CN202266073U - Steel tower rising structure of power transmission line - Google Patents

Steel tower rising structure of power transmission line Download PDF

Info

Publication number
CN202266073U
CN202266073U CN 201120419588 CN201120419588U CN202266073U CN 202266073 U CN202266073 U CN 202266073U CN 201120419588 CN201120419588 CN 201120419588 CN 201120419588 U CN201120419588 U CN 201120419588U CN 202266073 U CN202266073 U CN 202266073U
Authority
CN
China
Prior art keywords
steel tower
tower
transmission line
power transmission
tower body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120419588
Other languages
Chinese (zh)
Inventor
李春生
李红奎
张逸群
刘江川
安卫中
张建彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN 201120419588 priority Critical patent/CN202266073U/en
Application granted granted Critical
Publication of CN202266073U publication Critical patent/CN202266073U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a steel tower rising structure of a power transmission line, wherein the steel tower rising structure comprises a graft tower body of a rectangular truss structure and an original steel tower cement foundation; the periphery side of the graft tower body is provided with a reinforcing diagonal bracing; and the original steel tower cement foundation is provided with a reinforcing anchor bolt. Through the structure, a great amount of sand stones, cement and reinforcing steel bar materials can be saved, the modified construction cycle and the power outage time are shortened greatly, at the same time, and the problem that the foundation can not be poured additionally to erect a new steel tower by adopting a traditional method because of the geographic environment restriction of the channel and the power outage time restriction is solved.

Description

A kind of iron tower of power transmission line rising structure
Technical field
The utility model belongs to high-voltage transmission line towers renovation technique field, particularly a kind of iron tower of power transmission line rising structure.
Background technology
Along with the development of traffic infrastructure, railway, speedway constantly increase, and safe distance is not enough over the ground to bring the transmission line of electricity of crossing over railway, speedway thus, and transformation must in time raise.At present; Carry out the method that transmission line of electricity raises and transforms, normally original iron tower of power transmission line is torn open and moved, then with the broken removal of concrete pedestal; Again enlarge the cast basis; By section at the bottom of the new size design making iron tower, after former tower body is connected, new tower body is installed on the new basis simultaneously through four pre-embedded anchoring bolts.This method not only will be wasted a large amount of sandstone, cement and reinforcing bar material, and the effort of taking a lot of work, and construction period is very long, influences power transmission efficiency.Limited by restriction of passage geographical environment and power off time, can't adopt the conventional method situation of the new upright iron tower in cast basis in addition, more make electric power enterprise be in the dilemma.
The utility model content
The purpose of the utility model is to provide a kind of and can saves material to greatest extent, improves rebuilding construction efficient, shortens the iron tower of power transmission line rising structure of construction period and power off time.
The technical scheme that purpose adopted that realizes the utility model is: a kind of iron tower of power transmission line rising structure; The grafting tower body and the former iron tower concrete pedestal that comprise the rectangle trussed construction; All sides of said grafting tower body are provided with the reinforcement diagonal brace, and former iron tower concrete pedestal is provided with foot bolt intentinonally.
The iron tower of power transmission line rising structure of the utility model; Can practice thrift a large amount of sandstone, cement and reinforcing bar material; Shorten rebuilding construction cycle and power off time greatly; Solve restriction of passage geographical environment and power off time restriction simultaneously, can't adopt the conventional method problem of the new upright iron tower in cast basis in addition.
Description of drawings
Fig. 1 is the structural representation of the utility model.
The specific embodiment
Referring to Fig. 1; The iron tower of power transmission line rising structure of the utility model; Be the grafting tower body 2 and former iron tower concrete pedestal 1 of rectangle trussed construction, the two ends up and down of said grafting tower body 2 respectively can with section 4 at the bottom of the former tower body and former 5 corresponding connections of stone bolt, all heel posts of grafting tower body 2 are provided with reinforcement diagonal brace 3; With the flexural strength of enhancing grafting tower body 2, and on former iron tower concrete pedestal 1, set up and put four foot bolts 6 intentinonally.Like this; Can make improved tower body have enough compressive strength, flexural strength and wind resistance stability; Simultaneously when carrying out iron tower rising transformation; Only need on former iron tower concrete pedestal 1, set up to put four foot bolts 6 intentinonally, after section 4 integrated removals at the bottom of former tower body and the former tower body are raise, again with the two ends up and down of grafting tower body 2 distinguish can with section 4 at the bottom of the former tower body and former 5 corresponding connections of stone bolt; The lower end of strengthening diagonal brace 3 respectively with four intentinonally foot bolt 6 be connected, promptly accomplish the rising transformation of whole iron tower.Can practice thrift a large amount of sandstone, cement and reinforcing bar material thus, shorten rebuilding construction cycle and power off time greatly, solve restriction of passage geographical environment and power off time restriction simultaneously, can't adopt the conventional method problem of the new upright iron tower in cast basis in addition.

Claims (1)

1. iron tower of power transmission line rising structure, it is characterized in that: it comprises the grafting tower body and the former iron tower concrete pedestal of rectangle trussed construction, and all sides of said grafting tower body are provided with the reinforcement diagonal brace, and former iron tower concrete pedestal is provided with foot bolt intentinonally.
CN 201120419588 2011-10-29 2011-10-29 Steel tower rising structure of power transmission line Expired - Fee Related CN202266073U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120419588 CN202266073U (en) 2011-10-29 2011-10-29 Steel tower rising structure of power transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120419588 CN202266073U (en) 2011-10-29 2011-10-29 Steel tower rising structure of power transmission line

Publications (1)

Publication Number Publication Date
CN202266073U true CN202266073U (en) 2012-06-06

Family

ID=46156871

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120419588 Expired - Fee Related CN202266073U (en) 2011-10-29 2011-10-29 Steel tower rising structure of power transmission line

Country Status (1)

Country Link
CN (1) CN202266073U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132766A (en) * 2013-03-05 2013-06-05 山东电力集团公司淄博供电公司 Truss for lifting power transmission line tower connecting leg and erection method
CN104929380A (en) * 2015-05-21 2015-09-23 国家电网公司 Heightening steel tower boot foot used for tilt centralizing adjustment of transmission line steel towers and method for tilt centralizing adjustment of transmission line steel towers

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132766A (en) * 2013-03-05 2013-06-05 山东电力集团公司淄博供电公司 Truss for lifting power transmission line tower connecting leg and erection method
CN103132766B (en) * 2013-03-05 2014-12-10 国家电网公司 Truss for lifting power transmission line tower connecting leg and erection method
CN104929380A (en) * 2015-05-21 2015-09-23 国家电网公司 Heightening steel tower boot foot used for tilt centralizing adjustment of transmission line steel towers and method for tilt centralizing adjustment of transmission line steel towers

Similar Documents

Publication Publication Date Title
CN103867019B (en) Assembling external prestressing RPC wind power tower
CN203755778U (en) Assembly external pre-stress reactive powder concrete wind power tower
CN204849569U (en) Steel pipe concrete stem stem prefabricated unit construction bridge pier stud of putting more energy into
CN201416148Y (en) Symmetrical anchoring rope pull rod shuttering for oblique post
CN105970803B (en) The shearing resistance energy-dissipating device and construction method of assembled bridge pier
CN209040349U (en) A kind of ring muscle fastening shear wall structure being easily installed
CN202266073U (en) Steel tower rising structure of power transmission line
CN205662838U (en) Prestressing force joint construction of pier is assembled to prefabricated segment
CN101451380B (en) Processing method of prefabricating common concrete outer plate recycled concrete core shear wall
CN103046670B (en) Prefabricated recycled concrete shear wall with energy dissipation connector and fabrication method
CN202989755U (en) Integral-casting and fabricated prestressing force bridge structure
CN204590062U (en) A kind of pole tower pile used for transmission line
CN207619860U (en) A kind of beam bridge ruggedized construction
CN203429655U (en) Assembly type steel reinforced concrete single-double column foundation for container prefabricated house
CN206267169U (en) A kind of split blade type prestressing force anchor slab
CN201588413U (en) Reinforcing structure for concrete bracket in original workshop
CN109208786A (en) A kind of ring muscle that is easily installed fastens shear wall structure and its installation method
CN2673944Y (en) Prestressed pipe pile with large end filled with sand
CN203361184U (en) Tower foundation form of overhead transmission line
CN205530324U (en) Miniature stake of thin -walled cold -formed steel
CN204356793U (en) A kind of assembling hollow reinforced concrete independent foundation
CN207277864U (en) A kind of concrete temporary support moulding bed for large-scale steel structure assembly
CN203373631U (en) Prefabricated reinforced concrete pavement slab
CN203373630U (en) Prefabricated hollow reinforced concrete pavement slab
CN203878460U (en) Prefabricated assembly combined type portal pier

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120606

Termination date: 20121029