CN201891171U - Integral bolt assembling frame - Google Patents
Integral bolt assembling frame Download PDFInfo
- Publication number
- CN201891171U CN201891171U CN2010205866648U CN201020586664U CN201891171U CN 201891171 U CN201891171 U CN 201891171U CN 2010205866648 U CN2010205866648 U CN 2010205866648U CN 201020586664 U CN201020586664 U CN 201020586664U CN 201891171 U CN201891171 U CN 201891171U
- Authority
- CN
- China
- Prior art keywords
- bolt
- control template
- frame
- assembling frame
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to an integral bolt assembling frame, comprising a bottom part reinforcing bar support, an upper part control template and a top part reinforcing control template; the integral bolt assembling frame is characterized in that the bottom part reinforcing bar support is a frame structure welded by reinforcing bars and provided with a horizontal supporting frame at the top part, and bolt accurate positioning holes are arranged on the upper part control template and the top part reinforcing control template. The integral bolt assembling frame has the advantages that an embedded bolt is machined simply, the construction is operated easily, the embedded size of the bolt can be accurately controlled and located, and the construction efficiency and the construction quality are improved.
Description
Technical field
The utility model relates to a kind of bolt overall package frame, belongs to that in the steel work suspension column concrete basis preburied positioning device field of pre-embedded bolt in industry and the civilian construction factory building.
Background technology
In the pre-embedded bolt work progress, all be in template, to weld separately with reinforcing bar.Pre-buried size to bolt is difficult to accurate control, and the installation quality of the steel column in later stage is caused certain influence.
Summary of the invention
The purpose of this utility model provides the bolt overall package frame that a kind of pre-buried size to bolt can accurately be controlled the location.
The purpose of this utility model realizes in the following manner:
The utility model comprises bottom reinforcement bars support, top control template, roof reinforcement control template, it is characterized in that: the bottom reinforcement bars support is that a top that is welded by reinforcing bar is the frame construction of horizontal support frame, has the accurate locating hole of bolt on top control template and roof reinforcement control template.
The utility model has the advantages that: make the processing summary of pre-embedded bolt, easy to operateization of constructing can accurately be controlled the location to the pre-buried size of bolt, improved efficiency of construction and construction quality.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
The specific embodiment
With reference to accompanying drawing, comprise bottom reinforcement bars support 6, top control template 4, roof reinforcement control template 3, bottom reinforcement bars support 6 is that a top that is welded by reinforcing bar is the frame construction of horizontal support frame, has the accurate locating hole of bolt on top control template 4 and roof reinforcement control template 3.
When the utility model uses, on top control template 4, leave the accurate locating hole of bolt, pre-embedded bolt 1 usefulness nut 2 is fixed in the accurate locating hole of each bolt according to the position of pre-embedded bolt; To fix top control template 4 integrated stand of bolt on bottom reinforcement bars support 6; With the head of locating hole and each pre-embedded bolt 1 of roof reinforcement control template 3 that has the accurate locating hole of bolt corresponding one by one after, be fixed on the top of each pre-embedded bolt 1, like this, each bolt all has two point locations, and bolt can not be swung.Help to weld the good bolt of frame 1 with indented bars 5, make the fixed-site of all bolts become as a whole.Remove top twice fixed form 3 and 4 at last.To help bolt welded together 1 integral body to lay into concrete form then.
Claims (1)
1. bolt overall package frame, comprise bottom reinforcement bars support, top control template, roof reinforcement control template, it is characterized in that: the bottom reinforcement bars support is that a top that is welded by reinforcing bar is the frame construction of horizontal support frame, has the accurate locating hole of bolt on top control template and roof reinforcement control template.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205866648U CN201891171U (en) | 2010-11-02 | 2010-11-02 | Integral bolt assembling frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205866648U CN201891171U (en) | 2010-11-02 | 2010-11-02 | Integral bolt assembling frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201891171U true CN201891171U (en) | 2011-07-06 |
Family
ID=44220649
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010205866648U Expired - Lifetime CN201891171U (en) | 2010-11-02 | 2010-11-02 | Integral bolt assembling frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201891171U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493668A (en) * | 2011-12-15 | 2012-06-13 | 中国建筑第八工程局有限公司 | Locating mould and method for pre-embedding position embedding parts in ultrahigh precision |
CN102505705A (en) * | 2011-10-26 | 2012-06-20 | 铜陵有色建安钢构有限责任公司 | Method for pre-embedding bolts by using positioning steel plates |
CN102644379A (en) * | 2012-04-28 | 2012-08-22 | 中建一局集团建设发展有限公司 | Temporary supporting system of steel column base and construction method of temporary supporting system |
CN105544588A (en) * | 2015-12-15 | 2016-05-04 | 安徽伟宏钢结构集团股份有限公司 | Mounting process of steel structure pre-buried bolt |
CN106968180A (en) * | 2017-04-20 | 2017-07-21 | 崔冰 | A kind of dry type connection method of the concrete slab and girder steel of steel reinforced concrete combination beam |
-
2010
- 2010-11-02 CN CN2010205866648U patent/CN201891171U/en not_active Expired - Lifetime
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102505705A (en) * | 2011-10-26 | 2012-06-20 | 铜陵有色建安钢构有限责任公司 | Method for pre-embedding bolts by using positioning steel plates |
CN102493668A (en) * | 2011-12-15 | 2012-06-13 | 中国建筑第八工程局有限公司 | Locating mould and method for pre-embedding position embedding parts in ultrahigh precision |
CN102644379A (en) * | 2012-04-28 | 2012-08-22 | 中建一局集团建设发展有限公司 | Temporary supporting system of steel column base and construction method of temporary supporting system |
CN105544588A (en) * | 2015-12-15 | 2016-05-04 | 安徽伟宏钢结构集团股份有限公司 | Mounting process of steel structure pre-buried bolt |
CN106968180A (en) * | 2017-04-20 | 2017-07-21 | 崔冰 | A kind of dry type connection method of the concrete slab and girder steel of steel reinforced concrete combination beam |
CN106968180B (en) * | 2017-04-20 | 2019-03-22 | 崔冰 | A kind of dry type connection method of the concrete slab and girder steel of the mixed combination beam of steel- |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203640309U (en) | Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame | |
CN201891171U (en) | Integral bolt assembling frame | |
CN203891058U (en) | Built-in foundation bolt positioning tool for fixed type tower crane foundation | |
CN202214735U (en) | Pedestal anchor bolt positioning tool for shallow foundation | |
CN202517214U (en) | Upper car platform welding fixture | |
CN201474303U (en) | Beam column template clip | |
CN202090291U (en) | Tensioning support | |
CN102704696B (en) | Space locator for high, big and heavy steel upright column | |
CN203684703U (en) | Assembly jig frame for main truss spare parts of large-span steel structure roof cover | |
CN205011183U (en) | Debris elevator frame construction of improvement | |
CN105715055B (en) | A kind of nuclear power station large size penetration piece adjustable tool and adjusting method | |
CN204035432U (en) | A kind of Figure of eight grid steel frame processing mold | |
CN205046843U (en) | Reinforcing apparatus's stair template of marking time in middle of installation | |
CN202410262U (en) | Portable quickly combined rake of large-scale center transmission thickener | |
CN202000681U (en) | Three-dimensional die bracket for concrete embedded parts | |
CN202299429U (en) | Circulation adjustable angle iron stiffening system | |
CN204826636U (en) | Simple beam ear picking and shaping support | |
CN204954379U (en) | Welding formula numerical control machine bed base | |
CN203200666U (en) | Thin-walled concrete plate girder suspension load carrier | |
CN204022286U (en) | Transfer crane is without corbel type door frame | |
CN202324369U (en) | Steel bar positioning clamp for casting plane concrete | |
CN203742200U (en) | Detachable jacking and supporting device | |
CN204510481U (en) | Shaped steel junction plate vertical in steel building | |
CN202416340U (en) | Mounting structure of support for large-diameter air duct | |
CN203514522U (en) | Stand column and floor slab connecting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20110706 |