CN202170474U - Support system mixing type combined beam cable-stayed bridge - Google Patents

Support system mixing type combined beam cable-stayed bridge Download PDF

Info

Publication number
CN202170474U
CN202170474U CN2011201807363U CN201120180736U CN202170474U CN 202170474 U CN202170474 U CN 202170474U CN 2011201807363 U CN2011201807363 U CN 2011201807363U CN 201120180736 U CN201120180736 U CN 201120180736U CN 202170474 U CN202170474 U CN 202170474U
Authority
CN
China
Prior art keywords
pier
span
main
constructed
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201807363U
Other languages
Chinese (zh)
Inventor
徐恭义
梅新咏
程应刚
龚俊
谢波
朱军
彭振华
侯键
徐力
廖慕捷
陈宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Original Assignee
China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Reconnaissance and Design Institute Co Ltd filed Critical China Railway Major Bridge Reconnaissance and Design Institute Co Ltd
Priority to CN2011201807363U priority Critical patent/CN202170474U/en
Application granted granted Critical
Publication of CN202170474U publication Critical patent/CN202170474U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a support system mixing type combined beam cable-stayed bridge. Side-span concrete beams are poured on a side pier and an auxiliary pier of the cable-stayed bridge, a stay cable is hung on a middle-span combined beam, large-tonnage spherical steel supports are arranged between two main towers and main tower piers, the middle-span combined beam is constructed between the two large-tonnage spherical steel supports, the concrete beams are adopted as side spans, the combined beam is adopted as a middle span, and the whole bridge adopts a support system. In construction, foundations of the main tower piers, the auxiliary pier and the side pier are firstly constructed, pier bodies of the main tower piers, the auxiliary pier and the side pier are subsequently constructed, the large-tonnage spherical steel supports are hoisted to conduct pier-beam temporary consolidation of the side-span concrete beams and the main tower piers, a pier-beam temporary consolidation device is removed until the middle span is closed, so as to complete the transformation of a structure system. In the utility model, a main tower structure is simple in structure, good in stress and fewer in used materials; side-span main beams and the main towers are synchronously constructed, and middle-span main beams are constructed by a single cantilever method, thus being strong in wind resistance in construction; and the middle span can be constructed synchronously with the main towers, and the whole bridge can be closed soon after the main towers are capped, so that the construction period is short.

Description

The hybrid bondbeam cable stayed bridge of bearing system
Technical field
The utility model belongs to bridge construction engineering field, relates to a kind of cable stayed bridge of new structure form.
Background technology
China builds traffic infrastructure in a large number in recent years; The cable stayed bridge of topography and geomorphologies such as various leap rivers, straits, highway, railway continues to bring out thereupon, requires the design of cable stayed bridge and building technology to constantly bring forth new ideas development to adapt to the needs of various outside construction conditions.
Cable stayed bridge mainly is made up of king-tower, suspension cable, girder.King-tower is mainly reinforced concrete structure, also has the minority bridge to adopt head tower.Suspension cable adopts parallel steel wire suspension cable or steel strand stay cable.Girder mainly adopts prestressed reinforced concrete construction, bondbeam structure and steel box-beam structure, also has the minority bridge to adopt hybrid bondbeam structure and hybrid steel box-beam structure.
The structural system of double pylon cable stayed bridge mainly adopts floating system, also has the minority bridge to adopt fixed system and bearing system.
In original cable stayed bridge form, hybrid bondbeam cable stayed bridge is considerably less, and bearing system cable stayed bridge is also considerably less, and does not also have hybrid bondbeam cable stayed bridge of the two bearing system that combines and job practices thereof.
The actual bridge construction condition that the applicant ran into is following: the bridge location place belongs to the plains region, build a double pylon cable stayed bridge, and its main span needs low-angle to be inclined cross three railway lines, and one of them end bay is in the land, and another end bay will be crossed over innavigable river.
The main span of bridge will be crossed over railway line, for not influencing railways train operation, in stride and should adopt bondbeam.End bay can be set up support fluid concrete beam, the end bay concrete beam of when the construction king-tower, can constructing simultaneously like this.The bridge location place belongs to the plains region, and bridge floor is not high with lower king-post strut, adopts fixed system cannot satisfy force request.Very wide because of girder, and main span is that low-angle is inclined cross railway line, as adopts conventional floating system will strengthen the main span span; Increase cost; And have a main pylon pier need be built up in river course central authorities, river course department is difficult to approval, therefore needs to adopt the hybrid bondbeam cable stayed bridge of bearing system.
Summary of the invention
The purpose of the utility model is to above-mentioned present situation, aim to provide a kind of king-tower structure construction simple, stressed good, materials are few, the wind loading rating of construction period is strong, safety factor is high, the hybrid bondbeam cable stayed bridge of bearing system that the duration is short.
The implementation of the utility model purpose is the hybrid bondbeam cable stayed bridge of bearing system, cast end bay concrete beam on abutment pier, the auxiliary pier; In stride and hang suspension cable on the bondbeam; The spherical steel support of large-tonnage is arranged between two king-towers and the main pylon pier, stride bondbeam in the construction between the spherical steel support of two large-tonnages, end bay adopts concrete beam; In stride the employing bondbeam, full-bridge adopts the bearing system.
The utility model king-tower designs for straight column type, is equipped with parallel rope face, and the king-tower structure construction is simple, and stressed good, materials are few, saves cost, can enrich the king-tower moulding simultaneously; End bay girder and king-tower synchronously construction are accomplished in advance, thus in to stride girder be that single-cantilever is constructed, cable stayed bridge improves in wind resistance and other safety factor of construction period greatly; King-tower designs for straight column type, and suspension cable is parallel rope face, can construct synchronously with king-tower so stride in the main bridge also, and king-tower binds and can reach full-bridge soon and close up, and significantly the reduction of erection time, obtains favorable economic benefit.
Stride the suitable bondbeam that uses in all, end bay is fit to use cast-in-situ concrete beam, and the double pylon cable stayed bridge that lower king-post strut is not high all can adopt the utility model.
Description of drawings
Fig. 1 is the utility model structural representation,
Fig. 2 be the A-A of Fig. 1 to cut-away view,
Fig. 3 is that the B-B of Fig. 1 is to cut-away view.
The specific embodiment
With reference to Fig. 1,2,3; Cast end bay concrete beam 2 on the abutment pier 5 of the utility model, the auxiliary pier 6; In stride to hang on the bondbeam 3 to have between suspension cable 4, two king-towers 1 and the main pylon pier 7 in 8 constructions of the large-tonnage spherical steel support of spherical steel support 8, two large-tonnages and stride bondbeam 3.
With reference to Fig. 1,2,3, the concrete steps of construction the utility model are following:
The basis of a, elder generation's construction main pylon pier 7, auxiliary pier 6, abutment pier 5, its pier shaft of constructing subsequently,
B, the spherical steel support 8 of lifting large-tonnage are on main pylon pier, and the end bay concrete beam 2 of cast and the fixed part of king-tower is accomplished the temporary consolidation of main pylon pier and end bay concrete beam,
The construction of king-tower 1 is carried out on c, one side, on one side the remaining end bay concrete beam of segmented cast,
D, carry out on one side the king-tower construction again, in cantilever construction stride bondbeam 3 and hang suspension cable 4 on one side, up to maximum single-cantilever state,
E, stride the closure segment construction in carrying out, remove the temporary consolidation of main pylon pier and end bay concrete beam, accomplish Program for structural Transformation, the main structure construction completion,
F, carry out the construction of bridge floor and king-tower accessory structure, carry out loading test, full-bridge is tentative to be open to traffic.
The king-tower of the utility model is cemented on the end bay concrete beam, through dropping on the main pylon pier in that the spherical steel support of large-tonnage is set at the bottom of the beam.Stride during the end bay concrete beam stretches into a little through be provided with the steel reinforced concrete joint with in stride the fixed as a whole structure of bondbeam.

Claims (1)

1. the hybrid bondbeam cable stayed bridge of bearing system; Cast end bay concrete beam on abutment pier, the auxiliary pier, in stride and hang suspension cable on the bondbeam, it is characterized in that having between two king-towers and the main pylon pier the spherical steel support of large-tonnage; Stride bondbeam in the construction between the spherical steel support of two large-tonnages; End bay adopts concrete beam, in stride the employing bondbeam, full-bridge adopts the bearing system.
CN2011201807363U 2011-05-31 2011-05-31 Support system mixing type combined beam cable-stayed bridge Expired - Lifetime CN202170474U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201807363U CN202170474U (en) 2011-05-31 2011-05-31 Support system mixing type combined beam cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201807363U CN202170474U (en) 2011-05-31 2011-05-31 Support system mixing type combined beam cable-stayed bridge

Publications (1)

Publication Number Publication Date
CN202170474U true CN202170474U (en) 2012-03-21

Family

ID=45828670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201807363U Expired - Lifetime CN202170474U (en) 2011-05-31 2011-05-31 Support system mixing type combined beam cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN202170474U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296525A (en) * 2011-05-31 2011-12-28 中铁大桥勘测设计院有限公司 Support system mixed combined beam cable-stayed bridge and construction method thereof
CN104652245A (en) * 2014-11-05 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Longitudinal constraint method for cable-stayed bridges
CN105672140A (en) * 2016-03-08 2016-06-15 中铁港航局集团有限公司 Erecting, constructing and wind preventing method for long-span cable-stayed bridge steel box girder long cantilever in violent typhoon region

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296525A (en) * 2011-05-31 2011-12-28 中铁大桥勘测设计院有限公司 Support system mixed combined beam cable-stayed bridge and construction method thereof
CN104652245A (en) * 2014-11-05 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Longitudinal constraint method for cable-stayed bridges
CN105672140A (en) * 2016-03-08 2016-06-15 中铁港航局集团有限公司 Erecting, constructing and wind preventing method for long-span cable-stayed bridge steel box girder long cantilever in violent typhoon region

Similar Documents

Publication Publication Date Title
CN102296525B (en) Support system mixed combined beam cable-stayed bridge and construction method thereof
Hu et al. Recent development of design and construction of medium and long span high-speed railway bridges in China
CN211815489U (en) Super large span flying swallow type concrete filled steel tube arch bridge with self-anchoring suspension cable system
CN102330414B (en) Hanging basket cantilever method construction method of large-span continuous rigid beam sidespan cast-in-place beam section
CN105648924B (en) The construction method of multispan freely-supported steel truss girder bridge
CN102535327B (en) Through prestress steel truss and concrete combined continuous steel structure bridge and construction method thereof
CN102154990B (en) Electing method for side span overhang-middle span cable-stayed three-tower self-anchored type combination suspension bridge
CN106758871A (en) A kind of full cantilever construction prestressed concrete continuous rigid-framed bridge and its construction method
CN110205938B (en) Steel pipe arch installation method of through beam-arch combination bridge
CN207143733U (en) A kind of simple-supported thencontinuous bridge system converting system
CN208151833U (en) A kind of construction of novel RC-masonry combination arch bridge
CN103046476A (en) Railway long-span rotator T-shaped bridge construction method
CN103147385B (en) Double-spliced extradosed cable-stayed bridge
CN103938533A (en) Simple-supported continuous structure and construction method thereof
CN102839598A (en) Mixed type cable-supported bridge
Oliveira Pedro et al. Composite cable-stayed bridges: state of the art
CN202170474U (en) Support system mixing type combined beam cable-stayed bridge
CN210395128U (en) Hollow core plate beam connection structure in bridge widening
CN208072166U (en) Hybrid combining beam three stride continuous suspension bridge
CN201801806U (en) Externally-prestressed continuous beam bridge with first simple supporting and second continuation
CN110004816B (en) Corrugated steel web prestress UHPC combined box girder and construction method thereof
CN202830732U (en) Mixing-type cable- rope bearing bridge
CN102392421B (en) Small-town arch bridge local widening and reinforcing method based on characteristic of tidal traffic flow
CN211772868U (en) Pier temporary consolidation device in large-span continuous beam
CN202849924U (en) Corrugated steel web plate concrete continuous box girder for curved bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20120321

Effective date of abandoning: 20130911

RGAV Abandon patent right to avoid regrant