CN202017208U - Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile - Google Patents

Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile Download PDF

Info

Publication number
CN202017208U
CN202017208U CN2011200554644U CN201120055464U CN202017208U CN 202017208 U CN202017208 U CN 202017208U CN 2011200554644 U CN2011200554644 U CN 2011200554644U CN 201120055464 U CN201120055464 U CN 201120055464U CN 202017208 U CN202017208 U CN 202017208U
Authority
CN
China
Prior art keywords
pile
pulley
unit head
main frame
case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200554644U
Other languages
Chinese (zh)
Inventor
谢晓东
卢寿根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Chengdi Construction Co., Ltd.
Original Assignee
SHANGHAI CHENGDI CONSTRUCTION DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI CHENGDI CONSTRUCTION DEVELOPMENT Co Ltd filed Critical SHANGHAI CHENGDI CONSTRUCTION DEVELOPMENT Co Ltd
Priority to CN2011200554644U priority Critical patent/CN202017208U/en
Application granted granted Critical
Publication of CN202017208U publication Critical patent/CN202017208U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a center digging reverse drawing method pile driving device for a pre-stress centrifuge pipe pile and a square pile, comprising a main unit, a hoist mounted on the main unit, a power head, a soil taking box, a pulley and a wire rope, wherein the power head is mounted on the main unit, a soil taking drilling rod is connected below the power head, the lower end of the soil taking box is connected with a pile cap, the lower end of the pile cap is equipped with the centrifuge pipe pile and square pile, the soil taking drilling rod passes through the soil taking box, the centrifuge pipe pile and the square pile, and reaches the bottom. The utility model has the advantages of security, reliability, low cost, high benefit, no soil compacting, no slurry, environmental protection and etc.

Description

The anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of middle pick, square sunk pile device
Technical field
The anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick during the utility model relates to, during the square sunk pile device is mainly used in civilian and industrial infrastructure builds.
Background technology
The pile sinking device of existing prestressed centrifugally pile tube, side's stake mainly is applicable to the device that adopts hammering method and silent piling method, secondly is the device of boring extracting soil plunging and bored pile method.1, hammering method: when the stake diameter is bigger, can adopt hammering method during the no resident of periphery, but exist noise big, black smoke has vibration again during hammering, is a kind of pile-sinking method of high pollution.A lot of cities have forbidden in the center to use, and the hammer of present domestic maximum has only 10T simultaneously, and impact force is 1100 tons to the maximum.When bearing capacity can only change bored pile into greater than 1100 ton hours, so present high ferro and bridge pile foundation all are to select bored pile for use; 2, static pressure method: to be the deadweight that utilizes equipment be pressed into a kind of method in the soil to stake to static pressure method, but because equipment self-weight is bigger, higher to site requirements, it is limited to be pressed into power, the hydraulic pressure pile press of present domestic maximum is 800 tons, bearing capacity of single pile also can only be selected bored pile for use greater than just not adopting this method more than 400 tons.More than two kinds of pile-sinking method exist a kind of insurmountable problem, a large amount of stakes are beaten during (pressures) bury, and the soil body is outwards expanded, a large amount of soil compactions influence peripheral building, road and subway, tunnel and pipeline etc. can both produce cracking, displacement or the like.So can not beat (pressure) prestressed centrifugally pile tube in urban centre and subway limit, limit, tunnel and building compact district, side's stake can only be adopted bored pile.3, boring extracting soil plunging: promptly on former terrace, beat a hole with borrow equipment earlier, again stake is pressed in the hole, this method can adopt at northern area, because moisture content less in the soil, the hole can be shaped, but in southern Yangtze River Delta Area, water content is higher in the soil, draw the hole and just can't be shaped, stake just can't be beaten (pressure) and be gone into the also easy off normal of stake simultaneously.When stake was longer, boring extracting soil just was difficult to carry out, and the darkest at present fetching earth also can only be arrived about 30 meters; 4, another kind of pile foundation is the bored pile method: this method is a stake machine subdrilling hole on the ground, in the hole, irritate the steel bar concrete "forming column again, has the cost height, long in time limit, quality is difficult to not only guarantee and drilled pile but also have a large amount of mud to produce, mud is disposed and is difficult to, a large amount of mud all is disposed in the river, in the lake, in the sea, in the sewer, the size creek, sewer is stopped up by mud, government's annual cleaning sewer and creek mud expense are huge, cause great pollution, but at present on subway limit, urban centre, the river levee limit, the limit, tunnel, super highrise building, the high ferro foundation pile does not have soil compaction when promptly bearing capacity is big and can only adopt the bored pile method.
Summary of the invention
The utility model overcomes the deficiency of above several pile-sinking method, a kind of device that can replace present bored pile pile-sinking method fully, make the anti-daraf(reciprocal of farad) prestressed centrifugally of middle pick pile tube, the square sunk pile device that can use centrifugal pile tube, side's stake in the urban centre, this device has changed several pile-sinking method in the past, not directly stake to be beaten during (pressure) bury, but directly take out soil with auger at the center in stake when stake is pressed in the soil, and the soil that will take out reclaims by collection box simultaneously.
The utility model is to realize like this, the anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick in a kind of, the square sunk pile device, comprise main frame, be installed in the hoist engine on the main frame, unit head, case fetches earth, pulley, wire rope, described unit head is installed on the main frame, described unit head upper end is equipped with pulley, described pulley is connected with wire rope, described wire rope is connected with hoist engine by the main frame top, described unit head below is connected with the drilling rod that fetches earth, described unit head lower end outer periphery is equipped with the screening soil suite, described screening soil suite lower end is connected with the case that fetches earth, described screening soil suite mainly plays and prevents that soil from falling down from the case that fetches earth, hiding soil suite simultaneously can stretch, the described case lower end of fetching earth is connected with pile cover, the described both sides, case lower end of fetching earth are respectively arranged with pulley, on the described pulley wire rope is installed, described wire rope is connected with hoist engine by the pulley that is installed on the main frame, centrifugal pile tube is laid in described pile cover lower end, side's stake, the described drilling rod that fetches earth passes fetch earth case and centrifugal pile tube, side's stake arrives bottom of device.The described unit head and the case that fetches earth can slide on main frame.
The utlity model has following remarkable advantages and beneficial effect:
1) use this device to have low cost, high benefit, noiselessness, free of contamination characteristics;
2) by the case that fetches earth soil is collected, embodied the civilization degree of construction, guarantee safety of construction, the feature of environmental protection;
3) with centrifugal pile tube, side's stake, no soil compaction, no mud have been realized in the time of by digging.
Description of drawings
Fig. 1 is the side schematic view of the anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick, square sunk pile device in the utility model;
Fig. 2 is the connection diagram of the front parts of the anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick, square sunk pile device in the utility model.
Wherein: the 1-main frame; The 2-hoist engine; The 3-unit head; 4-hides soil suite; The 5-case that fetches earth; 6,7,8-pulley; 9,10-wire rope; The centrifugal pile tube of 11-, side's stake; The 12-drilling rod that fetches earth; The 13-pile cover.
The specific embodiment
The anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of a kind of middle pick shown in Fig. 1-2, the square sunk pile device, comprise main frame 1, be installed in the hoist engine 2 on the main frame, unit head 3, case 5 fetches earth, pulley 6,7,8, wire rope 9,10, described unit head 3 is installed on the main frame 1, described unit head 3 upper ends are equipped with pulley 6, described pulley 6 is connected with wire rope 9, described wire rope 9 is connected with hoist engine 2 by main frame 1 top, described unit head 3 belows are connected with the drilling rod 12 that fetches earth, described unit head 3 lower end outer periphery are equipped with and hide soil suite 4, described screening soil suite 4 lower ends are connected with the case 5 that fetches earth, described screening soil suite 4 mainly plays and prevents that soil from falling down from the case 5 that fetches earth, hiding soil suite 4 simultaneously can stretch, described case 5 lower ends of fetching earth are connected with pile cover 13, the described both sides, case 5 lower end of fetching earth are respectively arranged with pulley 7, on the described pulley 7 wire rope 10 is installed, described wire rope 10 is connected with hoist engine 2 by the pulley 8 that is installed on the main frame 1, centrifugal pile tube is laid in described pile cover 13 lower ends, side's stake 11, the described drilling rod 12 that fetches earth passes fetch earth case 5 and centrifugal pile tube, side's stake 11 arrives bottom of device.The described unit head 3 and the case 5 that fetches earth can slide on main frame 1.
The utility model is to implement like this: the drilling rod 12 that fetches earth that is connected with unit head 3 is inserted in the stake hole of centrifugal pile tube, side's stake 11, centrifugal pile tube, side's stake 11 are withstood on the pile cover 13; The centrifugal pile tube of first segment, side's stake 11 drive the pulley 7 that is connected the pulley 8 on the main frame and is installed on the case 5 that fetches earth by hoist engine 2 and rotate, driving pile cover 13 moves down, formed the piling action, driving the drilling rod 12 that fetches earth by unit head 3 simultaneously rotates, fetch earth by the drilling rod 12 that fetches earth, the piling action is carried out simultaneously with the action of fetching earth, until centrifugal pile tube, side's stake 11 are depressed into ground, in the case 5 that fetches earth, take out the soil that takes out by the drilling rod 12 that fetches earth then, stack to one side or the car outward transport; The unit head 3 and the drilling rod 12 that fetches earth are broken away from, the pulley 6 that drives unit head 3 upper ends by hoist engine 2 rotates, driving unit head 3 up moves, with crawler belt loop wheel machine the sling centrifugal pile tube of second joint, side stake 11, be installed with second in the centrifugal pile tube of second joint, the side's stake 11 and save the drilling rod 12 that fetches earth, save the drilling rod 12 that fetches earth with second and be connected on the unit head 3; The centrifugal pile tube of first segment, the centrifugal pile tube of side stake 11 and second joint, side 11 are connect by being weldingly connected; Weld full, the imporosity, the compliant requirement, passed examination, continuation is with the centrifugal pile tube of second joint, side's stake 11 drives pulley 8 that is connected on the main frame and the pulley 7 that is installed on the case 5 that fetches earth and rotates by hoist engine 2, driving pile cover 13 moves down, formed the piling action, driving the drilling rod 12 that fetches earth by unit head 3 simultaneously rotates, fetch earth by the drilling rod 12 that fetches earth, the piling action is carried out simultaneously with the action of fetching earth, until saving centrifugal pile tube with second, side's stake 11 is depressed into ground, in the case 5 that fetches earth, take out the soil that takes out by the drilling rod 12 that fetches earth then, stack to one side or the car outward transport; The centrifugal pile tube of the 3rd joint, the centrifugal pile tube of side's stake the 11 or the 4th joint, side's stake 11 can take above action to continue to implement.
It should be noted that at last: above embodiment only in order to the explanation the utility model and and the described technical scheme of unrestricted the utility model; Therefore, although this manual has been described in detail the utility model with reference to each above-mentioned embodiment,, those of ordinary skill in the art should be appreciated that still and can make amendment or be equal to replacement the utility model; And all do not break away from the technical scheme and the improvement thereof of the spirit and scope of utility model, and it all should be encompassed in the middle of the claim scope of the present utility model.

Claims (3)

1. the anti-daraf(reciprocal of farad) prestressed centrifugally of middle pick pile tube, square sunk pile device, comprise main frame, be installed in hoist engine, the unit head on the main frame, the case that fetches earth, pulley, wire rope, it is characterized in that: described unit head is installed on the main frame, described unit head upper end is equipped with pulley, described pulley is connected with wire rope, described wire rope is connected with hoist engine by the main frame top, and described unit head below is connected with the drilling rod that fetches earth.
2. the anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick, square sunk pile device in according to claim 1, it is characterized in that: described unit head lower end outer periphery is equipped with the screening soil suite, described screening soil suite lower end is connected with the case that fetches earth, the described case lower end of fetching earth is connected with pile cover, and the described both sides, case lower end of fetching earth are respectively arranged with pulley.
3. the anti-daraf(reciprocal of farad) prestressed centrifugally pile tube of pick, square sunk pile device in according to claim 2, it is characterized in that: on the described pulley wire rope is installed, described wire rope is connected with hoist engine by the pulley that is installed on the main frame, centrifugal pile tube, side stake are laid in described pile cover lower end, and the described drilling rod that fetches earth passes fetch earth case and centrifugal pile tube, side's stake and arrives bottom of device.The described unit head and the case that fetches earth can slide on main frame.
CN2011200554644U 2011-03-04 2011-03-04 Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile Expired - Lifetime CN202017208U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200554644U CN202017208U (en) 2011-03-04 2011-03-04 Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200554644U CN202017208U (en) 2011-03-04 2011-03-04 Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile

Publications (1)

Publication Number Publication Date
CN202017208U true CN202017208U (en) 2011-10-26

Family

ID=44810879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200554644U Expired - Lifetime CN202017208U (en) 2011-03-04 2011-03-04 Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile

Country Status (1)

Country Link
CN (1) CN202017208U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383428A (en) * 2011-02-23 2012-03-21 上海城地建设发展有限公司 Device and method for sinking pre-stressed centrifugal pipe pile (square pile) with in-pile boring and reverse drawing method
CN107165164A (en) * 2017-06-29 2017-09-15 盐城市中标工程装备制造有限公司 Pile tube sunk stake machine

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383428A (en) * 2011-02-23 2012-03-21 上海城地建设发展有限公司 Device and method for sinking pre-stressed centrifugal pipe pile (square pile) with in-pile boring and reverse drawing method
CN102383428B (en) * 2011-02-23 2015-12-09 上海城地建设股份有限公司 Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN107165164A (en) * 2017-06-29 2017-09-15 盐城市中标工程装备制造有限公司 Pile tube sunk stake machine

Similar Documents

Publication Publication Date Title
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN102776884B (en) In stir and rotate prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN102373705A (en) Pile sinking device and method for outer digging pre-stressed centrifugal pipe pile and square pile
CN106120789A (en) The interior pile sinking process boring vibration PHC tube pile of major diameter
CN102383428B (en) Middle pick reverse drawing method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN1488818A (en) Jacketed disc pile and piling method, extruding-expanding device, pile sinking machine and use
CN102373706B (en) Middle pick hydraulic method prestressed centrifugally pile tube pile-sinking device and pile-sinking method thereof
CN103572770B (en) A kind of stake case hydraulic structures and construction method thereof
CN203654309U (en) Pile-caisson hydraulic structure
CN202017208U (en) Center digging reverse drawing method pile driving device for pre-stress centrifuge pipe pile and square pile
CN208803479U (en) Pipe pile structure used as dewatering well
CN1182301C (en) Technology for boring and prefabricating cast piles for foundation of building
CN102953382A (en) Pile sinking device and pile sinking method for steel pipe pile by central stirring and reverse drawing
CN203007940U (en) Tubular pile protection structure in side slope hammering construction
CN106049413B (en) A kind of composite power drain consolidation system and construction method applied to deep layer foundation in saturated soft soil
CN1827924A (en) Foundation treatment method by static pressure replacement and multi-purpose press pipe thereof
CN205116168U (en) End grout static pressure tubular pile construction equipment is expanded in drilling
CN202039365U (en) Prestressed centrifugal square pipe pile sinking device using central digging hydraulic method
CN106930274A (en) The a full set of cylinder rotatory boring castinplace pile construction method that a kind of reinforcing bar cage location is fixed
CN111749231A (en) Double-sleeve double-drive full-rotation pile forming device and pile forming process
CN202202328U (en) Internal excavation pre-stress centrifugal pipe pile sinking host apparatus
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN202017207U (en) Middle-digging anchoring method prestress centrifugal pipe pile and square pile sinking device
CN201474602U (en) Prestressed pipe pile perforated pile-driving machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI CHENGDI CONSTRUCTION CO., LTD.

Free format text: FORMER OWNER: SHANGHAI CHENGDI CONSTRUCTION DEVELOPMENT CO., LTD.

Effective date: 20121127

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200000 JIADING, SHANGHAI TO: 201800 JIADING, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20121127

Address after: 201800 B, zone 502-1, Lane 518, Lane 1, Jiading District, Shanghai

Patentee after: Shanghai Chengdi Construction Co., Ltd.

Address before: 200000 room 1, building 188, 126 Nanan Road, Anting Town, Shanghai, Jiading District

Patentee before: Shanghai Chengdi Construction Development Co., Ltd.