CN202007383U - High-voltage insulating suspension basket - Google Patents

High-voltage insulating suspension basket Download PDF

Info

Publication number
CN202007383U
CN202007383U CN2011200163994U CN201120016399U CN202007383U CN 202007383 U CN202007383 U CN 202007383U CN 2011200163994 U CN2011200163994 U CN 2011200163994U CN 201120016399 U CN201120016399 U CN 201120016399U CN 202007383 U CN202007383 U CN 202007383U
Authority
CN
China
Prior art keywords
hanging basket
main couple
suspension basket
voltage insulation
insulated plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200163994U
Other languages
Chinese (zh)
Inventor
刘申华
周玉兵
肖红武
王树文
徐学磊
刘金明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 20th Bureau Group Corp
Original Assignee
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 20th Bureau Group Corp filed Critical China Railway 20th Bureau Group Corp
Priority to CN2011200163994U priority Critical patent/CN202007383U/en
Application granted granted Critical
Publication of CN202007383U publication Critical patent/CN202007383U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a high-voltage insulating suspension basket, relating to the technical field of security protection of the suspension basket for railway cast-in-situ beams. A front crossbeam is connected with the front side of a triangular main truss through a front suspending strip; a rear crossbeam is connected to the bottom end inside the suspension basket through a rear suspending strip; the upper end inside the suspension basket is provided with a sliding beam; the upper end in the front part of the suspension basket is connected with the triangular main truss through a transverse connecting system; the two sides of the transverse connecting system are connected with a shockproof board through front suspension bars; the two ends in the front side of the triangular main truss are connected to the two sides of the shockproof board at the bottom of the suspension basket through the wire ropes for hoisting templates; and the two sides of the suspension basket are provided with outer mold truss systems. Due to the high-voltage insulating suspension basket, the time for locking existing lines can be reduced, the building cost of projects is lowered, the security risks caused by assembling/disassembling shelves are avoided, the construction period is shortened, and therefore reference for continuous beam construction of the existing lines with long spans or being inconvenient to set up the shelves can be provided.

Description

The High-Voltage Insulation Hanging Basket
Technical field:
The utility model relates to railway cast-in-place beam Hanging Basket safety protection technique field, is specifically related to a kind of High-Voltage Insulation Hanging Basket.
Background technology:
The civil official collect the construction of the continuous girder span existing line of bridge 60+100+60m no matter be from the angle that intersects with existing line, stride existing line length, all be domestic rare apart from the height of existing line, the existing Beijing-Harbin railway of being striden simultaneously also is one of the busiest domestic main line, and its difficulty and security risk are well imagined.Because of the continuous upper and lower line of the existing Beijing-Harbin railway of girder span, have only 18 with the existing Beijing-Harbin railway angle of cut., causing case beam 100 main spans and the existing line distance that crosses, length reaches 91m, just enters existing line circuit top since No. 2 BOB(beginning of block) Hanging Baskets, and distance closely has only 0.9m between Hanging Basket base cross members and the existing line contact netting twine.Simultaneously, existing Beijing-Harbin line belongs to national heavy traffic main line, the current train of upper and lower line every day has more than 130 row, just had in average 11 minutes rows of cars travel by, therefore how to guarantee the existing line traffic safety in the work progress, prevent that effectively the contact net high-tension electricity from working the mischief to the constructor, prevent that the high-altitude junk from becoming emphasis and difficult point in the construction:
1, the Hanging Basket cantilever pouring stride in the existing line process may the high-altitude junk driving works the mischief to existing line.
2, the space is little between newly-built bridge bottom surface and the existing line, and it is little or the space not enough, can't set up frame to set up the space of frame.
3, Hanging Basket existing line contact net high-tension electricity may produce personal injury to operating personnel on the Hanging Basket.
4, need do follow-up engineerings such as removing frame, prolongation will be put blocking time and construction period.
5, operating expenses is far longer than the expense that the frame construction produces, and has increased construction costs and construction cost.
The utility model content:
The purpose of this utility model provides a kind of High-Voltage Insulation Hanging Basket, it solves the deficiency in the background technology, its bottom adopts all-insulated plate to wrap sealing entirely, effectively carries out the anti-electric measure of waterproof and has guaranteed existing line traffic safety and construction safety, and existing line is driven a vehicle without any influence.The totally enclosed characteristics of Hanging Basket are the blocking times that can reduce existing line simultaneously, reduce construction costs, avoid the security risk brought because of the assembling and disassembling frame, shortened the construction period, existing line is long, headroom is little for striding, be not easy to set up striding the existing line Construction of continuous beam reference being provided of frame.
In order to solve the existing problem of background technology, the utility model is by the following technical solutions: it comprises preceding suspender belt, all-insulated plate, rear cross beam, front beam, longeron, the iron wire protective screening, insulating slab, back strap, anti-electric alarm device, the triangle main couple, back anchor system, running gear and truss anchor system, lightning rod, sliding beam, horizontal connected system, lifting template wire rope, preceding suspension rod and external mold trussing, the triangle main couple that has an anti-electric alarm device is fixed on the upper end of Hanging Basket by back anchor system and running gear and truss anchor system, and triangle main couple top is provided with lightning rod; Longeron is arranged on Hanging Basket bottom, and the rear and front end of longeron is connected with front beam and rear cross beam respectively, and the lower end of rear cross beam, front beam, longeron is provided with all-insulated plate, and the all-insulated plate front side is provided with insulating slab, is connected with protective screening on the insulating slab; Front beam is connected with triangle main couple front side by preceding suspender belt, and rear cross beam is connected to the Hanging Basket inner bottom by back strap, and the Hanging Basket inner upper end is provided with sliding beam; The Hanging Basket nock is connected with the triangle main couple by horizontal connected system, laterally the connected system both sides are connected with all-insulated plate by preceding suspension rod, two ends, triangle main couple front side are connected to all-insulated plate both sides, Hanging Basket bottom by lifting template wire rope, and the Hanging Basket both sides are provided with the external mold trussing.
Described triangle main couple, horizontal connected system constitute forms main couple, is the main force structure of Hanging Basket, bears bottom die platform and concrete deadweight and working load.
Described rear cross beam, front beam, longeron constitute bottom die platform, be mainly used in and directly bear weight concrete, and shuttering, reinforcing bar binding, concreting provide the work-yard, still be the primary structure of fixedly connected discharge system simultaneously, be connected on the main couple by suspension system in the installation process.
Described inner and outer template and truss constitute template system.
Suspender belt, back strap, lifting template wire rope, preceding suspension rod are formed suspension system before described, and suspension system top is connected on the main couple, and the lower part connects bottom die platform, external mold and internal mold.
Described running gear and truss anchor system are located on the main couple posterior nodal point, comprise anchor pole shoulder pole girder and 2 vertical smart indented barss of pricking behind the anchor pole behind 2 shoulder pole girders, 4,2.The overturning moment that its effect produces when being the balance concreting is guaranteed Hanging Basket safety.Running gear comprises bolster, track, preceding bearing, rear support and pulling equipment.
Described all-insulated plate, insulating slab, anti-electric prior-warning device constitutes electricity prevention system.Mainly be fixed on above the bottom die platform, be used to isolate the high-tension electricity that electrified circuit produces.Anti-electric prior-warning device is used for the monitoring of Hanging Basket safe voltage, electric current, guarantees not take place electric shock accidents.
Described all-insulated plate is made up of steel plate, insulating slab two parts, and steel plate is set to the U type at rear cross beam, front beam place, is close to welding with forward and backward crossbeam; The insulating slab reverse side carries out waterproof sealing to be handled, and prevents to leak and influence insulation.Before the construction insulating slab, weld together with 3mm thick steel plate and crossbeam, longeron in the Hanging Basket bottom earlier, then brushing and stickup insulating slab on steel plate.
The utility model solves the deficiency in the background technology, and its bottom adopts all-insulated plate to wrap sealing entirely, effectively carries out the anti-electric measure of waterproof and has guaranteed existing line traffic safety and construction safety, and existing line is driven a vehicle without any influence.The totally enclosed characteristics of Hanging Basket are the blocking times that can reduce existing line simultaneously, reduce construction costs, avoid the security risk brought because of the assembling and disassembling frame, shortened the construction period, existing line is long, headroom is little for striding, be not easy to set up striding the existing line Construction of continuous beam reference being provided of frame.
Description of drawings:
Fig. 1 is a facade structures schematic diagram of the present utility model,
Fig. 2 is a Facad structure schematic diagram of the present utility model,
Fig. 3 is the structural representation of all-insulated plate in the utility model.
The specific embodiment:
With reference to Fig. 1-3, this specific embodiment is by the following technical solutions: it comprises preceding suspender belt 1, all-insulated plate 2, rear cross beam 3, front beam 4, longeron 5, iron wire protective screening 6, insulating slab 7, back strap 8, anti-electric alarm device 9, triangle main couple 10, back anchor system 11, running gear and truss anchor system 12, lightning rod 13, sliding beam 14, horizontal connected system 15, lifting template wire rope 16, preceding suspension rod 17 and external mold trussing 18, the triangle main couple 10 that has an anti-electric alarm device 9 is fixed on the upper end of Hanging Basket by back anchor system 11 and running gear and truss anchor system 12, and triangle main couple 10 tops are provided with lightning rod 13; Longeron 5 is arranged on Hanging Basket bottom, and the rear and front end of longeron 5 is connected with front beam 4 and rear cross beam 3 respectively, and the lower end of rear cross beam 3, front beam 4, longeron 5 is provided with all-insulated plate 2, and all-insulated plate 2 front sides are provided with insulating slab 7, are connected with protective screening 6 on the insulating slab 7; Front beam 4 is connected with triangle main couple 10 front sides by preceding suspender belt 1, and rear cross beam 3 is connected to the Hanging Basket inner bottom by back strap 8, and the Hanging Basket inner upper end is provided with sliding beam 14; The Hanging Basket nock is connected with triangle main couple 10 by horizontal connected system 15, laterally connected system 15 both sides are connected with all-insulated plate 2 by preceding suspension rod 17, two ends, triangle main couple 10 front side are connected to all-insulated plate 2 both sides, Hanging Basket bottom by lifting template wire rope 16, and the Hanging Basket both sides are provided with external mold trussing 18.
Described triangle main couple 10, horizontal connected system constitute 15 and form main couples, are the main force structures of Hanging Basket, bear bottom die platform and concrete deadweight and working load.
Described rear cross beam 3, front beam 4, longeron 5 constitute bottom die platform, be mainly used in and directly bear weight concrete, and shuttering, reinforcing bar binding, concreting provide the work-yard, still be the primary structure of fixedly connected discharge system simultaneously, be connected on the main couple by suspension system in the installation process.
Described inner and outer template and truss constitute template system.
Suspender belt 1, back strap 8, lifting template wire rope 16, preceding suspension rod 17 are formed suspension system before described, and suspension system top is connected on the main couple, and the lower part connects bottom die platform, external mold and internal mold.
Described running gear and truss anchor system 12 are located on the main couple posterior nodal point, comprise anchor pole shoulder pole girder and 2 vertical smart indented barss of pricking behind the anchor pole behind 2 shoulder pole girders, 4,2.The overturning moment that its effect produces when being the balance concreting is guaranteed Hanging Basket safety.Running gear comprises bolster, track, preceding bearing, rear support and pulling equipment.
Described all-insulated plate 2, insulating slab 7, anti-electric prior-warning device 9 constitutes electricity prevention system.Mainly be fixed on above the bottom die platform, be used to isolate the high-tension electricity that electrified circuit produces.Anti-electric prior-warning device 9 is used for the monitoring of Hanging Basket safe voltage, electric current, guarantees not take place electric shock accidents.
Described all-insulated plate 2 is made up of steel plate, insulating slab two parts, and steel plate is set to the U type at rear cross beam 3, front beam 4 places, is close to welding with forward and backward crossbeam; The insulating slab reverse side carries out waterproof sealing to be handled, and prevents to leak and influence insulation.Before the construction insulating slab, weld together with 3mm thick steel plate and crossbeam, longeron in the Hanging Basket bottom earlier, then brushing and stickup insulating slab on steel plate.
This specific embodiment solves the deficiency in the background technology, and its bottom adopts all-insulated plate to wrap sealing entirely, effectively carries out the anti-electric measure of waterproof and has guaranteed existing line traffic safety and construction safety, and existing line is driven a vehicle without any influence.The totally enclosed characteristics of Hanging Basket are the blocking times that can reduce existing line simultaneously, reduce construction costs, avoid the security risk brought because of the assembling and disassembling frame, shortened the construction period, existing line is long, headroom is little for striding, be not easy to set up striding the existing line Construction of continuous beam reference being provided of frame.

Claims (8)

1. High-Voltage Insulation Hanging Basket, it is characterized in that it comprises preceding suspender belt (1), all-insulated plate (2), rear cross beam (3), front beam (4), longeron (5), iron wire protective screening (6), insulating slab (7), back strap (8), anti-electric alarm device (9), triangle main couple (10), back anchor system (11), running gear and truss anchor system (12), lightning rod (13), sliding beam (14), horizontal connected system (15), lifting template wire rope (16), preceding suspension rod (17) and external mold trussing (18), the triangle main couple (10) that has an anti-electric alarm device (9) is fixed on the upper end of Hanging Basket by afterwards anchor system (11) and running gear and truss anchor system (12), and triangle main couple (10) top is provided with lightning rod (13); Longeron (5) is arranged on the Hanging Basket bottom, and the rear and front end of longeron (5) is connected with front beam (4) and rear cross beam (3) respectively, the lower end of rear cross beam (3), front beam (4), longeron (5) is provided with all-insulated plate (2), all-insulated plate (2) front side is provided with insulating slab (7), is connected with protective screening (6) on the insulating slab (7); Front beam (4) is connected with triangle main couple (10) front side by preceding suspender belt (1), and rear cross beam (3) is connected to the Hanging Basket inner bottom by back strap (8), and the Hanging Basket inner upper end is provided with sliding beam (14); The Hanging Basket nock is connected with triangle main couple (10) by horizontal connected system (15), laterally connected system (15) both sides are connected with all-insulated plate (2) by preceding suspension rod (17), triangle main couple (10) two ends, front side are connected to all-insulated plate (2) both sides, Hanging Basket bottom by lifting template wire rope (16), and the Hanging Basket both sides are provided with external mold trussing (18).
2. High-Voltage Insulation Hanging Basket according to claim 1 is characterized in that described triangle main couple (10), horizontal connected system constitute (15) and form main couple.
3. High-Voltage Insulation Hanging Basket according to claim 1 is characterized in that described rear cross beam (3), front beam (4), longeron (5) constitute bottom die platform.
4. High-Voltage Insulation Hanging Basket according to claim 1 is characterized in that described inner and outer template and truss constitute template system.
5. High-Voltage Insulation Hanging Basket according to claim 1, it is characterized in that described preceding suspender belt (1), back strap (8), lifting template wire rope (16), preceding suspension rod (17) composition suspension system, suspension system top is connected on the main couple, and the lower part connects bottom die platform, external mold and internal mold.
6. High-Voltage Insulation Hanging Basket according to claim 1, it is characterized in that described running gear and truss anchor system (12) are located on the main couple posterior nodal point, comprise anchor pole shoulder pole girder and 2 vertical smart indented barss of pricking behind the anchor pole behind 2 shoulder pole girders, 4,2.
7. High-Voltage Insulation Hanging Basket according to claim 1 is characterized in that described all-insulated plate (2), insulating slab (7), and anti-electric prior-warning device (9) constitutes electricity prevention system.
8. High-Voltage Insulation Hanging Basket according to claim 1 is characterized in that described all-insulated plate (2) is made up of steel plate, insulating slab two parts, and steel plate locates to be set to the U type at rear cross beam (3), front beam (4), is close to welding with forward and backward crossbeam; The insulating slab reverse side carries out waterproof sealing to be handled.
CN2011200163994U 2011-01-19 2011-01-19 High-voltage insulating suspension basket Expired - Lifetime CN202007383U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200163994U CN202007383U (en) 2011-01-19 2011-01-19 High-voltage insulating suspension basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200163994U CN202007383U (en) 2011-01-19 2011-01-19 High-voltage insulating suspension basket

Publications (1)

Publication Number Publication Date
CN202007383U true CN202007383U (en) 2011-10-12

Family

ID=44749038

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200163994U Expired - Lifetime CN202007383U (en) 2011-01-19 2011-01-19 High-voltage insulating suspension basket

Country Status (1)

Country Link
CN (1) CN202007383U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561193A (en) * 2011-12-23 2012-07-11 中铁四局集团第五工程有限公司 Construction technology of closure section for rotary continuous beam for overpass electrified railway and hanging basket thereof
CN103147411A (en) * 2013-03-30 2013-06-12 师长宏 Insulation covering hanging groove
CN104294767A (en) * 2014-10-30 2015-01-21 中国水利水电第五工程局有限公司 Lengthening hanging basket used for cantilever beam cast-in-place construction and construction method of lengthening hanging basket
CN106958345A (en) * 2017-05-16 2017-07-18 简华炽 A kind of adjustable rigid Hanging Basket
CN107761574A (en) * 2017-09-29 2018-03-06 中铁九局集团有限公司 A kind of across electric railway Business Line swivel flute profile continuous beam mid-span closing device
CN109629451A (en) * 2019-01-30 2019-04-16 中铁七局集团郑州工程有限公司 Across the multiply closed hanging basket cantilever method construction of road electric railway continuous bridge
CN110144832A (en) * 2019-05-22 2019-08-20 刘志广 A kind of adhesion type fully-enclosed safe protection canopy for high-flying highway cradle construction
CN113417219A (en) * 2021-05-31 2021-09-21 中铁十二局集团有限公司 Hydraulic internal mold asynchronous traveling system and method for bridge suspension casting basket box chamber

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561193A (en) * 2011-12-23 2012-07-11 中铁四局集团第五工程有限公司 Construction technology of closure section for rotary continuous beam for overpass electrified railway and hanging basket thereof
CN103147411A (en) * 2013-03-30 2013-06-12 师长宏 Insulation covering hanging groove
CN104294767A (en) * 2014-10-30 2015-01-21 中国水利水电第五工程局有限公司 Lengthening hanging basket used for cantilever beam cast-in-place construction and construction method of lengthening hanging basket
CN104294767B (en) * 2014-10-30 2016-04-06 中国水利水电第五工程局有限公司 A kind of semi girder cast-in-place construction spreading Hanging Basket and construction method thereof
CN106958345A (en) * 2017-05-16 2017-07-18 简华炽 A kind of adjustable rigid Hanging Basket
CN106958345B (en) * 2017-05-16 2022-08-02 简华炽 Adjustable rigid hanging basket
CN107761574A (en) * 2017-09-29 2018-03-06 中铁九局集团有限公司 A kind of across electric railway Business Line swivel flute profile continuous beam mid-span closing device
CN107761574B (en) * 2017-09-29 2021-02-12 中铁九局集团有限公司 Midspan folding device for swivel groove-shaped continuous beam of service line of electrified railway
CN109629451A (en) * 2019-01-30 2019-04-16 中铁七局集团郑州工程有限公司 Across the multiply closed hanging basket cantilever method construction of road electric railway continuous bridge
CN110144832A (en) * 2019-05-22 2019-08-20 刘志广 A kind of adhesion type fully-enclosed safe protection canopy for high-flying highway cradle construction
CN113417219A (en) * 2021-05-31 2021-09-21 中铁十二局集团有限公司 Hydraulic internal mold asynchronous traveling system and method for bridge suspension casting basket box chamber

Similar Documents

Publication Publication Date Title
CN202007383U (en) High-voltage insulating suspension basket
CN201221206Y (en) Movable anti-electricity protection shed rack
CN202936736U (en) Cable-stayed bridge composite beam construction bridge floor crane
CN107165062B (en) A method of removing Existing Railway Line gate-type pier capping beam protecting canopy frame
CN105239510A (en) Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN202247713U (en) Combined protective shed frame
CN103288002B (en) Simple combination door frame high-altitude weight hanging apparatus
CN208346656U (en) A kind of hanging basket for the construction of bridge coping prestress wire two times tensioning
CN102425123B (en) Combined type protection shed frame and construction method thereof
CN215210544U (en) Bridge curtain board construction protection device for existing tramcar crossing highway
CN208167536U (en) A kind of operation platform removed for bridge temporary support
CN203284126U (en) Simple composite gantry high-altitude weight hoisting device
CN212505875U (en) Pier top back pressure structure of No. 0 block triangular bracket of rigid frame bridge
CN106044580B (en) A kind of wet electrical dust precipitator body equipment integral hoisting method
CN206279438U (en) A kind of short tower steel truss girder cable-stayed bridge of steel
CN205295965U (en) Large -span continuous beam bridge strides existing station rotation construction and wraps protective structure entirely with hanging basket
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN109629451A (en) Across the multiply closed hanging basket cantilever method construction of road electric railway continuous bridge
CN202039299U (en) Totally-closed hanging basket
WO2019047300A1 (en) Attachment type protection roof extending across highway for continuous girder
CN204728225U (en) A kind of rail rail traffic bridge of embracing evacuates inspection platform
CN211341685U (en) Climbing frame convenient to build
CN212404859U (en) Auxiliary device for falling of bottom die of bent cap
CN107419670A (en) Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY 20TH BUREAU GROUP CO., LTD.

Effective date: 20130712

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130712

Address after: 266000 No. 89 Donghai East Road, Laoshan District, Shandong, Qingdao

Patentee after: China Railway 20 Bureau Group Co., Ltd.

Patentee after: China Railway 20th Bureau Group Co., Ltd.

Address before: 266000 No. 89 Donghai East Road, Laoshan District, Shandong, Qingdao

Patentee before: China Railway 20 Bureau Group Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20111012

CX01 Expiry of patent term