CN202299362U - Erecting structure for suspension type scaffold of pipe rack - Google Patents

Erecting structure for suspension type scaffold of pipe rack Download PDF

Info

Publication number
CN202299362U
CN202299362U CN2011204509262U CN201120450926U CN202299362U CN 202299362 U CN202299362 U CN 202299362U CN 2011204509262 U CN2011204509262 U CN 2011204509262U CN 201120450926 U CN201120450926 U CN 201120450926U CN 202299362 U CN202299362 U CN 202299362U
Authority
CN
China
Prior art keywords
scaffold
suspension type
cross bar
rods
vertical pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011204509262U
Other languages
Chinese (zh)
Inventor
陈学超
乔新泉
陈本富
徐伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering No14 Construction Co Ltd
Original Assignee
China National Chemical Engineering No14 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering No14 Construction Co Ltd filed Critical China National Chemical Engineering No14 Construction Co Ltd
Priority to CN2011204509262U priority Critical patent/CN202299362U/en
Application granted granted Critical
Publication of CN202299362U publication Critical patent/CN202299362U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model relates to an erecting structure for a suspension type scaffold of a pipe rack. The erecting structure comprises a plurality of horizontal rods, a plurality of longitudinal rods, a plurality of vertical rods, a plurality of fasteners, a beam on a constructed building and a door-shaped frame, wherein the horizontal rods, the longitudinal rods and the vertical rods are fastened through the fasteners; the door-shaped frame is a rectangle with an opening; circular rings are respectively connected with tail ends on two sides of an opening end; the two circular rings are same in axial direction; the planes of the circular rings are vertical to the plane of the rectangle; the horizontal rods or the longitudinal rods pass through the two circular rings; and the door-shaped frame is suspended on the beam. In order to overcome the difficulty in erecting the scaffold, a suspension type full framing scaffold is selected in the erecting structure, so that the safety risk in the crosswise operated ground civil work and pipe distributing operation for the pipe rack is reduced, the ground under the pipe rack after the civil work is finished is used as a place for the prefabricating and heat-insulating prefabricating of the pipeline, and the problem of narrow place is completely solved.

Description

Suspension type piping lane scaffold building structure
Technical field
The present technique scheme belongs to construction engineering technical field, specifically is a kind of suspension type piping lane scaffold building structure.
Background technology
Construction work is increasingly high for the safety requirements of engineering during engineering construction now, scaffold as the application of a conventional means of safety in production also more and more widely, scaffold had become essential technical safety measures in the project construction that has in the past.In the prior art, the difficult point that scaffold building generally can run into has: the project construction period is tighter; Crossed construction is frequent, and the piping lane main structure had been basically completed and has possessed the craft piping condition at that time, but the ground construction of civil engineering still has a lot; Project plant area space is comparatively compact; It is higher to set up the full hall of tradition scaffold expense.Because crossed construction often can not be set up scaffold from bottom to top with following the prescribed order, runs into and must use the scene that scaffold could be constructed, and just can not in time complete.
Summary of the invention
In order to solve the problems referred to above that exist in the prior art, the present technique scheme proposes a kind of suspension type piping lane scaffold building structure, and concrete technical scheme is following:
A kind of suspension type piping lane scaffold building structure comprises the beam on many cross bars, many vertical poles, many montants, a plurality of fastener and the construction building things; Said cross bar, vertical pole and montant are through the fastener snapping.Also comprise portal, said portal is the rectangle of opening, and the end on the both sides of openend is connected with annulus respectively, two annulus axially identical, and each plane, annulus place is perpendicular to plane, said rectangle place; Said cross bar or vertical pole pass said two annulus, and the portal beam hangs on the beam.
Comprise scaffold floor, scaffold floor is laid on adjacent cross bar and/or the adjacent vertical pole.
Comprise protective guard, protective guard is connected between the bilevel cross bar and/or between the bilevel vertical pole.
Comprise bridging, bridging is connected with cross bar, vertical pole and/or montant through fastener.
Difficult point to the scaffold building existence; This device is selected the full hall of suspension type scaffold; The ground civil engineering work of cross-operation and the security risk of piping lane piping work have been reduced like this; Ground can also and be incubated prefabricated place as pipe prefabrication below piping lane behind the civil engineering end-of-job, has solved the narrow and small problem in place fully.
Description of drawings
Fig. 1 is the sketch map of the utility model specific embodiment.Among the figure, 1-cross bar, 2-vertical pole, 3-montant, 4-fastener, 5-portal, 6-beam.
The specific embodiment
Below in conjunction with the accompanying drawing and the specific embodiment present technique scheme is further specified as follows:
A kind of suspension type piping lane scaffold building structure comprises the beam on many cross bars, many vertical poles, many montants, a plurality of fastener and the construction building things; Said cross bar, vertical pole and montant are through the fastener snapping.Also comprise portal, said portal is the rectangle of opening, and the end on the both sides of openend is connected with annulus respectively, two annulus axially identical, and each plane, annulus place is perpendicular to plane, said rectangle place; Said cross bar or vertical pole pass said two annulus, and the portal beam hangs on the beam.
Comprise scaffold floor, scaffold floor is laid on adjacent cross bar and/or the adjacent vertical pole.
Comprise protective guard, protective guard is connected between the bilevel cross bar and/or between the bilevel vertical pole.
Comprise bridging, bridging is connected with cross bar, vertical pole and/or montant through fastener.
Set up at boat scaffold: cancellation is as the scaffolding steel pipe of suspension material; And use the round steel of φ 12mm instead; Making is simple, and is easy to operate, reduced the working time and the labour intensity of scaffolder's work high above the ground; Reduced and set up the process safe risk, saved scaffold building time and expenses.This frock is applicable to the scaffold building of the open type frame construction that the duration is nervous, cross-operation is frequent.
Adopt this structure, the flow process of scaffold building is: the round steel portal is prefabricated → location is provided with → and vertical leger → little cross bar (joist) → bridging → shop scaffold floor → guard rail;
Round steel portal prefabricated: 200 of prefabricated quantity, round steel need be brushed corrosion resistant coating;
Cross bar: 2 scaffolders stand on 2 beams that close on and respectively the round steel portal that arranges are mentioned, and steel pipe is passed in the portal dicyclo, slowly it are put down then; Vertically connect with fastener between the leger;
Vertical pole: after treating that vertical pole connects completion, every separated 1.8m is arranged on the vertical pole with cross bar, and connects with fastener;
Bridging: after treating that vertical leger and little cross bar deploy, arrange horizontal cross brace, connection horizontal, vertical pole; Every group of about at interval 20m of bridging;
Scaffold floor is laid: after treating that above-mentioned work is all accomplished, lay the thick wooden springboard of 50mm;
Guard rail: with steel tube fastener guard rail is set apart from scaffold floor 200mm place in the suspension bracket outside.

Claims (4)

1. suspension type piping lane scaffold building structure comprises the beam on many cross bars, many vertical poles, many montants, a plurality of fastener and the construction building things; Said cross bar, vertical pole and montant are through the fastener snapping; It is characterized in that also comprising portal, said portal is the rectangle of opening, and the end on the both sides of openend is connected with annulus respectively; Two annulus axially identical, each plane, annulus place is perpendicular to plane, said rectangle place; Said cross bar or vertical pole pass said two annulus, and the portal beam hangs on the beam.
2. suspension type piping lane scaffold building structure according to claim 1 is characterized in that comprising scaffold floor, and scaffold floor is laid on adjacent cross bar and/or the adjacent vertical pole.
3. suspension type piping lane scaffold building structure according to claim 1 and 2 is characterized in that comprising protective guard, and protective guard is connected between the bilevel cross bar and/or between the bilevel vertical pole.
4. suspension type piping lane scaffold building structure according to claim 3 is characterized in that comprising bridging, and bridging is connected with cross bar, vertical pole and/or montant through fastener.
CN2011204509262U 2011-11-15 2011-11-15 Erecting structure for suspension type scaffold of pipe rack Expired - Lifetime CN202299362U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204509262U CN202299362U (en) 2011-11-15 2011-11-15 Erecting structure for suspension type scaffold of pipe rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204509262U CN202299362U (en) 2011-11-15 2011-11-15 Erecting structure for suspension type scaffold of pipe rack

Publications (1)

Publication Number Publication Date
CN202299362U true CN202299362U (en) 2012-07-04

Family

ID=46368288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204509262U Expired - Lifetime CN202299362U (en) 2011-11-15 2011-11-15 Erecting structure for suspension type scaffold of pipe rack

Country Status (1)

Country Link
CN (1) CN202299362U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797991A (en) * 2018-06-27 2018-11-13 中国化学工程第四建设有限公司 Suspension type lifting lug scaffold installation method
CN111706056A (en) * 2020-06-18 2020-09-25 上海建工集团股份有限公司 Construction device for scaffold, scaffold system and construction method thereof
CN111894253A (en) * 2020-07-23 2020-11-06 中国三冶集团有限公司 Ring type sliding scaffold for corridor and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797991A (en) * 2018-06-27 2018-11-13 中国化学工程第四建设有限公司 Suspension type lifting lug scaffold installation method
CN111706056A (en) * 2020-06-18 2020-09-25 上海建工集团股份有限公司 Construction device for scaffold, scaffold system and construction method thereof
CN111894253A (en) * 2020-07-23 2020-11-06 中国三冶集团有限公司 Ring type sliding scaffold for corridor and construction method thereof

Similar Documents

Publication Publication Date Title
CN104153587B (en) A kind of built with ribbed bricks body of wall assembly construction method
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN103982040B (en) A kind of construction of super highrise building vertical multi-transportation device
CN202324571U (en) Overhanging type double-row scaffold
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN104831812A (en) Whole assembly-type precast concrete frame structure, structural part production technology and mounting method
CN205575408U (en) Concrete precast component shedder
CN203238780U (en) Prefabricated stirrup cage of beam column core area
CN105484502B (en) A kind of industrial premises steel structural roof purlin and support bar combined installation method
CN104790675A (en) Reinforced concrete block masonry structure assemblage construction method
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN203779015U (en) Reinforcement cage forming machine
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN103993666A (en) Improved supporting system construction method suitable for large overhung outer floating plate roof
CN203963265U (en) Pipeline layout support
CN202299362U (en) Erecting structure for suspension type scaffold of pipe rack
CN209293474U (en) A kind of support device that cantilevered structure falsework is shared with external scaffolding
CN201635377U (en) Rigid suspended type scaffold provided with large-span steel roof equipment pipeline
CN203808249U (en) Column stirrup cage assembly for beam-column joint core region
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
CN109162447A (en) Steel platform of climbing support device and its application method
CN202658867U (en) Overhanging construction platform
CN203977840U (en) A kind of high-altitude long-span strengthening concrete vestibule braced structures
CN110030005A (en) The light-duty guarantor's circle support system of shield tunnel and its construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120704

CX01 Expiry of patent term