEERING TECHNOLOGY CO., LTD., UNIVERSITY OF SCIENCE AND TECHNOLOGY LIAONING

Assignor: Liaoning Metallurgical Coking Engineering Technology Co., Ltd.

Contract record no.: 2013210000061

Date of cancellation: 20130716

EE01 Entry into force of recordation of patent licensing contract

Assignee: ENGINEERING TECHNOLOGY CO., LTD., UNIVERSITY OF SCIENCE AND TECHNOLOGY LIAONING

Assignor: Ding Shili|Yang Liyun|Liaoning metallurgical coking engineering technology Co., Ltd.

Contract record no.: 2013210000080

Denomination of utility model: Novel stamp-charging coke oven

Granted publication date: 20120711

License type: Exclusive License

Record date: 20130718

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200727

Address after: 114051, No. 185, Qianshan Road, hi tech Zone, Liaoning, Anshan

Co-patentee after: Ding Shili

Patentee after: ENGINEERING TECHNOLOGY CO LTD University OF SCIENCE AND TECHNOLOGY LIAONING

Co-patentee after: Yang Liyun

Address before: 114015, No. 433, Tonghai Road, Qianshan District, Liaoning, Anshan

Co-patentee before: Ding Shili

Patentee before: LIAONING METALLURGICAL COKING ENGINEERING TECHNOLOGY Co.,Ltd.

Co-patentee before: Yang Liyun

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120711