CN202202561U - Construction sleeve for reserved hole of floor slab - Google Patents

Construction sleeve for reserved hole of floor slab Download PDF

Info

Publication number
CN202202561U
CN202202561U CN 201120246064 CN201120246064U CN202202561U CN 202202561 U CN202202561 U CN 202202561U CN 201120246064 CN201120246064 CN 201120246064 CN 201120246064 U CN201120246064 U CN 201120246064U CN 202202561 U CN202202561 U CN 202202561U
Authority
CN
China
Prior art keywords
sleeve
steel plate
steel sleeve
steel
steel bushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120246064
Other languages
Chinese (zh)
Inventor
贾蒙
杨东明
袁小林
王红媛
王金香
李嵬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Third Construction Co Ltd of China Construction First Group Co Ltd
Original Assignee
China Construction First Group Corp Ltd
Third Construction Co Ltd of China Construction First Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, Third Construction Co Ltd of China Construction First Group Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN 201120246064 priority Critical patent/CN202202561U/en
Application granted granted Critical
Publication of CN202202561U publication Critical patent/CN202202561U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a hole construction sleeve is reserved to floor, includes the steel sleeve, its characterized in that: the diameter of the steel sleeve is matched with the reserved hole of the floor slab, the height of the steel sleeve is matched with the thickness of the floor slab, the upper portion of the steel sleeve is covered with a closed cover plate, the upper edge of the steel sleeve is connected with a sleeve handle, the bottom of the steel sleeve is provided with a bottom steel plate, self-tapping screw holes are symmetrically formed in two sides of the center of the bottom steel plate, the center of the bottom steel plate is connected with a screw rod concentric with the steel sleeve, and the upper end of the screw rod penetrates through the closed cover plate to be connected with a fastening. The bottom steel plate is in a straight line shape, a cross shape, a meter shape or a round shape, and the length of the bottom steel plate is not more than the diameter of the steel sleeve. The utility model discloses the installation is convenient with the dismantlement, and is fixed firm, and it is tight with the template contact, prevents to leak thick liquid, makes to reserve the hole position accurate, and the appearance is pleasing to the eye, and repeatedly usable has avoided the waste of manual work and material, but wide application in the building structure construction.

Description

Floor reserving hole construction sleeve
Technical field
The utility model relates to a kind of structure construction instrument, particularly a kind of floor reserving hole construction sleeve.
Background technology
When structure construction, the sleeve pipe installation is a very strict operation during floor reserving hole, and common practices is with iron nail and iron wire colligation fixed sleeving; This mode very easily goes wrong in construction, mainly shows fixing insecure, contacts imprecision with template; Easy spillage when concrete pouring must also can destroy floor through picking cutter ability pore-forming after causing sleeve pipe to take out sometimes; Cause the waste of manual work, material, construction is also inconvenient.
The utility model content
The purpose of the utility model provides a kind of floor reserving hole construction sleeve, solve fixing insecure, the contact imprecision of the sleeve that exists when traditional floor reserving hole sleeve pipe is installed, the technical problem of spillage easily; And solve sleeve pipe and can't reuse, cause that cost rises, the problem of construction inconvenience.
For realizing above-mentioned purpose, the utility model adopts following technical scheme:
A kind of floor reserving hole construction sleeve; Comprise steel bushing, it is characterized in that: the diameter of said steel bushing and floor reserving hole adapt, and height adapts with slab thickness; Closed cover is stamped on the top of steel bushing; The upper edge of steel bushing is connected with the sleeve pipe handle, and the bottom steel plate is arranged at the bottom of steel bushing, and bilateral symmetry has the self-tapping screw hole to said bottom steel plate at the center; The center of bottom steel plate is connected with a screw rod concentric with steel bushing, and the upper end of said screw rod is passed closed cover and is connected with clamp nut.
Said bottom steel plate can be in-line, cross, M shape or circle, and its length is not more than the steel bushing diameter.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model has overcome the sleeve pipe that exists when traditional floor reserving hole sleeve pipe is installed can't be reused, and causes that cost rises, the shortcoming of construction inconvenience, has solved fixing insecure, the contact imprecision of sleeve, spillage technical problem easily.
The utlity model has following technological progress:
The utility model has solved all disadvantages that produce in the previous ordinary casing construction, and its advantage is that installation and removal are convenient, fixation; Contact tightly with template, stopped the spillage phenomenon, make the reserving hole position accurate; Good looking appearance; And reusable, as to have stopped artificial and material waste can be widely used in the building structure construction.
Description of drawings
Below in conjunction with accompanying drawing the utility model is done further detailed explanation.
Fig. 1 is the structural representation of the utility model.
Fig. 2 is the utility model bottom surface structural representation.
Reference numeral: 1-sleeve pipe handle, 2-steel bushing, 3-screw rod, 4-self-tapping screw hole, 5-bottom steel plate, 6-clamp nut, 7-closed cover.
The specific embodiment
Embodiment is referring to Fig. 1, shown in Figure 2, and a kind of floor reserving hole construction sleeve comprises steel bushing 2; It is characterized in that: the diameter of said steel bushing 2 and floor reserving hole adapt; Height adapts with slab thickness, and closed cover 7 is stamped on the top of steel bushing 2, and the upper edge of steel bushing 2 is connected with sleeve pipe handle 1; Bottom steel plate 5 is arranged at the bottom of steel bushing 2; Bilateral symmetry has the self-tapping screw hole 4 that is used to connect template at the center for said bottom steel plate 5, and the center of bottom steel plate 5 is connected with a screw rod 3 concentric with steel bushing, and the upper end of said screw rod 3 is passed closed cover 7 and is connected with clamp nut 6.
Said bottom steel plate 5 is cross, M shape or circle, and its length is not more than steel bushing 2 diameters.
Method for using: during construction; Use self-tapping screw bottom steel plate 5 to be fixed on the kapok plate of construction floor, after the upper end of screw rod 3 is passed closed cover 7 and is connected firmly with clamp nut 6, begin to carry out concreting; When concrete setting reaches 70% left and right sides, steel bushing 2 is extracted.

Claims (2)

1. floor reserving hole construction sleeve; Comprise steel bushing (2), it is characterized in that: the diameter and the floor reserving hole of said steel bushing (2) adapt, and height adapts with slab thickness; Closed cover (7) is stamped on the top of steel bushing (2); The upper edge of steel bushing (2) is connected with sleeve pipe handle (1), and bottom steel plate (5) is arranged at the bottom of steel bushing (2), and bilateral symmetry has self-tapping screw hole (4) to said bottom steel plate (5) at the center; The center of bottom steel plate (5) is connected with a screw rod concentric with steel bushing (3), and the upper end of said screw rod (3) is passed closed cover (7) and is connected with clamp nut (6).
2. floor reserving hole construction sleeve according to claim 1, it is characterized in that: said bottom steel plate (5) is in-line, cross, M shape or circle, and its length is not more than steel bushing (2) diameter.
CN 201120246064 2011-07-13 2011-07-13 Construction sleeve for reserved hole of floor slab Expired - Fee Related CN202202561U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120246064 CN202202561U (en) 2011-07-13 2011-07-13 Construction sleeve for reserved hole of floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120246064 CN202202561U (en) 2011-07-13 2011-07-13 Construction sleeve for reserved hole of floor slab

Publications (1)

Publication Number Publication Date
CN202202561U true CN202202561U (en) 2012-04-25

Family

ID=45966692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120246064 Expired - Fee Related CN202202561U (en) 2011-07-13 2011-07-13 Construction sleeve for reserved hole of floor slab

Country Status (1)

Country Link
CN (1) CN202202561U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103231444A (en) * 2013-04-16 2013-08-07 姚景祥 Tool for manufacturing exhaust vents of smoke exhaust ventilating pipes and using method thereof
CN103291072A (en) * 2013-05-31 2013-09-11 上海宝冶集团有限公司 Method for reserving holes in floors by aid of PVC (polyvinyl chloride) sleeves
CN105735643A (en) * 2016-04-08 2016-07-06 中建八局第一建设有限公司 Sleeve device for reserved hole of pipeline
CN108385971A (en) * 2018-02-11 2018-08-10 中国建筑局(集团)有限公司 Turnover type pipeline sleeve fixing tool on aluminum alloy template and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103231444A (en) * 2013-04-16 2013-08-07 姚景祥 Tool for manufacturing exhaust vents of smoke exhaust ventilating pipes and using method thereof
CN103231444B (en) * 2013-04-16 2016-09-28 姚景祥 Smoke discharge ventilation pipeline steam vent tools and using method thereof
CN103291072A (en) * 2013-05-31 2013-09-11 上海宝冶集团有限公司 Method for reserving holes in floors by aid of PVC (polyvinyl chloride) sleeves
CN105735643A (en) * 2016-04-08 2016-07-06 中建八局第一建设有限公司 Sleeve device for reserved hole of pipeline
CN108385971A (en) * 2018-02-11 2018-08-10 中国建筑局(集团)有限公司 Turnover type pipeline sleeve fixing tool on aluminum alloy template and construction method thereof

Similar Documents

Publication Publication Date Title
CN202202561U (en) Construction sleeve for reserved hole of floor slab
CN206495501U (en) A kind of cast-in-place concrete floor reserving hole template
CN202644990U (en) Fixing device for reserved pipeline or hole template
CN201362959Y (en) Floor slab preformed hole device
CN206109997U (en) Two -sided sliding chute device
CN204609300U (en) A kind of fixed sleeving for construction drainage pipeline preformed hole hole
CN208267362U (en) A kind of constructing device of deformation joint concrete wall formwork
CN207032868U (en) The form clamp of reversed beam is poured after a kind of
CN103306473A (en) Tool type anchoring part for overhanging scaffold
CN202187553U (en) Floor prepared hole die with steel bed die
CN205742548U (en) A kind of pre-shear stud being embedded in concrete
CN203097290U (en) Assembled type split bolt
CN206554071U (en) H profile steel and round steel pipe built pile
CN206144146U (en) Fixing device of stagnant water for building festival
CN204718855U (en) The simple type fast repairing leveling device of concrete core sample
CN201635404U (en) Precise positioning structure of preserved pipeline
CN201372568Y (en) Connection device for clear water concrete construction
CN211286687U (en) Cast-in-place concrete floor thickness controller
CN204370564U (en) Underfloor constructional column concrete pouring structure
CN212105168U (en) Floor thickness control instrument
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN204252537U (en) A kind of hole to be provided mould
CN203795854U (en) Preformed hole formwork fixing device for bare concrete floor
CN209924437U (en) Novel detachable die for reserving holes
CN205476442U (en) A wall pouring mode structure is led to anti - L shape concrete

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120425