CN201746133U - 盾构皮带输送机分流器 - Google Patents

盾构皮带输送机分流器 Download PDF

Info

Publication number
CN201746133U
CN201746133U CN 201020505813 CN201020505813U CN201746133U CN 201746133 U CN201746133 U CN 201746133U CN 201020505813 CN201020505813 CN 201020505813 CN 201020505813 U CN201020505813 U CN 201020505813U CN 201746133 U CN201746133 U CN 201746133U
Authority
CN
China
Prior art keywords
shunt
belt conveyor
crossbeam
shielded
band conveyor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201020505813
Other languages
English (en)
Inventor
贺飞
张宁川
方新强
王伟
陈贝贝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Original Assignee
China Railway Tunneling Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunneling Equipment Co Ltd filed Critical China Railway Tunneling Equipment Co Ltd
Priority to CN 201020505813 priority Critical patent/CN201746133U/zh
Application granted granted Critical
Publication of CN201746133U publication Critical patent/CN201746133U/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本实用新型涉及一种盾构机皮带输送机出料分流器,主要在盾构皮带机头部出料口下端处,设置一个分流器,使列车编组中的渣车牵引位置通过皮带机出料口下端时,也能使渣车连续接料;主要由分流抖、轨道、汽缸等组成。通过汽缸推动分料抖的位置变化达到分流的目的,具有体积小,结构简单,维修方便等优点,可广泛运用于隧道施工盾构、TBM及其它行业的皮带输送机机分流,使生产连续作业,提高工作效率。

Description

盾构皮带输送机分流器 
技术领域
本实用新型涉及一种皮带输送机分流器,具体涉及隧道地下施工的盾构皮带输送机分流器。 
背景技术
目前,在隧道施工过程中,盾构进行隧道开挖时,开挖出的物料通过用皮带输送机转运物料到列车编组的渣车中,渣车再转运到洞外,这样形成连续作业。可是由于列车编组的渣车与渣车是通过牵引连接,牵引连接给渣车与渣车之间形成一个大的间隙,这样当一节渣车物料满载,换另一节渣车接料时,由于皮带输送机连续作业,过程中就会使物料落在渣车牵引的间隙处,使工作产生二次作业,同时也污染隧道壁,给施工带来极为不变。 
如何能够让物流不落到渣车的间隙处,让施工连续作业,提高工作效率,避免二次作业带来的耗时耗力,已是一个急需解决的问题。 
发明内容
为了克服上述现有技术中的不足,使物料通过分流器分流,不落在渣车之间的间隙处,让施工能够连续作业,提高工作效率,本实用提新型供了一种结构简单、操作方便,分流效率高的装置,即盾构皮带输送机分流器。 
本实用新型的目的是这样实现的: 
盾构皮带输送机分流器,包括分流抖6和轨道7及气缸4,在分流抖6下端两侧安装有轨道7,轨道7的前端固定在支撑皮带输送机前端的支撑横梁8上,后端固定在支撑5上,支撑5与皮带输送机的后端横梁连接;汽缸4前端与分流抖6的中心线后端处连接,汽缸4后端与滑动梁3连接,滑动梁3与支撑梁2及横梁1连接,横梁1固定在皮带输送机下部的底板上。 
分流斗6由侧板6-1、底板6-2、挡板支撑6-3、滑块6-4和6-5支撑梁组成,其中挡板支撑6-3两端焊接在两边的侧板6-1上,同时底板6-2两边也焊接在侧板6-1上,底板6-2另一端焊接在6-3挡板支撑上,滑块6-4焊接在侧板6-1外侧。 
积极有益效果:本实用新型使皮带输送机输送的物料通过分流器分流,在运渣车进行交接的时候,不落在渣车之间的间隙处,让施工能够连续作业,提高工作效率;本实用提新型结构简单、操作简便,分流效率高、维修方便,可广泛运用于隧道施工盾构、TBM及其它行业的皮带输送机机分流,使生产连续作业,提高工作效率。 
附图说明
附图1为本实用新型的结构示意图; 
附图2为本实用新型结构图中的A-A剖视图; 
附图3为本实用新型中分流抖的结构示意图; 
图中为:横梁1、支撑梁2、滑动梁3、汽缸4、支撑5、分流抖6、轨道)、支撑横梁8、侧板6-1、底板6-2、挡板支撑6-3、滑块6-4、支撑梁6-5。 
具体实施方式
下面结合附图,对本实用新型作进一步的说明 
如图1、图2、图3所示,本实用新型主要是在隧道盾构施工中,在盾构皮带机头部出料口下部设置分流器,让列车编组中渣车牵引间隙处通过皮带机出料口下端时,能够连续接料,不使物料落在隧道壁上,形成二次作业。 
盾构皮带输送机分流器,包括分流斗6和分流斗轨道7及气缸4,分流斗6的中心线后端处安装有一个汽缸4、其下端安装两侧安装滑道7,并 借助于盾构机的气体动力源装置来使汽缸推动分流斗运动,并安装手动换向阀,来控制方向,手动换向阀安装在拖车左侧立柱或容易控制的位置,手动换向阀通过管路与气缸4和动力源连接;轨道梁7的前端固定在支撑皮带输送机前端的横梁8上,后端固定在支撑5上,横梁8两端固定在盾构机拖车的横梁上;支撑5与皮带输送机的后端横梁连接;汽缸4前端与分流斗6连接,另一端与滑动梁3连接,滑动梁3与支撑梁2及横梁1连接,横梁1固定在皮带输送机下部的底板上。这样使整个分流装置跟皮带机输送机形成一体,当皮带输送机出现滑动现象时,分流器也同时滑动,使工作连续进行。 
分流斗6由侧板6-1、底板6-2、挡板支撑6-3、滑块6-4和6-5支撑梁组成,其中挡板支撑6-3两端焊接在两边的侧板6-1上,同时底板6-2两边也焊接在侧板6-1上,底板6-2另一端焊接在6-3挡板支撑上,滑块6-4焊接在侧板6-1外侧。这样就形成一个能分流的盒体。 
本实用新型使皮带输送机输送的物料通过分流器分流,在运渣车进行交接的时候,不落在渣车之间的间隙处,让施工能够连续作业,提高工作效率;本实用提新型结构简单、操作简便,分流效率高、维修方便,可广泛运用于隧道施工盾构、TBM及其它行业的皮带输送机机分流,使生产连续作业,提高工作效率。 
以上实施例仅用于说明本发明的优选实施方式,但本发明并不限于上述实施方式,在所述领域普通技术人员所具备的知识范围内,本发明的精神和原则之内所作的任何修改、等同替代和改进等,其均应涵盖在本发明请求保护的技术方案范围之内。 

Claims (2)

1.盾构皮带输送机分流器,包括分流斗(6)和分流斗轨道(7)及气缸(4),其特征在于:分流斗(6)的中心线后端处安装有一个汽缸(4)、其下端安装两侧安装滑道(7),手动换向阀安装在拖车左侧立柱或容易控制的位置,手动换向阀通过管路与气缸(4)和动力源连接;轨道梁(7)的前端固定在支撑皮带输送机前端的横梁(8)上,后端固定在支撑(5)上,横梁(8)两端固定在盾构机拖车的横梁上;支撑(5)与皮带输送机的后端横梁连接;汽缸(4)前端与分流斗(6)连接,另一端与滑动梁(3)连接,滑动梁(3)与支撑梁(2)及横梁(1)连接,横梁(1)固定在皮带输送机下部的底板上。
2.根据权利要求1所述的盾构皮带输送机分流器,其特征在于:所述的分流斗(6)由侧板(6-1)、底板(6-2)、挡板支撑(6-3)、滑块(6-4)和(6-5)支撑梁组成,其中挡板支撑(6-3)两端焊接在两边的侧板(6-1)上,同时底板(6-2)两边也焊接在侧板(6-1)上,底板(6-2)另一端焊接在(6-3)挡板支撑上,滑块(6-4)焊接在侧板(6-1)外侧。
CN 201020505813 2010-08-26 2010-08-26 盾构皮带输送机分流器 Expired - Lifetime CN201746133U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201020505813 CN201746133U (zh) 2010-08-26 2010-08-26 盾构皮带输送机分流器

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201020505813 CN201746133U (zh) 2010-08-26 2010-08-26 盾构皮带输送机分流器

Publications (1)

Publication Number Publication Date
CN201746133U true CN201746133U (zh) 2011-02-16

Family

ID=43580810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201020505813 Expired - Lifetime CN201746133U (zh) 2010-08-26 2010-08-26 盾构皮带输送机分流器

Country Status (1)

Country Link
CN (1) CN201746133U (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761807A (zh) * 2016-11-25 2017-05-31 中铁上海工程局集团有限公司 一种盾构机连续自动出土方法
CN107697655A (zh) * 2017-11-09 2018-02-16 安庆巨元高分子材料科技有限公司 一种固态聚酰胺树脂输送装置
CN108045977A (zh) * 2017-11-30 2018-05-18 无锡锡东能源科技有限公司 一种料仓匀料装置
CN112960422A (zh) * 2021-02-20 2021-06-15 中国建材国际工程集团有限公司 一种硅砂侧卸接料装置

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761807A (zh) * 2016-11-25 2017-05-31 中铁上海工程局集团有限公司 一种盾构机连续自动出土方法
CN107697655A (zh) * 2017-11-09 2018-02-16 安庆巨元高分子材料科技有限公司 一种固态聚酰胺树脂输送装置
CN108045977A (zh) * 2017-11-30 2018-05-18 无锡锡东能源科技有限公司 一种料仓匀料装置
CN112960422A (zh) * 2021-02-20 2021-06-15 中国建材国际工程集团有限公司 一种硅砂侧卸接料装置

Similar Documents

Publication Publication Date Title
EP3020664B1 (en) Movable loading machine with twin telescopic boom structure
CN201746133U (zh) 盾构皮带输送机分流器
CN110902405B (zh) 移动式粉料集装箱灌装车
CN106761807B (zh) 一种盾构机连续自动出土方法
CN208790617U (zh) 一种皮带机连续出渣装置
CN101858221B (zh) 适用钻爆施工隧道连续皮带出碴方法及其实施***和设备
CN201427577Y (zh) 底卸式矿车
CN102424278A (zh) 连续转运***及其受料装置
CN204508259U (zh) 单臂架带缓冲仓结构的移动式散料装车***
CN102145816B (zh) 一种散料搬运***的工艺及设备
CN202063155U (zh) 矿井空车平移换道装置
CN201932717U (zh) 一种散料搬运设备
CN201095529Y (zh) 大运量重型板式给料机
CN201201797Y (zh) 一种双向运输胶带输送机
CN105173673A (zh) 渣土场胶带机多向转料及消除机头盲区排土工艺
CN202245365U (zh) 链斗式取料机
CN205662108U (zh) 一种轮胎式移动连续给料装置
CN203877472U (zh) 皮带机转载点v型缓冲溜槽
CN202520309U (zh) 掘进机平行快速锚杆支护作业装置
CN112943237A (zh) 一种自动化水力切块煤巷掘进台车
CN2892751Y (zh) 井下巷道矸石充填综合输送机
CN202022540U (zh) 刮板机轨道
CN204919235U (zh) 煤矿用两轨距组合窄轨铁路道岔
WO2013033887A1 (zh) 连续转运***及其受料装置
CN103723502A (zh) 移动式可调量散状物料卸料***

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA RAILWAY MANUFACTURING EQUIPMENT GROUP CO., L

Free format text: FORMER NAME: CHINA RAILWAY TUNNELING EQUIPMENT CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 450016, Henan, Zhengzhou Province, 1405 East navigation road, CITIC Plaza, 4 floor, East

Patentee after: China Railway Manufacturing Equipment Group Co., Ltd.

Address before: 450016, Henan, Zhengzhou Province, 1405 East navigation road, CITIC Plaza, 4 floor, East

Patentee before: China Railway Tunneling Equipment Co., Ltd.

EE01 Entry into force of recordation of patent licensing contract

Assignee: XIAMEN XGMA CHINA RAILWAY HEAVY MACHINERY CO., LTD.

Assignor: China Railway Manufacturing Equipment Group Co., Ltd.

Contract record no.: 2015350000053

Denomination of utility model: Shunt for shielded belt conveyor

Granted publication date: 20110216

License type: Exclusive License

Record date: 20150624

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110216