CN201649654U - Discharging platform for high-rise building construction - Google Patents

Discharging platform for high-rise building construction Download PDF

Info

Publication number
CN201649654U
CN201649654U CN 201020000103 CN201020000103U CN201649654U CN 201649654 U CN201649654 U CN 201649654U CN 201020000103 CN201020000103 CN 201020000103 CN 201020000103 U CN201020000103 U CN 201020000103U CN 201649654 U CN201649654 U CN 201649654U
Authority
CN
China
Prior art keywords
discharging platform
floor
side bar
bottom plate
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201020000103
Other languages
Chinese (zh)
Inventor
石太林
刘斌
何武艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU JIANGZHONG GROUP CO Ltd
Original Assignee
JIANGSU JIANGZHONG GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU JIANGZHONG GROUP CO Ltd filed Critical JIANGSU JIANGZHONG GROUP CO Ltd
Priority to CN 201020000103 priority Critical patent/CN201649654U/en
Application granted granted Critical
Publication of CN201649654U publication Critical patent/CN201649654U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to a discharging platform for high-rise building construction. The discharging platform comprises upper and lower floor concrete edge beams arranged opposite and a bottom plate welded by channel steel. The discharging platform has the innovation points that: the bottom plate is arranged on the outer side of the lower floor concrete edge beam and welded and fixed with steel bar bolts in the lower floor concrete edge beam; and the upper floor concrete edge beam is provided with a steel wire rope for hanging the bottom plate. The discharging platform has the advantages that: the bottom plate extending out of the floor edge beam is arranged outside the building floor which needs to convey a material, and a hanging basket loaded with the material can be directly placed on the bottom plate and then conveyed to the floor by constructors when a crane conveys the material, so the danger that the constructors are taken out of the building is not caused. The discharging platform with the structure has simple structure, can be flexibly arranged on the outer side of each floor, and can be continuously recycled after detachment.

Description

A kind of high-building construction discharging platform
Technical field
The utility model relates to a kind of high-building construction discharging platform, comprises upper and lower floor concrete side bar of arranging relatively and the base plate of being made by the channel-section steel welding.
Background technology
In building operations, building material need be transported to corresponding floor and construct, traditional method is to adopt the hanging basket that crane will be equipped with material to deliver to outside the corresponding floor, pull into hanging basket in the building by the constructor after, meanwhile, the operating personnel of crane control hanging basket and put down.It exists shortcoming to be: the operating personnel of crane must draw in hanging basket the constructor and put down hanging basket in a flash in the building, otherwise the constructor easily brings to outside the floor by the hanging basket of return, cause the accident.Also have some units in charge of construction to adopt vertical lift wells to transport material, but the position of vertical lift well is more fixing, can't cloth and the whole floor of building, there is certain limitation.
The utility model content
The technical problems to be solved in the utility model provides a kind of high-building construction discharging platform that can install and use and have the higher-security energy at each floor.
For solving the problems of the technologies described above, the technical solution of the utility model is: a kind of high-building construction discharging platform, comprise upper and lower floor concrete side bar of arranging relatively and the base plate of making by the channel-section steel welding, its innovative point is: all be embedded with the reinforcing bar bolt in the concrete side bar of described upper and lower floor, described base plate is located at down the concrete side bar outside of floor, and fixing with the reinforcing bar bolt welding in the layer concrete side bar of going downstairs; The described interior pre-buried reinforcing bar bolt end of concrete side bar of going up floor is an annular, and this steel hoop bolt hangs the outer end and the middle part of base plate respectively by wire rope.
Further, three limits away from side bar all are welded with guardrail on the described base plate.
Further, close order safety net is installed on the described guardrail.
Advantage of the present utility model is: by setting up the base plate that stretches out the floor side bar outside the floor that need transport material at building; when crane transports material; can directly the hanging basket that material is housed be placed on the base plate; transport back in the floor by the constructor again; the danger that the constructor is taken out of building can not appear; guardrail and close order safety net can the better protect constructor safety, improved safety factor.Adopt the discharging platform of this kind structure, simple in structure, can be set up in each floor outside flexibly, and can continue turnover after removing and use.
Description of drawings
Accompanying drawing is the structural representation of the utility model high-building construction discharging platform preferred embodiment.
The specific embodiment
As shown in drawings, the utility model relates to a kind of high-building construction discharging platform, comprises reinforcing bar bolt 1, reinforcing bar bolt 2, base plate 3, wire rope 4, wire rope 5, guardrail 6.
Be embedded with reinforcing bar bolt 1 and reinforcing bar bolt 2 respectively in the above-mentioned upper and lower floor concrete side bar of arranging relatively, described base plate 3 is made by the channel-section steel welding, the upper surface is covered with wooden scaffold floor, this base plate 3 is located at the outside of layer concrete side bar downstairs, and is fixing near an end and 2 welding of the reinforcing bar bolt in the side bar of side bar.Upstairs reinforcing bar bolt 1 end in the layer concrete side bar is an annular, is tied with the outer end that hangs base plate 3 respectively and the wire rope 4,5 at middle part on it.All be welded with guardrail 6 on three limits away from side bar on the base plate 3, and close order safety net is being installed on guardrail 6, can guarantee constructor's safety.

Claims (3)

1. high-building construction discharging platform, comprise upper and lower floor concrete side bar of arranging relatively and the base plate of making by the channel-section steel welding, it is characterized in that: all be embedded with the reinforcing bar bolt in the concrete side bar of described upper and lower floor, described base plate is located at down the concrete side bar outside of floor, and fixing with the reinforcing bar bolt welding in the layer concrete side bar of going downstairs; The described interior pre-buried reinforcing bar bolt end of concrete side bar of going up floor is an annular, and this steel hoop bolt hangs the outer end and the middle part of base plate respectively by wire rope.
2. high-building construction discharging platform according to claim 1 is characterized in that: three limits away from side bar on the described base plate all are welded with guardrail.
3. high-building construction discharging platform according to claim 1 is characterized in that: close order safety net is installed on the described guardrail.
CN 201020000103 2010-01-04 2010-01-04 Discharging platform for high-rise building construction Expired - Fee Related CN201649654U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201020000103 CN201649654U (en) 2010-01-04 2010-01-04 Discharging platform for high-rise building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201020000103 CN201649654U (en) 2010-01-04 2010-01-04 Discharging platform for high-rise building construction

Publications (1)

Publication Number Publication Date
CN201649654U true CN201649654U (en) 2010-11-24

Family

ID=43114883

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201020000103 Expired - Fee Related CN201649654U (en) 2010-01-04 2010-01-04 Discharging platform for high-rise building construction

Country Status (1)

Country Link
CN (1) CN201649654U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720360A (en) * 2011-05-19 2012-10-10 陈永生 Combination device of secondary high building supported lifted and poured cement formwork and building material lifting and lifting box
CN103993728A (en) * 2014-05-05 2014-08-20 泰兴市第一建筑安装工程有限公司 Assembly-type section steel cantilever protective shed
CN105178681A (en) * 2015-09-07 2015-12-23 国网河南新安县供电公司 Temporary worktable for steel tube tower
CN105756334A (en) * 2016-04-22 2016-07-13 成都市第七建筑工程公司 High-rise building shape steel cantilever scaffold and unloading platform deflection safety monitoring pre-warning device and pre-warning method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102720360A (en) * 2011-05-19 2012-10-10 陈永生 Combination device of secondary high building supported lifted and poured cement formwork and building material lifting and lifting box
CN102720360B (en) * 2011-05-19 2015-04-01 陈永生 Combination device of secondary high building supported lifted and poured cement formwork and building material lifting and lifting box
CN103993728A (en) * 2014-05-05 2014-08-20 泰兴市第一建筑安装工程有限公司 Assembly-type section steel cantilever protective shed
CN103993728B (en) * 2014-05-05 2015-11-25 泰兴市第一建筑安装工程有限公司 A kind of assembling shaped steel is encorbelmented protection canopy
CN105178681A (en) * 2015-09-07 2015-12-23 国网河南新安县供电公司 Temporary worktable for steel tube tower
CN105756334A (en) * 2016-04-22 2016-07-13 成都市第七建筑工程公司 High-rise building shape steel cantilever scaffold and unloading platform deflection safety monitoring pre-warning device and pre-warning method thereof

Similar Documents

Publication Publication Date Title
CN103086279B (en) Vertical transportation construction method for building construction
CN205955236U (en) Container formula of taking pulley platform of unloading of encorbelmenting
CN103015782A (en) Construction platform and construction method for integrating silo roof and silo wall slip form
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN201649654U (en) Discharging platform for high-rise building construction
CN201334769Y (en) Attached type lifting scaffold with double guide rails
CN205557951U (en) Novel local cast -in -place assembled coincide building roof boarding
CN205328487U (en) Dismantlement system of superelevation extra -large -size tower crane
CN202483180U (en) Movable building material loading and unloading platform
CN202359510U (en) Multi-functional working vehicle for concrete anti-collision guardrail of bridge
CN102392532B (en) Construction method for built-in hanging scaffold of high-rise building
CN206554524U (en) A kind of construction discharging platform
CN107060474A (en) A kind of sleeve-type chimney people goods shunting vertical transferring apparatus and construction method
CN103982046A (en) Lifting and installation method of buckling restrained braces
CN217461535U (en) Overhanging type discharging platform for high-rise building
CN205500636U (en) Water conservancy project component handling device
CN207296361U (en) A kind of regularization assembled overhanging protection canopy
CN105863280B (en) A kind of discharging platform that can be voluntarily lifted
CN205116685U (en) Can dismantle shaped steel of encorbelmenting platform of unloading
CN202390077U (en) Lifting appliance for conveying tower crane
CN107630583B (en) It is a kind of to hang steel pipe truss construction method with Bailey bracket is counter
CN205894715U (en) Light steel structure is semi -automatic under enclosed construction constructs from hoisting machine that climbs
CN105155832B (en) A kind of hanging basket equipment and its moving method
CN204112692U (en) Simple and easy lift-type wellbore operations platform
CN205531262U (en) Steel construction construction platform can rise automatically

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101124

Termination date: 20140104