CN202321958U CN 201120470284 CN201120470284U CN202321958U CN 202321958 U CN202321958 U CN 202321958U CN 201120470284 CN201120470284 CN 201120470284 CN 201120470284 U CN201120470284 U CN 201120470284U CN 202321958 U CN202321958 U CN 202321958U
Authority
CN
China
Prior art keywords
reinforcement cage
hanger
sling
reinforcement
quality
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120470284
Other languages
Chinese (zh)
Inventor
刘鹏斌
黄军
张志安
郭英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN 201120470284 priority Critical patent/CN202321958U/en
Application granted granted Critical
Publication of CN202321958U publication Critical patent/CN202321958U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model concretely relates to an integrated sling for a reinforcement cage, solving the problems of the prior sling that: the hoisting process wastes time and labor and the quality of the reinforcement cage is affected. The integrated sling for a reinforcement cage comprises a bar-shaped hanger in a truss structure with left, right, front and back sections all in an isosceles trapezoid shape; two reinforcement steel bars with upper ends higher than the hanger and forming a triangular shape by enclosing with the bottom of the hanger are fixed in the middle of the hanger; a plurality of pairs of symmetric slingers along the left-right direction are fixed on the left and right sides of the bottom of the hanger, and hoist cables are connected in the slingers. The structure of the sling is reasonably and reliably designed, and the quality of binding the reinforcement steel bars is well ensured by integral hoisting, thus all the vertical reinforcement steel bar joints are butt-welded, the quality of the beam is relatively well controlled, and simultaneously after hoisting, the reinforcement cage is not deformed and is bound on a mould. The construction efficiency is increased by the integral hoisting process, and after the reinforcement cage is integrally bound, the binding and connecting step of the mid-span reinforcement steel bars is not needed, the usage of the material is reduced and unnecessary labor is also saved.

Description

The whole suspender of steel reinforcement cage
Technical field
The utility model relates to suspender, is specially web at the bottom of the post-stressed freely-supported T of a kind of passenger-cargo conllinear railway beam, top board with the whole suspender of steel reinforcement cage.
Background technology
The post-stressed freely-supported T of passenger-cargo conllinear railway is the beam prefabricated existing time for many years of construction at home, and each item technology, technology be comparative maturity and complete all.Construction method, equipment frock all are similar basically.But all be to adopt partly to stride Hoisting Program basically aspect reinforcing bar cage hoisting, so just caused the steel reinforcement cage must the secondary colligation, cause the longitudinal reinforcement can not flash butt-welding, influence quality.
Summary of the invention
There is the problem that wastes time and energy and influence the steel reinforcement cage quality in the utility model in order to solve existing suspender lifting, provides a kind of steel reinforcement cage whole suspender.
The utility model is to adopt following technical scheme to realize: the whole suspender of steel reinforcement cage; Comprise that cross section, the left and right sides and cross section, front and back are the isosceles trapezoid shape and are the strip suspension bracket of truss structure; The suspension bracket center fixed has two to surround the reinforcing bar that triangular shape and upper end exceed suspension bracket with the bottom surface; The left and right sides, suspension bracket bottom surface is fixed with some to the symmetrically arranged suspension ring of left and right directions, all is connected with lifting rope in the suspension ring.During operation, the lifting rope integral hanging on the longitudinal reinforcement of steel reinforcement cage, has been overcome existing suspender lifting and had the problem that wastes time and energy and influence the steel reinforcement cage quality.
The utility model reasonable in design is reliable, can well guarantee the reinforcing bar binding quality through integral hoisting, makes the whole butt welding of longitudinal reinforcement joint; Beam physique amount is controlled preferably, and lifting back steel reinforcement cage is indeformable simultaneously, and steel reinforcement cage is through colligation on mold; Integral hoisting has improved the construction effect; Save the span centre reinforcing bar binding behind the steel reinforcement cage overall binding and connected operation, reduced material usage, saved unnecessary manual work.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Among the figure: 1-suspension bracket, 2-reinforcing bar, 3-suspension ring, 4-lifting rope.
The specific embodiment
The whole suspender of steel reinforcement cage; Comprise that cross section, the left and right sides and cross section, front and back are the isosceles trapezoid shape and are the strip suspension bracket 1 of truss structure; Suspension bracket 1 center fixed has two to surround the reinforcing bar 2 that triangular shape and upper end exceed suspension bracket 1 with the bottom surface; The left and right sides, suspension bracket 1 bottom surface is fixed with some to the symmetrically arranged suspension ring 3 of left and right directions, all is connected with lifting rope 4 in the suspension ring 3.In the practical implementation process, suspension bracket 1 adopts 100 square tubes to be welded.

Claims (1)

1. the whole suspender of a steel reinforcement cage; It is characterized in that: comprise that cross section, the left and right sides and cross section, front and back are the isosceles trapezoid shape and are the strip suspension bracket (1) of truss structure; Suspension bracket (1) center fixed has two to surround the reinforcing bar (2) that triangular shape and upper end exceed suspension bracket (1) with the bottom surface; Suspension bracket (1) left and right sides, bottom surface is fixed with some to the symmetrically arranged suspension ring of left and right directions (3), all is connected with lifting rope (4) in the suspension ring (3).
CN 201120470284 2011-11-23 2011-11-23 Integrated sling for reinforcement cage Expired - Fee Related CN202321958U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120470284 CN202321958U (en) 2011-11-23 2011-11-23 Integrated sling for reinforcement cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120470284 CN202321958U (en) 2011-11-23 2011-11-23 Integrated sling for reinforcement cage

Publications (1)

Publication Number Publication Date
CN202321958U true CN202321958U (en) 2012-07-11

Family

ID=46433948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120470284 Expired - Fee Related CN202321958U (en) 2011-11-23 2011-11-23 Integrated sling for reinforcement cage

Country Status (1)

Country Link
CN (1) CN202321958U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105621224A (en) * 2016-03-01 2016-06-01 华中科技大学 Lifting tool
CN108946435A (en) * 2018-10-12 2018-12-07 中铁六局集团广州工程有限公司 A kind of hanging beam structure
CN109110629A (en) * 2018-10-12 2019-01-01 中铁六局集团广州工程有限公司 A kind of hoisting device for reinforcement cage

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105621224A (en) * 2016-03-01 2016-06-01 华中科技大学 Lifting tool
CN108946435A (en) * 2018-10-12 2018-12-07 中铁六局集团广州工程有限公司 A kind of hanging beam structure
CN109110629A (en) * 2018-10-12 2019-01-01 中铁六局集团广州工程有限公司 A kind of hoisting device for reinforcement cage
CN109110629B (en) * 2018-10-12 2023-11-14 中铁六局集团有限公司 Steel reinforcement cage hoist device

Similar Documents

Publication Publication Date Title
CN202080812U (en) Dedicated sling system for large-scaled reinforcing cage
CN207211464U (en) A kind of new reinforcing steel bar truss plate
CN202321958U (en) Integrated sling for reinforcement cage
CN107130734B (en) Corrugated plate dst Horizontal H-shaped structure beam and its construction method
CN202913337U (en) Prestress combination box girder composed of concrete frange plates and corrugated steel webs
CN204529069U (en) Prefabricated case beam steel bar overall hoisting device
CN102777036A (en) Air reverse mechanical joint construction method of super-long vertical reinforcement cage
CN105317146A (en) Steel structure earthquake-resistant floor for construction and manufacturing method
CN201395894Y (en) Reinforcing-cage and steel-rib integrated girder skeleton
CN204225098U (en) Overweight reinforcing cage
CN204059609U (en) A kind of reinforcing steel bar connecting device of precast beam Column border node
CN104100002A (en) Connecting structure of floor and column
CN205206112U (en) Novel three -dimensional steel bar truss building carrier plate
CN202730754U (en) H-shaped support pile
CN210104528U (en) Light steel net rack-UHPC combined bridge structure
CN106583603A (en) Manufacturing method for sprayed concrete reinforcing mesh and bracket used in manufacturing method
CN219431131U (en) Steel bar truss template
CN112593657A (en) Manufacturing method of large-span light beam
CN206815377U (en) A kind of attachment structure of pipe gallery assembly
CN203270942U (en) Dual-point network mould fixing member assembly
CN201424706Y (en) Novel connecting structure of steel secondary beam and concrete main beam
CN206448167U (en) The recyclable template of continuous beam with high-pier transverse prestress stretching notch closure
CN204370691U (en) A kind of Combination Welding annular compound stirrup
CN203961022U (en) The syndeton of a kind of floor and post
CN203160491U (en) Steel truss structure for floor plates

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120711

Termination date: 20191123