CN202204726U - Fixing device for whole steel-cored aluminum strand abruption experiment - Google Patents

Fixing device for whole steel-cored aluminum strand abruption experiment Download PDF

Info

Publication number
CN202204726U
CN202204726U CN2011203301572U CN201120330157U CN202204726U CN 202204726 U CN202204726 U CN 202204726U CN 2011203301572 U CN2011203301572 U CN 2011203301572U CN 201120330157 U CN201120330157 U CN 201120330157U CN 202204726 U CN202204726 U CN 202204726U
Authority
CN
China
Prior art keywords
steel
termination
aluminium strand
cored aluminium
fixing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011203301572U
Other languages
Chinese (zh)
Inventor
顾坤林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Far East Cable Co Ltd
New Far East Cable Co Ltd
Far East Composite Technology Co Ltd
Original Assignee
Far East Cable Co Ltd
New Far East Cable Co Ltd
Far East Composite Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Far East Cable Co Ltd, New Far East Cable Co Ltd, Far East Composite Technology Co Ltd filed Critical Far East Cable Co Ltd
Priority to CN2011203301572U priority Critical patent/CN202204726U/en
Application granted granted Critical
Publication of CN202204726U publication Critical patent/CN202204726U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Sampling And Sample Adjustment (AREA)

Abstract

The utility model discloses a fixing device for a whole steel-cored aluminum strand abruption experiment, which includes two fixed ends made of high-strength high-polymer materials and cast at the two ends of the steel-cored aluminum strand respectively. The fixing device has a simple structure and is convenient to operate, and the two fixed ends made of the high-strength high-polymer materials can stand high-strength stretching force, and easily satisfies the test strength requirement specified in the national standard of GB/T1179-2009 round concentric steel-cored aluminum strand.

Description

Whole of a kind of steel-cored aluminium strand is broken test fixtures
Technical field
The utility model relates to whole of a kind of steel-cored aluminium strand and breaks test fixtures.
Background technology
Whole pull-off force test of steel-cored aluminium strand is the project that manufacturer and power department must be tested; GB/T1179-2009 circle line twists in the steel-cored aluminium strand national standard with one heart to be stipulated; " when requiring to carry out the pull-off force test of steel-cored aluminium strand; should be able to bear the calculating that is not less than regulation specified stretching resistance 95%, and arbitrary single line all should not rupture.The pull-off force of steel-cored aluminium strand should through stretching be fixed on suitable degree of accuracy be at least ± 1% tension tester on the method for steel-cored aluminium strand survey.For ease of test, the two ends of steel-cored aluminium strand sample should make suitable termination.Load when duration of test, the pull-off force of steel-cored aluminium strand by one or more single line when twisted wire fracture take place is confirmed.If the fracture of single line occurs in apart from the 1cm of termination, and stretching resistance then can test when requiring less than the pull-off force of regulation again, can test at most 3 times.”
Generally, one is to use the steel pipe crimping to connect fixes, and presses interface that single aluminium wire fracture is arranged, and causes test failure to test again, and cost is high.Two are to use low-melting alloy to cast fixes; Because the adhesion adhesion of low-melting alloy and steel and aluminium is low, when pull-off force was tested, the fracture of single line occurred in apart from the 1cm of termination; And stretching resistance is less than the pull-off force requirement of regulation, and it is low to break the success of the test rate.
The utility model content
The utility model technical matters to be solved provides a kind of whole of steel-cored aluminium strand that can stand high-strength pulling force and breaks test fixtures.
In order to solve the problems of the technologies described above, the technical scheme that the utility model provided is: whole of a kind of steel-cored aluminium strand is broken test fixtures, comprises the fixedly termination of being processed by the high strength macromolecular material; Said fixedly termination is provided with two, two fixedly the termination cast in the two ends of steel-cored aluminium strand respectively.
Said fixedly termination is truncated cone shape; Said two fixedly the big nose circle of termination lay respectively at the outer end at the two ends of steel-cored aluminium strand.
After having adopted technique scheme; The utlity model has positive effect: the utility model is simple in structure; Easy to operate; Process by the high strength macromolecular material two fixedly the termination can stand high-strength pulling force, surpass GB/T1179-2009 circle line and twist the proof strength requirement of stipulating in the steel-cored aluminium strand national standard with one heart.
Description of drawings
For the content that makes the utility model is expressly understood more easily,, the utility model is done further detailed explanation, wherein below according to specific embodiment and combine accompanying drawing
Fig. 1 is the structural representation of the utility model.
Structural representation when Fig. 2 scatters for the termination of steel-cored aluminium strand.
Fig. 3 is the structural representation of the steel die among the embodiment 1 of the utility model.
Fig. 4 is the right view of Fig. 3.
Label in the accompanying drawing is:
Fixedly the termination 1.
Embodiment
(embodiment 1)
See Fig. 1, present embodiment comprises fixedly termination 1.
Fixedly termination 1 is processed by the high strength macromolecular material.Fixedly termination 1 is provided with two, two fixedly termination 1 cast in the two ends of steel-cored aluminium strand respectively.Fixedly termination 1 is truncated cone shape.Two fixedly the big nose circle of termination 1 lay respectively at the outer end at the two ends of steel-cored aluminium strand.
The casting fixedly prescription of the high strength macromolecular material of termination 1 is: 90 parts of 100 parts of bisphenol A type epoxy resins, 35 parts of modified polyamide epoxy curing agents, 10 parts of simple function group epoxy active diluents, 2 parts of hexane diamine catalyzer, 2 parts of coupling agents, 0.5 part of organosilane foam-breaking agent, 40 parts of high fineness silica flour reinforcing agents and high fineness hydrate of aluminium tendering resistant agents.
The carbon fiber complex core aerial condutor is broken test method, may further comprise the steps:
1. aluminium wire and the steel wire with two terminations of steel-cored aluminium strand scatters, and be as shown in Figure 2.
2. two termination top casting high strength macromolecular materials that scatter at steel-cored aluminium strand form two fixedly terminations 1.Be specially: at first on the inwall of the steel die that is truncated cone shape, coat release agent, the structure of steel die such as Fig. 3 and shown in Figure 4; Then two terminations of scattering of steel-cored aluminium strand are put into steel die respectively, upwards place two terminations of scattering of steel-cored aluminium strand, and the little nose circle of steel die downwards, nose circle is upwards placed greatly; Casting high strength macromolecular material forms two fixedly terminations 1 in steel die then.
The compound method of release agent is: 10 parts of weighing polyvinyl alcohol PVA pulverulent solids, and put into 90 parts distilled water, and be heated to 65~75 ℃, fully stir, make pressed powder be dissolved into transparence liquid fully, being cooled to normal temperature can use.
3. after the high strength macromolecular material solidifies with two fixedly termination 1 cooperate with two circular stiff ends of tension tester respectively, and carry out tensile test.
Above-described specific embodiment; Purpose, technical scheme and beneficial effect to the utility model have carried out further explain, it should be understood that the above is merely the specific embodiment of the utility model; Be not limited to the utility model; All within the spirit and principle of the utility model, any modification of being made, be equal to replacement, improvement etc., all should be included within the protection domain of the utility model.

Claims (2)

1. whole an of steel-cored aluminium strand is broken test fixtures, it is characterized in that: comprise the fixedly termination (1) of being processed by the high strength macromolecular material; Said fixedly termination (1) is provided with two, two fixedly termination (1) cast in the two ends of steel-cored aluminium strand respectively.
2. whole of a kind of steel-cored aluminium strand according to claim 1 is broken test fixtures, it is characterized in that: said fixedly termination (1) is truncated cone shape; Said two fixedly the big nose circle of termination (1) lay respectively at the outer end at the two ends of steel-cored aluminium strand.
CN2011203301572U 2011-09-05 2011-09-05 Fixing device for whole steel-cored aluminum strand abruption experiment Expired - Lifetime CN202204726U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203301572U CN202204726U (en) 2011-09-05 2011-09-05 Fixing device for whole steel-cored aluminum strand abruption experiment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203301572U CN202204726U (en) 2011-09-05 2011-09-05 Fixing device for whole steel-cored aluminum strand abruption experiment

Publications (1)

Publication Number Publication Date
CN202204726U true CN202204726U (en) 2012-04-25

Family

ID=45968844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203301572U Expired - Lifetime CN202204726U (en) 2011-09-05 2011-09-05 Fixing device for whole steel-cored aluminum strand abruption experiment

Country Status (1)

Country Link
CN (1) CN202204726U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980800A (en) * 2011-09-05 2013-03-20 远东电缆有限公司 Fixing device and method for breaking test of carbon fiber composite core aerial conductor
CN107655752A (en) * 2017-10-19 2018-02-02 国网新疆电力公司电力科学研究院 A kind of power transmission tower aluminum stranded conductor tensile test fixture

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980800A (en) * 2011-09-05 2013-03-20 远东电缆有限公司 Fixing device and method for breaking test of carbon fiber composite core aerial conductor
CN107655752A (en) * 2017-10-19 2018-02-02 国网新疆电力公司电力科学研究院 A kind of power transmission tower aluminum stranded conductor tensile test fixture

Similar Documents

Publication Publication Date Title
CN103669208B (en) A kind of anchoring process being applicable to large-tonnage FRP inhaul cable
CN102220712A (en) Steel wire rope containing composite material
CN202204726U (en) Fixing device for whole steel-cored aluminum strand abruption experiment
CN202183580U (en) Suspension wire clamp
CN102980800A (en) Fixing device and method for breaking test of carbon fiber composite core aerial conductor
CN104234325B (en) The installation method of FRP rib tape screw plug bond type anchorage
CN103255658B (en) A kind of fiber rope end casting consolidation method
CN104234324A (en) Novel FRP rib threaded adhesive type anchorage device and mounting method of anchorage device
CN207318233U (en) A kind of rubber seal tensile test piece special fixture
CN204166984U (en) A kind of flexible tensile cable
CN202483189U (en) Strand tapered anchorage pre-tightening device
CN206177789U (en) A testing arrangement that is used for gluing agent and material cohesion
CN208721501U (en) A kind of breaking force of rope measuring device
CN204112601U (en) The threaded bond type anchorage of new-type FRP rebar
CN204331117U (en) A kind of ADSS optical cable short span taper strain clamp
CN202625646U (en) Steel wire rope twisting preventing device
CN102979347A (en) Connecting structure of composite material tower rod and ladder supporting seat
CN202068156U (en) Pre-twisted binary division anti-skid ball separation rod
CN203296267U (en) Bonded anchorage for FRP (Fiber Reinforce Plastic) ribs
CN204112600U (en) New type FRP rib tape screw plug bond type anchorage
CN103290998B (en) Bond-type anchorage for FRP (Fiber Reinforced Plastic) rib and implementation method thereof
CN202625664U (en) Attaching and connecting plate in tower crane for assembling steel tube tower
CN205120454U (en) Wire centre gripping end making devices
CN202562802U (en) Connecting device for cable and fitting tensile test
CN209525035U (en) A kind of fixture for breaking force of rope measurement

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120425

CX01 Expiry of patent term