CN202157321U - Screwing-in type large bearing steel pipe pile - Google Patents

Screwing-in type large bearing steel pipe pile Download PDF

Info

Publication number
CN202157321U
CN202157321U CN2011202198521U CN201120219852U CN202157321U CN 202157321 U CN202157321 U CN 202157321U CN 2011202198521 U CN2011202198521 U CN 2011202198521U CN 201120219852 U CN201120219852 U CN 201120219852U CN 202157321 U CN202157321 U CN 202157321U
Authority
CN
China
Prior art keywords
steel pipe
pile
pipe pile
pile body
screwing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011202198521U
Other languages
Chinese (zh)
Inventor
张雷
颜东锋
章国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Sino Transport Technology Co., Ltd.
Original Assignee
SINO TRANSPORT MATERIALS GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SINO TRANSPORT MATERIALS GROUP CO Ltd filed Critical SINO TRANSPORT MATERIALS GROUP CO Ltd
Priority to CN2011202198521U priority Critical patent/CN202157321U/en
Application granted granted Critical
Publication of CN202157321U publication Critical patent/CN202157321U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a screwing-in type large bearing steel pipe pile and aims at providing the screwing-in type large bearing steel pipe pile which is simple in structure, convenient and quick to fabricate, high in production efficiency and convenient to construct so as to improve bearing force of pipe piles or reduce the number of piles to be piled and reduce vibration and noise generated in construction simultaneously. The technical scheme is that the screwing-in type large bearing steel pipe pile comprises a pipe-shaped pile body and is characterized in that spiral blades are coaxially arranged on the outer cylindrical surface of the pile body. The screwing-in type large bearing steel pipe pile is suitable for foundations of buildings.

Description

The big carrying steel pipe pile of screw-in
Technical field
The utility model relates to a kind of steel pipe pile, and the big carrying steel pipe pile of particularly a kind of screw-in is mainly as the building foundation.
Background technology
The load that is arranged on generations such as ground building and building structure is supported by ground usually.In case therefore the weight of structure surpasses the support force of ground; Will begin to occur the anomalies such as sinking of different shape; Sink to tilting to enlarge after after a while, structure becomes and can't continue to use, so when building the structure of constant weight; At first to make geological test, use foundation pile if the support force deficiency then need be strengthened support force in the place of building.For example need to strengthen support force and can use steel pipe system or concrete system pile body for building.Can adopt is driven underground pile body utilizes the method for the frictional force between pile body surface and the stratum, also can adopt the method for pile body being buried underground the stratum with required support force.The kind of used pile body is along with height, weight and the distance of building, and the degree of depth with support force stratum is different and change.The method of piling is generally adopted in the construction of foundation pile in the prior art, and this method can be accompanied by the fierceness vibration and the noise of ground.Therefore can make peripheral resident and constructor suffer from the influence of noise and vibration.
Summary of the invention
The technical problem that the utility model will solve is: to the problem of above-mentioned existence provide a kind of simple in structure, manufacturing is convenient, production efficiency is high, the big carrying steel pipe pile of the screw-in of easy construction; To increase the pile tube support force or to reduce piling number, the vibrations and the noise that produce when reducing to construct simultaneously.
The technical scheme that the utility model adopted is: the big carrying steel pipe pile of screw-in, comprise the tubulose pile body, and it is characterized in that: the coaxial spiral vane that is shaped on the external cylindrical surface of said pile body.
The hand of spiral of said blade is left-handed or dextrorotation.
Said blade is that integral body is processed or is spliced by plurality of sections.
Said blade arrangement is in pile body wherein on one section the external cylindrical surface or be arranged on the external cylindrical surface of whole pile body.
Adopt welding fixing between said pile body and the blade.
The beneficial effect of the utility model is: the utility model is the coaxial spiral vane that is shaped on the external cylindrical surface of pile body; The effective cross section of having strengthened the pile body front end is long-pending; Thereby obviously strengthened the load of pile body, made it can bear bigger down force in vertical direction; Because the existence of helical blade under the prerequisite of same load bearing requirements, has reduced the piling number, has accelerated construction speed; With regard to the steel pipe pile of same bearer power, it is underground that the draw of the utility model when construction helical blade capable of using is imbedded pile body, thereby required external force when having reduced construction has reduced the construction power consumption; Adopt screw-in during construction, the vibration and the noise that when job practicess such as hammering commonly used have reduced construction greatly, have produced have improved the working environment and the living environment of constructor and surrounding resident, more apparent modern civilized construction theory greatly.
Description of drawings
Fig. 1 is the front view of embodiment 1.
Fig. 2 is that the A-A of Fig. 1 is to sectional drawing.
Fig. 3 is the front view of embodiment 2.
Fig. 4 is the front view of embodiment 3.
The specific embodiment
Embodiment 1: like Fig. 1, shown in Figure 2, present embodiment comprises the tubulose pile body 1 that steel pipe is processed, and coaxial welding has spiral vane 2 (steel) on its external cylindrical surface.Blade 2 can be that directly integral solder also can be by being welded in pile body 1 surface after the plurality of sections splicing in pile body 1 surface behind the global formation in this example, and this blade arrangement is on the external cylindrical surface of whole pile body 1, and its hand of spiral is dextrorotation.
The manufacturing process of present embodiment is following: wherein the technological process of production of pile body 1 is: open flat-sanction plate-edging-pipe crimping-welding-full circle-aligning-flush-detection-packing warehouse-in etc.; Helical blade 2 adopts the continuous cold rolling mode to produce, the product size stable performance, and production efficiency is high; At last blade 2 is welded on the external cylindrical surface of pile body 1 and gets final product.
In practical application, excavate a little at first on the ground, this routine steel pipe pile is installed on the building machinery, stand on assigned position, apply revolving force and screw in.When being threaded to prescribed depth the second joint steel pipe pile is welded on the first segment steel pipe pile, notes during welding and should the helical blade 2 of two joint steel pipe piles be aligned mutually.Repeat above operation and reach the regulation requirement up to stake is dark, then the final section steel pipe pile is screwed into the head portion that makes steel pipe pile and exposes the face of land, promptly accomplish piling work at specified altitude.
With regard to as with regard to the steel pipe of foundation pile, if external diameter is bigger, when just burying underground, acting on resistance on the steel pipe part, can to draw the power of steel pipe than spiral part bigger, makes pile body be difficult in ground, bury underground swimmingly.Therefore the required external force of the utility model is less relatively, can select the motor of less power, more shows advantage energy-saving and cost-reducing today for vigorously advocating.
The said steel pipe pile of present embodiment not only can be used for bases such as building structure, middle high constructure, road markings, bridge, also can be widely used on all similar foundation piles.Its helical blade part especially has the effect of tangible increase bearing load for subgrade.
Embodiment 2: as shown in Figure 3, present embodiment structure and embodiment 1 are basic identical, and its difference only is that the hand of spiral of blade 2 is left-handed.
Embodiment 3: as shown in Figure 4, present embodiment structure and embodiment 2 are basic identical, and its difference is that blade 2 only is arranged in pile body 1 wherein on one section the external cylindrical surface, and promptly certain part of pile body 1 external cylindrical surface is welded with blade 2.

Claims (5)

1. the big carrying steel pipe pile of screw-in comprises tubulose pile body (1), it is characterized in that: the coaxial spiral vane (2) that is shaped on the external cylindrical surface of said pile body (1).
2. the big carrying steel pipe pile of screw-in according to claim 1 is characterized in that: the hand of spiral of said blade (2) is left-handed or dextrorotation.
3. the big carrying steel pipe pile of screw-in according to claim 1 is characterized in that: said blade (2) is processed for integral body or is spliced by plurality of sections.
4. the big carrying steel pipe pile of screw-in according to claim 1 is characterized in that: said blade (2) is arranged in pile body (1) wherein on one section the external cylindrical surface or be arranged on the external cylindrical surface of whole pile body (1).
5. the big carrying steel pipe pile of screw-in according to claim 1 is characterized in that: adopt welding fixing between said pile body (1) and the blade (2).
CN2011202198521U 2011-06-27 2011-06-27 Screwing-in type large bearing steel pipe pile Expired - Fee Related CN202157321U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202198521U CN202157321U (en) 2011-06-27 2011-06-27 Screwing-in type large bearing steel pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202198521U CN202157321U (en) 2011-06-27 2011-06-27 Screwing-in type large bearing steel pipe pile

Publications (1)

Publication Number Publication Date
CN202157321U true CN202157321U (en) 2012-03-07

Family

ID=45764963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202198521U Expired - Fee Related CN202157321U (en) 2011-06-27 2011-06-27 Screwing-in type large bearing steel pipe pile

Country Status (1)

Country Link
CN (1) CN202157321U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660945A (en) * 2012-05-31 2012-09-12 福州市第三建筑工程公司 Spiral steel strip and cement diameter-increasing pipe pile and construction method thereof
CN103774687A (en) * 2014-01-22 2014-05-07 深圳市海能通信股份有限公司 Single-pipe tower prefabricated spiral steel pipe pile foundation
CN111042147A (en) * 2019-11-20 2020-04-21 天津建岩岩土工程有限公司 Screw-in type steel pile supporting method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660945A (en) * 2012-05-31 2012-09-12 福州市第三建筑工程公司 Spiral steel strip and cement diameter-increasing pipe pile and construction method thereof
CN102660945B (en) * 2012-05-31 2014-09-10 福州市第三建筑工程公司 Spiral steel strip and cement diameter-increasing pipe pile and construction method thereof
CN103774687A (en) * 2014-01-22 2014-05-07 深圳市海能通信股份有限公司 Single-pipe tower prefabricated spiral steel pipe pile foundation
CN111042147A (en) * 2019-11-20 2020-04-21 天津建岩岩土工程有限公司 Screw-in type steel pile supporting method

Similar Documents

Publication Publication Date Title
CN204370469U (en) A kind of drilled pile long leg jacket offshore wind turbine foundation
CN108487231B (en) Snowflake type steel sheet pile and processing method thereof
CN110984214A (en) Offshore wind power single pile-wing plate-rockfill composite foundation and construction method thereof
CN102400469A (en) Secant pile drum type foundation and construction method thereof
CN202157321U (en) Screwing-in type large bearing steel pipe pile
CN101139834B (en) Concrete pile structure
CN211646449U (en) Combined single-pile foundation of offshore wind turbine
US20140030029A1 (en) Tapered Pipe System and Method for Foundation Support
CN110984212A (en) Offshore wind turbine combined single-pile foundation and construction method
CN105297764A (en) Offshore wind plant fan single pile foundation and construction method thereof
CN202090352U (en) Deep foundation pit bracing system with steel pipe piles-self-drilling type pre-stress anchor rods
CN202124863U (en) Screw anchor excavated composite foundation
CN201850557U (en) Discontinuous flange type screw pile foundation
CN203530959U (en) High-strength underground diaphragm wall
CN102677667A (en) Concrete variable-section pipe pile
CN102888841B (en) End part thread five-pointed-star-shaped variable-section prefabricated pipe pile and construction method thereof
CN102454169A (en) Solar photovoltaic power station foundation construction method
CN102352642A (en) Pneumatic slotting drill bit
RU2725348C2 (en) Multiblade screw pile (versions)
CN202148523U (en) Jet grouting soil-cement-pile strengthened pile
CN109555127A (en) A kind of construction for the flush type multimedium built pile that drills
CN202131625U (en) Pneumatic grooving drill
CN202416304U (en) Special-shaped concrete tubular pile
CN202559341U (en) Concrete variable section pile
CN102900074B (en) Prefabricated tubular pile with end screw thread with X-shaped variable section and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZHEJIANG ZHONGJIAO TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: SINO TRANSPORT MATERIALS GROUP CO., LTD.

Effective date: 20120209

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Chen Hefu

Inventor after: Zhang Lei

Inventor after: Yan Dongfeng

Inventor after: Zhang Guoqiang

Inventor before: Zhang Lei

Inventor before: Yan Dongfeng

Inventor before: Zhang Guoqiang

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHANG LEI YAN DONGFENG ZHANG GUOQIANG TO: CHEN HEFU ZHANG LEI YAN DONGFENGZHANG GUOQIANG

Free format text: CORRECT: ADDRESS; FROM: 310014 HANGZHOU, ZHEJIANG PROVINCE TO: 310020 HANGZHOU, ZHEJIANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120209

Address after: The Zhonghao Grand Hotel Building No. 76 North Qiutao Road Hangzhou city Zhejiang province 310020 room 9006

Patentee after: Zhejiang Sino Transport Technology Co., Ltd.

Address before: Blue City Plaza No. 203 Hangzhou Zhaohui Road, Zhejiang province 310014 City office room 1601

Patentee before: Sino Transport Materials Group Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120307

Termination date: 20140627

EXPY Termination of patent right or utility model