CN202227749U CN 201120321034 CN201120321034U CN202227749U CN 202227749 U CN202227749 U CN 202227749U CN 201120321034 CN201120321034 CN 201120321034 CN 201120321034 U CN201120321034 U CN 201120321034U CN 202227749 U CN202227749 U CN 202227749U
Authority
CN
China
Prior art keywords
track
underground
traffic
ground
lower platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201120321034
Other languages
Chinese (zh)
Inventor
唐静
宋丛丽
周小斌
缪东
叶芹禄
肖俊
杨铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN 201120321034 priority Critical patent/CN202227749U/en
Application granted granted Critical
Publication of CN202227749U publication Critical patent/CN202227749U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses an underground automatic parking area for track traffic, which comprises an underground traffic track arranged below an underground platform; pillars for supporting the underground platform are arranged at four sides of the underground traffic track; the underground traffic track is connected with an ATC (Automatic Train Control) system of a track traffic main line; and the underground traffic track is communicated with a railway through an interconnection track. According to the underground automatic parking area for the track traffic disclosed by the utility model, the parking area is arranged underground; the parking and maintaining requirements of track traffic trains can be satisfied; furthermore, the ground space can also be sufficiently utilized for developing commercial buildings and residential buildings, thus, the land use efficiency is greatly increased.

Description

The underground automated parking ground of track traffic
Technical field
The utility model relates to the underground automated parking ground of a kind of track traffic, and it is applicable to rail traffic vehicles maintenance base and parking lot.
Background technology
Along with developing rapidly of China's track traffic, the track traffic land scale increases day by day.How saving the area, the service efficiency that improves the soil more and more causes people's attention.The parking lot is as the regional land used sport of rail line, and its land scale often receives the influence of urban development and planning, and the land used efficient that improves the parking lot is very important.
Existing track traffic parking lot all is located on the ground, if the rail line circuit planning in the city bustling location or sight spot district, ground type is still adopted in the design in parking lot, not only can take valuable rare land used resource, badly influences the view in city simultaneously.Owing to receive the buried depth influence at the station that integrates with and the absolute altitude influence of adjacent road and culvert, adopt the parking lot of ground type for the track traffic underground line, increase the energy consumption of climbing thereby must increase the gradient that admission.
In addition, when the domestic city rail traffic vehicles is from main track entering rolling stock section at present, all need carry out the signaling mode conversion, this certainly will bring need set up the conversion rail, increase the service time, increase a series of problems such as management link and service on buses or trains.
Under above-mentioned technical background, design and a kind ofly can improve land used efficient, can ensure that again the parking lot of train safe and operational efficiency seems very important.
Summary of the invention
The purpose of the utility model is in order to solve the deficiency that the above-mentioned background technology exists; Provide a kind of track traffic underground automated parking ground; Make it can not only satisfy the demand that rail transit train stops, keeps in repair; Raising the land utilization efficiency greatly, but also can ensure train safe and operational efficiency, the streamlining management link.
For realizing above-mentioned purpose, the technical scheme that the utility model adopts is following:
The underground automated parking ground of a kind of track traffic; Comprise the underground traffic track that lower platform below, ground is provided with; Be provided with the pillar that supports the ground lower platform around the said underground traffic track; The underground traffic track links to each other with track traffic main track ATC control system, and the underground traffic track is connected with railway through the interconnection track.
Further, said ground lower platform is provided with several daylightings with courtyard or skylight.
Further, be provided with the multi-section escape stair that leads on the ground lower platform between said underground traffic track and the ground lower platform.
Again further, the space of said ground lower platform top is provided with underground parking office building or residential building or commercial building or communal facility.
The utility model is arranged on the parking lot underground, can not only satisfy that rail transit train stops, the demand of maintenance, and the ventilation and the daylighting environment that can utilize lighting and ventilation courtyard or skylight to wait to improve the parking lot, has improved land use efficient greatly.Signal employing in parking lot is linked to each other with track traffic signal equipment main track ATC control system, promptly ensure train safe and operational efficiency, also simplified the equipment of management link.
Description of drawings
Accompanying drawing 1 is the structural texture sketch map of the utility model embodiment.
Label declaration among the figure: 1, underground traffic track; 2, commercial building or communal facility; 3, escape stair; 4, ventilation and lighting well or skylight; 5, platform; 6, pillar; 7, interconnection track.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is done further to specify.
As shown in Figure 1; The underground automated parking ground of the utility model track traffic; Comprise the underground traffic track 1 that lower platform 5 belows, ground are provided with; Be provided with the pillar 6 that supports ground lower platform 5 around the underground traffic track 1, underground traffic track 1 links to each other with track traffic main track ATC control system, and underground traffic track 1 is connected with railway through interconnection track 7.Ground lower platform 5 is provided with the bigger daylighting of several areas with courtyard or skylight 4, is used for daylighting of underground automated parking ground and ventilation.Be provided with the multi-section escape stair 3 that leads on the ground lower platform 5 between underground traffic track 1 and the ground lower platform 5, as the walk up and down passage of underground automated parking ground with ground lower platform 5.The space of lower platform 5 tops, ground is provided with underground parking office building or residential building or commercial building or communal facility.
The utility model is when implementing, and train adopts automatic control system ATC auto arrangement to get into underground traffic track 1, and commander's train can adopt unmanned operation.Train leaves on the underground traffic track 1 after getting into the parking lot, and the staff can carry out upkeep operation to train through escape stair 3 entering parking lots.Underground parking office building or residential building or commercial building or communal facility 2 can fully be developed in space above the ground lower platform 5 of top, parking lot.
In addition, escape stair 3 can be laid in place according to the design in concrete parking lot.The commercial building of multilayer or the exploitation of communal facility 2 can be carried out in the both sides of ground lower platform 5.
The utility model is arranged at the parking lot underground, can not only satisfy the demand that rail transit train stops, keeps in repair, but also can make full use of the exploitation that ground space carries out commercial building and residential building, greatly raising the land utilization efficiency.

Claims (4)

1. underground automated parking ground of track traffic; Comprise the underground traffic track (1) that ground lower platform (5) below is provided with; It is characterized in that: said underground traffic track (1) is provided with the pillar (6) that supports ground lower platform (5) all around; Underground traffic track (1) links to each other with track traffic main track ATC control system, and underground traffic track (1) is connected with railway through interconnection track (7).
2. the underground automated parking ground of track traffic according to claim 1 is characterized in that: said ground lower platform (5) is provided with several daylightings with courtyard or skylight (4).
3. the underground automated parking ground of track traffic according to claim 1 and 2 is characterized in that: be provided with the multi-section escape stair (3) that leads on the ground lower platform (5) between said underground traffic track (1) and the ground lower platform (5).
4. the underground automated parking ground of track traffic according to claim 3 is characterized in that: the space of said ground lower platform (5) top is provided with underground parking office building or residential building or commercial building or communal facility.
CN 201120321034 2011-08-30 2011-08-30 Underground automatic parking area for track traffic Expired - Lifetime CN202227749U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120321034 CN202227749U (en) 2011-08-30 2011-08-30 Underground automatic parking area for track traffic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120321034 CN202227749U (en) 2011-08-30 2011-08-30 Underground automatic parking area for track traffic

Publications (1)

Publication Number Publication Date
CN202227749U true CN202227749U (en) 2012-05-23

Family

ID=46078338

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120321034 Expired - Lifetime CN202227749U (en) 2011-08-30 2011-08-30 Underground automatic parking area for track traffic

Country Status (1)

Country Link
CN (1) CN202227749U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812358A (en) * 2017-03-01 2017-06-09 李新亚 Street self-service three-dimensional garage
CN107856675A (en) * 2017-10-20 2018-03-30 中铁第四勘察设计院集团有限公司 A kind of motor-car uses institute's system control method
CN107878469A (en) * 2017-10-20 2018-04-06 中铁第四勘察设计院集团有限公司 A kind of motor-car uses institute's system
CN111608442A (en) * 2020-07-13 2020-09-01 邓胜红 Ecological energy-saving underground garage of LOFT structure
CN112319508A (en) * 2020-10-30 2021-02-05 山西省交通规划勘察设计院有限公司 Underground automatic parking lot for rail transit

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812358A (en) * 2017-03-01 2017-06-09 李新亚 Street self-service three-dimensional garage
CN107856675A (en) * 2017-10-20 2018-03-30 中铁第四勘察设计院集团有限公司 A kind of motor-car uses institute's system control method
CN107878469A (en) * 2017-10-20 2018-04-06 中铁第四勘察设计院集团有限公司 A kind of motor-car uses institute's system
CN111608442A (en) * 2020-07-13 2020-09-01 邓胜红 Ecological energy-saving underground garage of LOFT structure
CN112319508A (en) * 2020-10-30 2021-02-05 山西省交通规划勘察设计院有限公司 Underground automatic parking lot for rail transit

Similar Documents

Publication Publication Date Title
CN202227749U (en) Underground automatic parking area for track traffic
US20120085612A1 (en) Vehicle propulsion energy and utility power delivery system
CN106638193A (en) Modularized city
CN106428028A (en) Fenster hanging type aerial urban public transit transportation system
Ververo et al. Toward Green TODs
CN101311413A (en) Process for using underground passage combined with roads on ground as passage of trolley bus
CN201460324U (en) Elevated parking lot of rail transit
CN109779295A (en) A kind of Urban Space Characteristics planning and designing system
TWI577590B (en) Solar and hydrodynamic airlift system
CN202081674U (en) Stereoscopic maintenance-free light steel structure parking garage
CN206693036U (en) A kind of multi-functional monorail train hanger
CN207079625U (en) A kind of city emergency drainage system with rapid transit and underground pipe gallery function
CN201873917U (en) Separated type green traffic system
CN211395746U (en) Intercity railway underground station of track area top integration development
CN108104580A (en) Linear city planning system
CN106013938A (en) Overground and underground urban traffic and pipe network complex
CN205557571U (en) Prestressing force divides and adds series side storehouse drainage type underground pipe gallery
CN102677559A (en) Special electromobile road system in house building
CN206396793U (en) City integrated piping lane is connected structure of building together with track traffic underground open-cut station
CN101372825A (en) Method for using underground passage combined with ground road as trolley bus passage
Hamed Sustainable Energy Production Solutions in Railway Stations
CN101392482B (en) Arrangement method of public transit hub station under trestle
CN217379942U (en) Overhead interchange type three-dimensional parking system
CN102720105A (en) Method for building traffic light-free overpass at crossroad (T road)
CN102400426A (en) Preparation method of separate green traffic system device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120523