CN201485974U - Plug-in floor steel secondary beam node structure - Google Patents

Plug-in floor steel secondary beam node structure Download PDF

Info

Publication number
CN201485974U
CN201485974U CN200920093964XU CN200920093964U CN201485974U CN 201485974 U CN201485974 U CN 201485974U CN 200920093964X U CN200920093964X U CN 200920093964XU CN 200920093964 U CN200920093964 U CN 200920093964U CN 201485974 U CN201485974 U CN 201485974U
Authority
CN
China
Prior art keywords
steel secondary
secondary beam
plug
node structure
flooring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN200920093964XU
Other languages
Chinese (zh)
Inventor
肖野
李炳益
龙建
杨眉
蒋家宏
陆洲导
余江涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeast Electric Power Design Institute of China Power Engineering Consulting Group filed Critical Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN200920093964XU priority Critical patent/CN201485974U/en
Application granted granted Critical
Publication of CN201485974U publication Critical patent/CN201485974U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a plug-in floor steel secondary beam node structure which comprises framework concrete beams and floor steel secondary beams; and the plug-in floor steel secondary beam node structure is characterized in that the floor steel secondary beams are spliced into the framework concrete beams. The utility model has the advantages that the serving time of the framework concrete beams is saved, thereby greatly improving the construction progress; the factory space is increased, thereby facilitating the arrangement of the process pipeline equipment; and the lifting lugs or embedded parts for the framework concrete beams are eliminated, therefore, the plug-in floor steel secondary beam node structure is better in economical efficiency and more beautiful in appearance.

Description

Plug-in type flooring steel secondary beam node structure
Technical field
The utility model belongs to thermal power generation power plant civil engineering structure design field, especially relates to a kind of combination flooring plug-in type steel secondary beam node structure.
Background technology
Because process pipe and equipment are more, and load is bigger, and it is reinforced concrete frame that the main building structure adopts main frame mostly, each floor face adopts girder steel to cast board combining structure in the main building of steam power station.Each floor face steel secondary beam is connected with the concrete frame concrete beam and all adopts pure being articulated and connected, way has two kinds of ways usually: a kind of mode is that the steel secondary beam directly is bearing in the girder side and chooses on the ear, another kind of mode is to reserve embedded part in the girder side, steel secondary beam and the welding of girder side embedded part.
First kind directly is bearing in the connected mode advantage of choosing on the ear is stressed comparatively clear and definite, owing to use for many years on the main building flooring of steam power station, technology is ripe, and related specifications and handbook all have theoretical the support; Shortcoming is that the installation of flooring steel secondary beam must be waited until after the main frame concrete reaches design strength and just can carry out, and takes 28 days usually and the main frame concrete reaches design strength, has influenced construction period greatly; Because floor load is bigger, and it is also very big usually to choose ear, and the girder side is chosen ear and taken the factory building space, influences process pipe and arrange in addition, and uneconomical, not attractive in appearance.
The form of second kind of steel secondary beam and the welding of girder side embedded part is same, and technology is comparative maturity also owing to use for many years on the main building flooring of steam power station, and related specifications and handbook all have theoretical the support; Its shortcoming is that the installation of flooring steel secondary beam must be waited until after the main frame concrete reaches design strength and just can carry out equally, the construction period lengthening; Beam side embedded part is more and bigger in addition, and construction blanking difficulty is relatively large.
The utility model content
Technical problem to be solved in the utility model provides and a kind ofly saves construction period, guarantees structural safety, reduces the factory building space, overall cost is low, the combination flooring plug-in type steel secondary beam joint structure of good looking appearance.
For solving the problems of the technologies described above, the utility model provides a kind of plug-in type flooring steel secondary beam node structure, comprises frame concrete beam, flooring steel secondary beam, and it is characterized in that: flooring steel secondary beam is plugged in the frame concrete beam.
Flooring steel time web has preformed hole, and the vertical muscle of the framework in the frame concrete beam passes the preformed hole on the flooring steel time web.
In order to satisfy the die-cut requirement of flooring steel secondary beam, be provided with below the flooring steel secondary beam in the frame concrete beam and hang muscle.
In order to satisfy flooring steel secondary beam anchoring requirement, according to flooring steel secondary beam and upper load size, flooring steel time beam end is provided with dowel.
The utility model advantage is to have saved frame concrete beam conditioned time, accelerating construction progress greatly; Increase the factory building space, helped the process pipe apparatus arrangement; Save the frame concrete beam and chosen ear or embedded part, better economy, profile is better appearance also.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the sectional view along A-A line among Fig. 1.
The specific embodiment
With reference to Fig. 1,2, frame concrete beam 1 is the cast-in-situ steel reinforced concrete beam, and floor plate 3 is cast-in-situ steel reinforced concrete floorings, and flooring steel secondary beam 2 is a H shaped steel, and flooring steel secondary beam directly inserts in the frame concrete beam, near midline position; Flooring steel time web has preformed hole, the preformed hole that the vertical muscle 4 of frame concrete beam inner frame passes flooring steel time web does not weld with flooring steel secondary beam, in flooring steel secondary beam underframe concrete beam, be provided with and hang muscle 6 and satisfy the die-cut requirement of flooring steel secondary beam, flooring steel time beam end is provided with dowel 5 according to itself and upper load size, satisfies flooring steel secondary beam anchoring requirement.
During building operations, before the frame concrete beam was not built, flooring steel secondary beam directly inserted and forms effective node in the frame concrete beam, treat flooring steel secondary beam installation in position after, re-lay the flooring reinforcing bar, last pouring frame concrete beam and floorslab concrete.

Claims (5)

1. a plug-in type flooring steel secondary beam node structure comprises frame concrete beam, flooring steel secondary beam, and it is characterized in that: flooring steel secondary beam is plugged in the frame concrete beam.
2. plug-in type flooring steel secondary beam node structure according to claim 1 is characterized in that: flooring steel time web has preformed hole, and the vertical muscle of the framework in the frame concrete beam passes the preformed hole on the flooring steel time web.
3. plug-in type flooring steel secondary beam node structure according to claim 1 and 2 is characterized in that: be provided with below the flooring steel secondary beam in the frame concrete beam and hang muscle.
4. plug-in type flooring steel secondary beam node structure according to claim 1 and 2 is characterized in that: flooring steel time beam end is provided with dowel.
5. plug-in type flooring steel secondary beam node structure according to claim 3 is characterized in that: flooring steel time beam end is provided with dowel.
CN200920093964XU 2009-07-08 2009-07-08 Plug-in floor steel secondary beam node structure Expired - Lifetime CN201485974U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920093964XU CN201485974U (en) 2009-07-08 2009-07-08 Plug-in floor steel secondary beam node structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920093964XU CN201485974U (en) 2009-07-08 2009-07-08 Plug-in floor steel secondary beam node structure

Publications (1)

Publication Number Publication Date
CN201485974U true CN201485974U (en) 2010-05-26

Family

ID=42424859

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920093964XU Expired - Lifetime CN201485974U (en) 2009-07-08 2009-07-08 Plug-in floor steel secondary beam node structure

Country Status (1)

Country Link
CN (1) CN201485974U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733419A (en) * 2012-04-01 2012-10-17 中国水电顾问集团贵阳勘测设计研究院 Supporting structure of underground plant floor slab and construction method
CN105133729A (en) * 2015-08-05 2015-12-09 北京建工华创科技发展股份有限公司 Abnormity beam column steel frame with sandwich board and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102733419A (en) * 2012-04-01 2012-10-17 中国水电顾问集团贵阳勘测设计研究院 Supporting structure of underground plant floor slab and construction method
CN105133729A (en) * 2015-08-05 2015-12-09 北京建工华创科技发展股份有限公司 Abnormity beam column steel frame with sandwich board and construction method thereof

Similar Documents

Publication Publication Date Title
CN201635388U (en) Cast-in-place concrete arc outer wall body unilateral formwork system
CN102926504B (en) Construction method of steel and concrete overlapped beam combined part
CN205242848U (en) Adopt prefabricated assembled steel - concrete combination beam of high strength bolt connection
CN101906754B (en) Rigid connection method for steel beam and concrete pier
CN203307961U (en) Profiled steel embedded column precast concrete double-slab shear wall structure
CN109295994B (en) Full-assembly type wind power tower cylinder foundation with combined structure
CN107217787A (en) A kind of assembled coupling beam of built-in profiled sheet groove structure
CN211572019U (en) Box shaped steel concrete column and concrete beam connected node
CN201485974U (en) Plug-in floor steel secondary beam node structure
CN105220792A (en) A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof
CN108756038A (en) Assembly concrete shear wall and floor support plate rigid connection node and construction method
CN204098221U (en) A kind of prefabricated primary-secondary beam connected node comprising T-shaped anti-shear steel plate
CN202831392U (en) Connecting steel component for joint part of steel reinforced concrete laminated beams
CN202466913U (en) Concrete overlapping plate connected by 180 DEG bent reinforcing steel anchor within span
CN205206112U (en) Novel three -dimensional steel bar truss building carrier plate
CN111119026B (en) Assembled steel-concrete combined structure for reinforcing long-span box type arch bridge
CN210597875U (en) Cross beam
CN210857609U (en) Steel plate concrete frame shear structure
CN209975863U (en) Section steel ultra-light concrete member
CN216766287U (en) Concrete beam and steel column connection structure
CN202055259U (en) Foundation bolt preformed hole structure for equipment
CN210947797U (en) Novel deviation is prevented to prefabricated balcony board device
CN216075233U (en) Membrane shell shear wall for connecting station platen and truss floor bearing plate
CN209817179U (en) Prefabricated assembled shear wall structure
CN216476314U (en) Assembly type formwork system of cast-in-place plate of steel structure building

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA POWER ENGINEERING CONSULTING GROUP NORTHEAST

Free format text: FORMER NAME: NORTHEASTERN ELECTRIC POWER DESIGN INSTITUTE, CHINA POWER ENGINEERING CONSULTING GROUP CORPORATION

CP01 Change in the name or title of a patent holder

Address after: 130021 Jilin City, Changchun province people's street, No. 4368

Patentee after: Co., Ltd of Northeastern Electric Power Design Institute, China Power Engineering Consulting Group Corporation

Address before: 130021 Jilin City, Changchun province people's street, No. 4368

Patentee before: Northeastern Electric Power Design Institute, China Power Engineering Consulting Group Corporation

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20100526