CN201517208U - Adjustable connection node for fan foundation steel pile and conversion steel structure - Google Patents

Adjustable connection node for fan foundation steel pile and conversion steel structure Download PDF

Info

Publication number
CN201517208U
CN201517208U CN2009202114622U CN200920211462U CN201517208U CN 201517208 U CN201517208 U CN 201517208U CN 2009202114622 U CN2009202114622 U CN 2009202114622U CN 200920211462 U CN200920211462 U CN 200920211462U CN 201517208 U CN201517208 U CN 201517208U
Authority
CN
China
Prior art keywords
steel
conversion
pipe pile
pile
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202114622U
Other languages
Chinese (zh)
Inventor
孙绪东
李先林
路志浩
李峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baogang Engineering Technology Co Ltd
Original Assignee
Shanghai Baogang Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baogang Engineering Technology Co Ltd filed Critical Shanghai Baogang Engineering Technology Co Ltd
Priority to CN2009202114622U priority Critical patent/CN201517208U/en
Application granted granted Critical
Publication of CN201517208U publication Critical patent/CN201517208U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to an adjustable connection node for fan foundation steel pile and conversion steel structure, which comprises a steel tube pile, a fan foundation conversion steel structure, a fixed sleeve ring and a bracket, a short post of the foundation conversion steel structure is inserted into the steel tube pile from the top of the steel tube pile to form an internal sleeve type connection, the fixed sleeve ring is sleeved on the short post, meanwhile, the fixed sleeve ring is welded together with the short post and the steel tube pile bracket. The steel tube pile is connected with the fan foundation conversion steel structure by the short post. The utility model has advantages that the conversion steel structure is connected with the steel tube pile by the connection node of the utility model, the formed space can be adjusted in three directions, the utility model can be adapted to the construction error of the pile, the node adjustable target can be implemented when in field installation, and the field connection requirement can be satisfied; the field welding work amount is small, the mounting is convenient, the speed is fast, and the node applied force is safe and reliable.

Description

A kind of blower foundation piling bar and connected node regulated of changing steel work of being used for
Technical field
The utility model relates to wind generator facility, particularly a kind of blower foundation piling bar and connected node regulated of changing steel work of being used for.
Background technology
Wind-power electricity generation is a green energy resource technology with fastest developing speed in the world, landwid electric field build fast-developing in, it has been observed that some restrictions that the land Wind Power Utilization is suffered, problems such as, noise pollution big as floor space.Oversea wind aboundresources, Oversea wind power generation are influenced by noise, birds and the less-restrictive of problem such as Electromagnetic Interference, and it does not take land land resources, does not relate to problems such as land acquisition.Have, the variation of marine wind speed with altitude is less again, does not therefore need to set up very high support tower, thereby can reduce the cost of offshore wind generating group.Also have, marine turbulence intensity is low, and sea level frictional force is less, and the fatigue load that acts on the wind power generating set reduces, thereby can prolong the application life of wind-powered electricity generation unit.
Because above plurality of advantages, the ocean will become a wind-power market that develops rapidly.Deposits in Eastern Coastal China depth of water 50m is vast with interior oceanic area, and it is very near apart from power load center (the flourishing power shortages of coastal economy district), full-fledged along with the offshore wind farm field technology, wind-powered electricity generation will become the important energy source source of Deposits in Eastern Coastal China area sustainable development.
Build the blower fan unit in east China shallow sea and intertidal zone, its base form has many difficulties if adopt existing pile foundation to add the concrete bearing platform mode: it is high that concrete is difficult for being transported to scene, long construction period, operating expenses height, comprehensive cost.In view of this, the base form that adopts many steel pipe piles to add to change steel work can overcome above-mentioned deficiency.The conversion steel work can be at produce in factory, be transported to the building site again, be connected with stake, so that this kind foundational system has is simple for production, transportation, easy for installation, difficulty of construction is low, the field Welding amount is little, and speed of application is fast, short construction period, be convenient to boisterous off time of construction at sea, advantage such as comprehensive benefit is good.But because can there be the deviation of plane and short transverse in stake after the construction at the scene, adopt the connection joints of steel structure form of bolt usually, very high to required precision, therefore can't adapt to the construction error of stake, can not satisfy connection request herein.If adopt field Welding to adapt to construction error, field condition then can't guarantee welding quality, can bring serious quality problems thus.
The utility model content
Task of the present utility model provides a kind of blower foundation piling bar and connected node regulated of changing steel work of being used for, it has solved a series of problems of above-mentioned existing in prior technology, blower foundation conversion steel work is connected with steel pipe pile by short column, and its connected node can be regulated.
Technical solution of the present utility model is as follows:
A kind of blower foundation piling bar and connected node regulated of changing steel work of being used for, it comprises steel pipe pile, blower foundation conversion steel work, it also comprises retaining collar and rest, the short column of basis conversion steel work inserts from the steel pipe pile top and forms the inner cased type connection in the steel pipe pile, retaining collar then is set on the short column, and retaining collar and short column and steel pipe pile rest weld together simultaneously;
Described steel pipe pile is connected with blower foundation conversion steel work by short column.
Perfusion high strength grout in the space between described short column and the steel pipe pile.
A kind of blower foundation piling bar that is used for of the present utility model has following major advantage with the connected node regulated of changing steel work:
1, the conversion steel work is connected with steel pipe pile by the utility model connected node, and the space three-dimensional can be regulated, and can adapt to the construction error of stake, and the adjustable program mark of node satisfies on-the-spot connection request when realizing on-the-spot the installation.
2, the field Welding workload is little, and is easy for installation, and speed is fast.
3, node is stressed safe and reliable.
Description of drawings
Accompanying drawing is a kind of structural representation that is used for the connected node regulated of blower foundation piling bar and conversion steel work of the present utility model.
Number in the figure:
1 is steel pipe pile, 2 short columns for blower foundation conversion steel work, and 3 is retaining collar, 4 is steel pipe pile interior lining panel and stiffener, and 5 is short column base plate and stiffener, and 6 is the level adjusting gap between short column 2 and the steel pipe pile 1, irritate high strength grout, 7 is the rest at steel pipe pile top.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is elaborated.
Referring to accompanying drawing, the utility model is a kind of blower foundation piling bar and connected node regulated of changing steel work of being used for, and the blower foundation piling bar can be a steel pipe pile 1, and steel pipe pile 1 is the ordinary steel pile tube, can be box section, round tube or polygon pipe; Steel pipe pile 1 also can be steel tube concrete pile.
Short column 2 inserts from steel pipe pile 1 top and forms the inner cased type connection in the steel pipe pile 1.3 of retaining collars are set on the short column 2, and are movable.After finish location to be connected, retaining collar 3 is welded with short column 2 and the rest 7 that is fixed in steel pipe pile 1 top respectively.
Steel pipe pile 1 is connected with blower foundation conversion steel work by short column 2.Be provided with gap 6 in level and short transverse between short column 2 and the steel pipe pile 1, regulate, adapt to the site operation error of steel pipe pile 1 with the space three-dimensional that realizes connected node.The size in gap can be determined according to the regulated quantity that reality requires.
After blower foundation conversion steel work was in place, three-dimensional was adjusted to design attitude, and is fixing, pours into high strength grout in the space 6 between short column 2 and steel pipe pile 1, and this space is filled up, and realizes the location of conversion steel work, and connection is finished in final welding.
As shown in FIG., be provided with base plate and stiffener 5, in steel pipe pile 1, be provided with liner plate and stiffener 4, in order to strengthen its strength and stiffness in short column 2 bottoms.
The utility model has been realized the blower foundation piling bar and has been changed being connected of steel work, and its connected node can be regulated.
Certainly, those skilled in the art in the present technique field will be appreciated that, the foregoing description only is to be used for illustrating the utility model, and be not with opposing qualification of the present utility model, as long as in connotation scope of the present utility model, all will drop in the scope of the utility model claim conversion, the modification of the foregoing description.

Claims (2)

1. one kind is used for blower foundation piling bar and the connected node regulated of changing steel work, it comprises steel pipe pile, blower foundation conversion steel work, it is characterized in that, it also comprises retaining collar and rest, the short column of basis conversion steel work inserts from the steel pipe pile top and forms the inner cased type connection in the steel pipe pile, retaining collar then is set on the short column, and retaining collar and short column and steel pipe pile rest weld together simultaneously;
Described steel pipe pile is connected with blower foundation conversion steel work by short column.
2. blower foundation piling bar and the connected node regulated of changing steel work of being used for according to claim 1 is characterized in that, perfusion high strength grout in the space between described short column and the steel pipe pile.
CN2009202114622U 2009-10-29 2009-10-29 Adjustable connection node for fan foundation steel pile and conversion steel structure Expired - Fee Related CN201517208U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202114622U CN201517208U (en) 2009-10-29 2009-10-29 Adjustable connection node for fan foundation steel pile and conversion steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202114622U CN201517208U (en) 2009-10-29 2009-10-29 Adjustable connection node for fan foundation steel pile and conversion steel structure

Publications (1)

Publication Number Publication Date
CN201517208U true CN201517208U (en) 2010-06-30

Family

ID=42497929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202114622U Expired - Fee Related CN201517208U (en) 2009-10-29 2009-10-29 Adjustable connection node for fan foundation steel pile and conversion steel structure

Country Status (1)

Country Link
CN (1) CN201517208U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733410A (en) * 2012-07-18 2012-10-17 中国水电顾问集团中南勘测设计研究院 Jacket wind turbine foundation connecting piece
CN105064395A (en) * 2015-09-06 2015-11-18 中国能源建设集团广东省电力设计研究院有限公司 Offshore wind turbine foundation and construction mechanism thereof
CN106368233A (en) * 2015-07-24 2017-02-01 中国能源建设集团广东省电力设计研究院有限公司 Offshore fan supporting structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733410A (en) * 2012-07-18 2012-10-17 中国水电顾问集团中南勘测设计研究院 Jacket wind turbine foundation connecting piece
CN106368233A (en) * 2015-07-24 2017-02-01 中国能源建设集团广东省电力设计研究院有限公司 Offshore fan supporting structure and construction method thereof
CN105064395A (en) * 2015-09-06 2015-11-18 中国能源建设集团广东省电力设计研究院有限公司 Offshore wind turbine foundation and construction mechanism thereof

Similar Documents

Publication Publication Date Title
Sun et al. The current state of offshore wind energy technology development
CN201649118U (en) Foundation structure of jacket-type offshore wind turbine
CN105297765B (en) A kind of marine wind electric field fan combined type rock-socketed pile foundation and its construction method
CN205152976U (en) Marine precast concrete cushion cap wind turbine foundation
KR101318111B1 (en) Substructure of hybrid offshore wind turbine with multi-pile for reducing wave forces, and constructing method for the same
CN202732247U (en) Trussed type offshore wind generating set base structure
CN202323978U (en) Base components for offshore wind power set installation
CN102777333A (en) Truss structure of wind turbine generator set
CN201526424U (en) Single pile type foundation structure of offshore wind driven generator
CN202295236U (en) Floating-type offshore wind power platform
CN110453714B (en) Offshore wind power jacket gravity type cylindrical foundation structure and construction method thereof
CN103938644A (en) Prefabricated concrete bearing platform with reserved pile nest holes and fabricated multi-pile foundation installation method based on prefabricated concrete bearing platform with reserved pile nest holes
CN105862907A (en) Annular combination type super-large diameter offshore wind power single pile foundation and construction technology thereof
CN201704699U (en) Steel structure foundation system of offshore fan
CN201952809U (en) Steel truss type offshore anemometer tower foundation structure
CN201502064U (en) Offshore wind turbine steel structural foundation
CN202416341U (en) Steel truss automatically-standing seaborne anemometer tower
CN201517208U (en) Adjustable connection node for fan foundation steel pile and conversion steel structure
CN103243732A (en) Installing method of marine anemometer tower base structure
CN103161174A (en) Offshore wind turbine generator set installation fundamental assembly
CN201599157U (en) Offshore wind turbine infrastructure with multi-pile steel framework and without peripheral connecting pipes
CN205116207U (en) Offshore wind farm fan combined type embedded rock pile basis
CN209941726U (en) Offshore wind turbine single pile foundation reinforced pile foundation structure
CN201517216U (en) Adjustable connection node for fan basic steel pile and conversion steel structure
CN202450543U (en) Foundation structure of novel guide frame-type marine anemometer tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100630

Termination date: 20181029