CN201485204U - Gas tank hanging device - Google Patents

Gas tank hanging device Download PDF

Info

Publication number
CN201485204U
CN201485204U CN2009201767710U CN200920176771U CN201485204U CN 201485204 U CN201485204 U CN 201485204U CN 2009201767710 U CN2009201767710 U CN 2009201767710U CN 200920176771 U CN200920176771 U CN 200920176771U CN 201485204 U CN201485204 U CN 201485204U
Authority
CN
China
Prior art keywords
gas chamber
walking dolly
hanging apparatus
mast
walking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009201767710U
Other languages
Chinese (zh)
Inventor
张道华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
MCC CHENGGONG CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC CHENGGONG CONSTRUCTION CO Ltd filed Critical MCC CHENGGONG CONSTRUCTION CO Ltd
Priority to CN2009201767710U priority Critical patent/CN201485204U/en
Application granted granted Critical
Publication of CN201485204U publication Critical patent/CN201485204U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a gas tank hanging device, which belongs to building mounting equipment and resolves problems that the mounting equipment in the prior art is easy to be limited by construction occasions and is over high in construction cost. The gas tank hanging device comprises a travelling trolley, a backstay, a supporting frame, a pulling rope and a hoister, the supporting frame is fixed on the travelling trolley, the backstay is movably connected to one edge of the travelling trolley, the hoister is arranged on the travelling trolley, and one end of the pulling rope is connected with the hoister after penetrating through the top end of the backstay and the top end of the supporting frame while the other end is suspended. The gas tank hanging device is simple in structure, convenient in assembling and disassembling and high in construction operation technical requirements, greatly reduces construction cost compared with the prior art, and has extremely high practical value and popularization value.

Description

The gas chamber hanging apparatus
Technical field
The utility model relates to a kind of building and installation device, specifically, relates to a kind of hanging apparatus of large-scale gas chamber.
Background technology
Dry gas holder is a kind of of gas chamber, is applied to a lot of construction sites, and according to the difference of construction requirement, the specification size of dry gas holder also has nothing in common with each other.Dry gas holder erecting device commonly used is crane or tower crane, but, the mounting tools of this routine only is applicable to the gas chamber that specification is less, highly lower, for large-scale dry gas holder, the dry gas holder of height more than 80m particularly, crane commonly used or tower crane are difficult to finish its installation task because of insufficient height.The more important thing is, the use of crane or tower crane can be subjected to the restriction in place, camp site, if tower crane can not be installed in the camp site, perhaps can not use the crane construction, the installation of gas chamber just can't be implemented so, and adopt the construction cost of crane or tower crane very high, the construction cost of average every day even can reach more than 20,000, the installation of a large-scale dry gas holder usually needed one month even the longer time, adopting tower crane or crane to construct resulting cost like this may be up to hundreds thousand of, this does not just meet the interests of construction party fully, and therefore, adopting new erecting device is the inevitable choice that dry gas holder is installed.
The utility model content
The purpose of this utility model is to provide a kind of gas chamber hanging apparatus, solves problems of the prior art, when realizing that gas chamber is installed, avoids the influence of workyard, and reduces construction cost.
To achieve these goals, the technical solution adopted in the utility model is as follows:
The gas chamber hanging apparatus, comprise walking dolly, mast, bracing frame, stay cord and winch, support frame as described above is fixed on the walking dolly, mast is movably connected on the limit of walking dolly, winch is installed on the walking dolly, stay cord one end is connected with winch after passing mast top, bracing frame top, and the other end is unsettled.
The bottom that described mast quantity is 2, two masts is installed on the two ends on a limit of walking dolly respectively, and the top is interconnected in a bit.
Support frame as described above is made up of four strut bars, and the bottom of four strut bars is individually fixed on four angles of walking dolly, and the top is interconnected in a bit.
Described gas chamber hanging apparatus also is provided with the walking track supporting with walking dolly, and described walking track is fixedly installed on the gas chamber top board.
Described walking track is around one week of gas chamber top board edge, and walking dolly moves on the walking track, realizes the installation of the structural constituent of each side of gas chamber.
Also be provided with the electrical motor that the control walking dolly moves on the described walking dolly.
Described winch quantity is 2.
The unsettled end of described stay cord is provided with the suspension hook that is used to hang the gas chamber structural constituent.
Described gas chamber top board is provided with at least one mast and hangs, and concrete quantity can be provided with according to actual needs, in general, two masts is set hangs enough most of construction demands.
The utility model utilizes hydraulic jacking device drive gas chamber top board controlledly to rise, after each gas chamber top board rises end, the hanging apparatus that use is installed on the gas chamber top board is hung each structural constituent of gas chamber, successively finishes installation according to order from bottom to up.
Compared with prior art, the beneficial effects of the utility model are:
One. the utility model mainly adopts mast to lift up into the row construction, and mast hangs and is installed on the gas chamber top board, and therefore the outer place of occupying volume, is not influenced by the workyard.
Two. construction cost of the present utility model is only produced by the productive costs that mast hangs, and only need about 20,000 and the cost that mast hangs is general, and a mast hangs the installation that just can finish a dry gas holder, and construction cost reduces greatly.
Three. mast hangs simple in structure, the assembling, the dismounting very convenient, the control of work progress is simple to operation.
The utility model is fit to the installation of the gas chamber of all size, and especially on large-scale gas chamber, advantage is especially obvious.
Description of drawings
Fig. 1 is a scheme of installation of the present utility model.
The corresponding title of label in the accompanying drawing: 1-walking dolly, 2-mast, 3-strut bar, 4-winch, 5-stay cord, 6-electrical motor, the 7-track of walking, 8-suspension hook, 9-gas chamber top board.
The specific embodiment
As shown in Figure 1, the gas chamber hanging apparatus comprises walking dolly 1, two masts 2, bracing frame, stay cord 5 and winchs 4.Support frame as described above is fixed on the walking dolly 1, and the bottom of two masts 2 is movably connected on the two ends on a limit at close gas chamber top board 9 edges of walking dolly 1 respectively, and the top is interconnected in a bit; Winch 4 is installed on the walking dolly 1, and stay cord 5 adopts steel ropes, and the one end is connected with winch 4 after passing mast 2 tops, bracing frame top, and the other end is unsettled hangs a suspension hook 8.Suspension hook 8 is used to hang the structural constituent of gas chamber.
Support frame as described above is made up of four strut bars 3, and the bottom of four strut bars 3 is individually fixed on four angles of walking dolly 1, and the top is interconnected in a bit.
Strut bar 3 and mast 2 are steel pipe.
Described gas chamber hanging apparatus also is provided with the walking track 7 supporting with walking dolly 1, and the shape of walking track 7 is decided according to the shape of gas chamber, is fixedly installed in gas chamber top board 9 edges, and around gas chamber top board one week of 9 edges.Walking dolly 1 moves on walking track 7, realizes the installation of the structural constituent of each side of gas chamber.
Moving of described walking dolly by electrical motor 6 controls.
Described winch 4 quantity are 2.

Claims (8)

1. gas chamber hanging apparatus, it is characterized in that, comprise walking dolly (1), mast (2), bracing frame, stay cord (5) and winch (4), support frame as described above is fixed on the walking dolly (1), mast (2) is movably connected on the limit of walking dolly (1), winch (4) is installed on the walking dolly (1), and stay cord (5) one ends are connected with winch (4) after passing mast (2) top, bracing frame top, and the other end is unsettled.
2. gas chamber hanging apparatus according to claim 1 is characterized in that, described mast (2) quantity is the two ends that the bottom of 2, two masts is installed on (1) limit of walking dolly respectively, and the top is interconnected in a bit.
3. gas chamber hanging apparatus according to claim 1 is characterized in that, support frame as described above is made up of four strut bars (3), and the bottom of four strut bars (3) is individually fixed on four angles of walking dolly (1), and the top is interconnected in a bit.
4. gas chamber hanging apparatus according to claim 1 is characterized in that, described gas chamber hanging apparatus also is provided with and the supporting walking track (7) of walking dolly (1), and described walking track (7) is fixedly installed on the gas chamber top board (9).
5. gas chamber hanging apparatus according to claim 4 is characterized in that, described walking track (7) is around gas chamber top board (9) one week of edge.
6. gas chamber hanging apparatus according to claim 1 is characterized in that, also is provided with the electrical motor (6) that the control walking dolly moves on the described walking dolly (1).
7. gas chamber hanging apparatus according to claim 1 is characterized in that, the unsettled end of described stay cord (5) is provided with the suspension hook (8) that is used to hang the gas chamber structural constituent.
8. gas chamber hanging apparatus according to claim 1 is characterized in that, described gas chamber top board (9) is provided with at least one mast and hangs.
CN2009201767710U 2009-09-15 2009-09-15 Gas tank hanging device Expired - Lifetime CN201485204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201767710U CN201485204U (en) 2009-09-15 2009-09-15 Gas tank hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201767710U CN201485204U (en) 2009-09-15 2009-09-15 Gas tank hanging device

Publications (1)

Publication Number Publication Date
CN201485204U true CN201485204U (en) 2010-05-26

Family

ID=42424094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201767710U Expired - Lifetime CN201485204U (en) 2009-09-15 2009-09-15 Gas tank hanging device

Country Status (1)

Country Link
CN (1) CN201485204U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103274315A (en) * 2013-04-28 2013-09-04 云南建工安装股份有限公司 Installing and hoisting device for side plate and upright of gas chamber
CN107459000A (en) * 2017-08-04 2017-12-12 上海二十冶建设有限公司 Large-scale top of gas cabinet integrated hydraulic method for dismounting

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103274315A (en) * 2013-04-28 2013-09-04 云南建工安装股份有限公司 Installing and hoisting device for side plate and upright of gas chamber
CN103274315B (en) * 2013-04-28 2015-01-28 云南建工安装股份有限公司 Installing and hoisting device for side plate and upright of gas chamber
CN107459000A (en) * 2017-08-04 2017-12-12 上海二十冶建设有限公司 Large-scale top of gas cabinet integrated hydraulic method for dismounting

Similar Documents

Publication Publication Date Title
CN201268937Y (en) Double-layer hanging cradle for working aloft
CN201864516U (en) Lifting appliance special for overhauling isolating switch
CN202299574U (en) Plug-in type communication base station lifting tower
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN201793330U (en) Gantry hanger frame device
CN201215876Y (en) Assistant hanging rack for mounting top rack of electric pole
CN201485204U (en) Gas tank hanging device
CN101660660B (en) Novel installing method of gas cabinet
CN201321352Y (en) Special lifting device for electrical equipment
CN205077842U (en) Multi -use architecture support
CN201952153U (en) Portable detachable hoisting equipment
CN105016220A (en) Holding rod joint adding device
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN204980945U (en) Supplementary tower crane dismounting device
CN2839223Y (en) The construction lifting appliance in floor type steel structure circle storehouse
CN201660377U (en) Special gantry crane for overlength and large-tonnage parts
CN204198306U (en) A kind of device for purlin lifting in building operation
CN203878957U (en) Protective screen module unit
CN206188299U (en) Dedicated assembled handling instrument of fan cabin internal
CN201261681Y (en) Sling for mounting RH furnace circulating pipe
CN205973588U (en) Simple and easy immersible pump hoisting device
CN201381196Y (en) Light hanging bracket
CN204848024U (en) Girder steel hoist device for construction
CN218668451U (en) Hanging basket for high-altitude auxiliary installation of aluminum plate
CN204324748U (en) A kind of large-scale gas storage holder Steel Structure Installation hoisting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: China MCC5 Group Corp., Ltd.

Assignor: MCC Chenggong Construction Co., Ltd.

Contract record no.: 2010510000035

Denomination of utility model: Gas tank hanging device

Granted publication date: 20100526

License type: Exclusive License

Record date: 20100611

ASS Succession or assignment of patent right

Owner name: CHINA NO.5 METALLURGICAL GROUP CO., LTD.

Free format text: FORMER OWNER: MCC CHENGGONG CONSTRUCTION CO., LTD.

Effective date: 20100910

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 610082 NO.8, SECTION 1 OF RENMIN NORTH ROAD, CHENGDU CITY, SICHUAN PROVINCE TO: 610063 CHINA NO.5 METALLURGICAL GROUP CO., LTD., INDUSTRIAL PARK, JINJIANG DISTRICT, CHENGDU CITY, SICHUANG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20100910

Address after: Jinjiang District Industrial Park in Chengdu city in Sichuan province 610063 Chinese Wuye Group Co. Ltd.

Patentee after: China MCC5 Group Corp., Ltd.

Address before: 610082 section 8, Renmin North Road, Sichuan, Chengdu

Patentee before: MCC Chenggong Construction Co., Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20100526